Q2 2026 AND SUBSEQUENT TO Q2 2026 HIGHLIGHTS

As of June 30, 2026, the Company had approximately $1.3 billion total cash and restricted cash, including $530.3 million at the Thacker Pass JV level.

o

On March 19, 2026, the Company entered into an at-the-market (“ATM”) equity program, pursuant to which the Company may sell its common shares, no par value, up to a maximum aggregate offering price of $250 million (the “March 2026 ATM Program”). Net proceeds received from the March 2026 ATM Program may be used for general corporate purposes, which may include funding of corporate and project overhead, capital expenditures, debt repayment, and working capital. As of June 30, 2026, the Company issued and sold 13.0 million common shares at an average price of $5.36 per share for aggregate net proceeds of $68.5 million after sales agent’s commission and other expenses. Subsequent to Q2 2026, the Company issued and sold 1.1 million common shares at an average price of $3.87 per share for aggregate net proceeds of $4.2 million after sales agent’s commission and other expenses.

o

On June 3, 2026, the Company received its third advance on the U.S. Department of Energy (the “DOE”) loan (“DOE Loan”) of $342 million. Cumulative advances total $1.209 billion.

o

On August 5, 2026, the Company entered into a securities purchase agreement (the “Purchase Agreement”) with YA II PN, Ltd., an affiliate of Yorkville Advisors Global, LP (“Yorkville”), for up to $175 million in aggregate principal amount of subordinated convertible debentures (the “Yorkville Debentures”). At the initial closing, the Company has agreed to issue $150 million in Yorkville Debentures. The Company retains the right to issue up to an additional $25 million in Yorkville Debentures in one or more subsequent closings at its discretion, subject to conditions as further described in the Purchase Agreement. See Note 16 – Subsequent Events – Yorkville Convertible Debentures and Yorkville Advisors below for further discussion.

o

As of August 12, 2026, the Company had 363,042,943 shares issued and outstanding.

The Company continues to progress major construction of the processing plant at Thacker Pass Phase 1, targeting mechanical completion in late 2027. As of June 30, 2026:

o

3.42 million workhours were completed without a serious injury or lost-time incident, with a total recordable incident frequency rate of 0.58.

o

$1.8 billion of construction capital and other project-related costs had been capitalized, of which $1.6 billion is part of the total capital expenditure (“Capex”) estimate of $2.93 billion per the Company’s Technical Report entitled “NI 43-101 Technical Report on the Thacker Pass Project Humboldt County, Nevada, USA,” effective December 31, 2024 (“Technical Report”). The Company continues to target a total Capex range of $1.3 billion to $1.6 billion for Thacker Pass Phase 1 for fiscal year 2026. See Capital Expenditure and 2026 Capex Guidance below for details.

o

Detailed engineering design completed surpassed 95%, while procurement exceeded 80%, including the shipment of major plant materials and equipment.

o

Over 1,600 personnel were on site, and on-site personnel levels are expected to increase to over 2,000 in the second half of 2026.

o

Over 1,500 workers were residing at the Company’s all-inclusive housing facility in Winnemucca (the “Workforce Hub” or “WFH”).

Long-lead equipment continued arriving at Thacker Pass and the fabrication yard in Winnemucca. Outstanding long-lead items are expected to be delivered throughout 2026, along with other equipment and construction materials.

o

Over 85% of the structural steel for Thacker Pass, which is sourced from the United Arab Emirates, is in transit or has arrived on site at Thacker Pass or the laydown yard in Winnemucca. The balance is expected in Q3 2026. The Company and Bechtel have worked with the steel supplier to minimize the impact of the Middle East conflict, including the closure of the Strait of Hormuz, on the fabrication and shipment of steel to Thacker Pass. The Company has successfully re-routed steel through the Port of Jeddah.

Development milestones achieved at Thacker Pass during Q2 2026 include:

o

Completing upgrades to the high voltage power line connecting Thacker Pass to the local power grid.

o

Placement of the first Electrical Room, 115kV Power Transformer and Control Enclosures.

o

Progressing structural steel at the Filter Building, Magnesium Sulfate Building and the Lithium Carbonate Building.

o

Deliveries of approximately 100 prefabricated pipe rack modules, with pre-installed piping manufactured in Winnemucca. Deliveries are expected to continue throughout Q3 2026.

o

Commencement and continuation of key equipment installation at the following facilities:

Lithium Carbonate Crystallizer: Bicarbonate Reactor;

Magnesium Sulfate Building: Turbo Fans, Stage 4 Crystallizer;

Filter Building: Air Compressors and Receivers, Conveyor Tail Pulleys, Neutralization Filter Discharge Conveyors;

Countercurrent Decantation and Run-of-Mine areas: Thickener Steel and Shell Plates;

Sulfuric Acid Plant: Fin Fan Coolers, SS Converter, Steam Turbine Generator, Main Compressor, Cold Interpass Heat Exchanger, Hot Interpass Heat Exchanger and the 198-foot-tall Duplex Plant Stack.

The following are expected development milestones for the second half of 2026:

o

All main concrete required at the site is expected to be completed.

o

Early commissioning of utilities in the individual plants is expected to commence.

o

Given the advanced level of detailed engineering achieved, the Company has commenced a definitive capital estimate, targeting completion by the end of Q3 2026. Advanced engineering and procurement is expected to enable the team to estimate remaining quantