Mawson Infrastructure Group Inc
For the period ended Mar 31, 2024. Filed May 15, 2024.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Mar 31, 2024 · Filed May 15, 2024
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Legal Proceedings
We have been made a defendant in certain legal proceedings which may have in the future or have had in the recent past significant effects on our financial position or profitability. On July 13, 2022, Celsius Mining LLC and Celsius Network LLC and other related entities (collectively, “Celsius”), filed for bankruptcy relief under Chapter 11 in the United States Bankruptcy Court for the Southern District of New York (the “Court”), Case No. 22-10964. In that matter, on November 23, 2023, Celsius filed an adversary proceeding against Mawson, its subsidiaries Luna Squares LLC and Cosmos Infrastructure LLC, asserting various claims related to the alleged breach of a Co-Location Agreement and Secured Promissory Note. Adv. Case No. 23-01202, claiming it is owed approximately $8 million under the promissory note and claiming entitlement to return of $15.33 million paid as deposit. Mawson denied that Celsius is entitled to the relief it seeks in the adversary proceeding and is actively defending the matter. Many of the related claims and disputes between Celsius and Mawson have been disclosed in more detail in Mawson’s previous filings with the SEC. As part of its defense, Mawson sought to have the matter removed from the adversary proceeding to arbitration based on the arbitration clause contained in one of the transaction’s agreements. Celsius opposed the removal and the matter was heard before the Court. On February 27, 2024, the Court ruled in part that the claims regarding the Co-Location Agreement could be arbitrated, but the claims for the promissory note would stay before the Court. The Court appointed a litigation administrator to handle the claims arising out of the promissory note. Mawson appealed this decision to the District Court for the Southern District of New York and ultimately prevailed. As of May 1, 2024, and pursuant to a court order dated April 22, 2024, the Celsius civil lawsuit against Luna Squares and Mawson has been dismissed pursuant to the Company’s successful motion to compel arbitration. Currently, no arbitration proceedings or further appeals have been filed by either party.
On December 22, 2023, Mawson Infrastructure Group Inc. and Luna Squares LLC made formal demand on CleanSpark Inc. and CSRE Properties Sandersville, LLC for $2,000,000 for breach of contract for failing to pay for an energy earnout provision contained in the Purchase and Sale Agreement dated September 8, 2022, between the parties. Subsequently, on January 12, 2024, Mawson and Luna filed notice of its claim for formal arbitration before the American Arbitration Association. On February 5, 2024, CleanSpark and CSRE filed a motion objecting to jurisdiction of the arbitration proceedings. An arbitrator was appointed to hear the matter and on May 1, 2024 ruled that the arbitration proceedings be dismissed for lack of jurisdiction on the grounds of conflicting language contained in the purchase and sale agreement. The ruling did not address the merits of the Company’s claims, and the Company intends to pursue its claims by civil lawsuit through a court filing.
On March 28, 2024, the Company was made a defendant in a civil suit before the Supreme Court of NSW in Sydney Australia, in the matter entitled “W Capital Advisors Pty Ltd in its capacity as trustee for the W Capital Advisors Fund v. Mawson Infrastructure Group, Inc.”, Docket No. 2024/00117331, alleging a claim to seek US$166,219 as unpaid interest under a convertible note after the Company paid in full the principal of $500,000, and AUD$298,926 under a loan deed, plus interest and costs for sums due claiming corporate guarantee by the Company for a “Variation Deed to Loan Deed” dated September 29, 2022, executed by its Australian entity, Mawson Infrastructure Group Pty Ltd. As noted previously in the Company’s Current Report on Form 8-K filed on March 29, 2024, the Company, pursuant to Australian law, on March 28, 2024, sent a preliminary discovery notice to W Capital to obtain documents and to investigate and ascertain if W Capital is a related party to Mr. James Manning, the Company’s former director and executive, and to investigate and ascertain if transactions between W Capital Advisors Pty Ltd and the Company were related party transactions.
The Company and some of its subsidiaries, including Australian entities, are currently in disputes, as outlined below. These disputes may be in or may lead to litigation.
On January 8, 2024, a commercial demand was made Flynt ICS Pty Ltd to the Company’s subsidiary and an Australian entity, MIG No. 1 Pty Ltd, for $129,930, for alleged claimed sums due under a service agreement. As determined by the Audit Committee’s investigation into Mr. James Manning, Flynt ICS Pty Ltd is a party related to Mr. James Manning, a former director and executive of the Company. On March 19, 2024, MIG No.1 Pty Ltd was placed into an Australian court appointed liquidation and wind-up process. See Note 3 - Subsidiary Deconsolidation to the Consolidated Condensed Financial Statements (Unaudited) in Item 1. Financial Statements, for further discussion.
On February 1, 2024, a former independent contractor, Noam Danenberg, through his professional company, N. Danenberg Holding (2000) Ltd, apparently filed a civil suit in Tel Aviv Israel against the Company for an alleged $90,000 in fees and other benefits. The Company has never been formally served nor has it submitted to jurisdiction in Israel.
On October 30, 2023, the directors of the Company’s Australian subsidiary, Mawson Infrastructure Group Pty Ltd (“Mawson AU”) appointed voluntary administrators in Australia to Mawson AU. Voluntary administration is a process under Australian corporate law where an external administrator is appointed to take control of the relevant entity, investigate and report to creditors about the relevant entity’s business, property, affairs and financial circumstances, and report on the options available to creditors. It is not a court process. On November 3, 2023, W Capital Advisors appointed receivers and managers in Australia under the terms of their security relating to their working capital facility.
On January 3, 2024, W Capital put Mawson on notice of its intent to collect what it asserts are past due amounts for the following claims as of December 31, 2023: (a) principal and interest payable on the Loan Amount advanced to Mawson under a variation deed, amounting to $1.30 million (AU $1.90 million); (b) the principal amount advanced under convertible note, amounting to $0.50 million; and (c) interest payable on the principal amount advanced under a convertible note, amounting to $0.07 million. W Capital is also claiming issuance of an alleged 1,500,000 shares of the Company. The Company paid to W Capital $0.50 million on March 6, 2024, and is reserving all of its rights and remedies as they pertain to W Capital’s alleged claims for additional AU$1.30 million and 1,500,000 shares which the Company disputes. On March 28, 2024, the Company was made a defendant in a civil suit before the Supreme Court of NSW, in Sydney Australia, in the matter entitled “W Capital Advisors Pty Ltd in its capacity as trustee for the W Capital Advisors Fund v. Mawson Infrastructure Group, Inc.”, Docket No. 2024/00117331, alleging a claim to seek US$166,219 as alleged unpaid interest under a convertible note after the Company paid in full the principal of $500,000, and an alleged AUD$298,926 under a loan deed, plus interest and costs for sums allegedly due claiming corporate guarantee by the Company for a “Variation Deed to Loan Deed” dated September 29, 2022, executed by Australian entity, Mawson Infrastructure Group Pty Ltd. As noted previously in the Company’s Current Report on Form 8-K filed on March 29, 2024, the Company, pursuant to Australian law, on March 28, 2024, sent a preliminary discovery notice to W Capital to obtain documents and materials to investigate and ascertain if W Capital is a related party to Mr. James Manning, the Company’s former director and executive, and to investigate and ascertain if transactions between W Capital Advisors Pty Ltd and the Company were related party transactions.
On April 19, 2024, a civil suit entitled “Blockware Solutions, LLC v. Mawson Bellefonte LLC and Mawson Infrastructure Group, Inc.” was filed in the US District Court, Southern District of New York under Civil Action No. 1:24-cv-02976 with the plaintiff, Blockware Solutions, LLC, claiming alleged merchandise price and incidental damages of $115,500, alleged consequential damages due to lost profits of $358,689, and other alleged non-specified damages, for alleged claims of non-payment. Mawson Bellefonte, LLC is a Delaware subsidiary of the Company. Mawson Bellefonte and the Company intend to defend against these alleged claims made related to this matter.
On April 23, 2024, the Company’s subsidiary and an Australian entity, Mawson AU Pty Ltd, was placed into an Australian court appointed liquidation and wind-up process.
On April 29, 2024, the Company’s subsidiary and an Australian entity, Mawson Services Pty Ltd, was placed into an Australian court appointed liquidation and wind-up process.
The Company and its subsidiaries have been in the past, and from time to time in the future, may be involved in certain litigation related to our businesses. For example, the Company and its subsidiaries receive letters of demand for payments from time to time which could lead to legal proceedings.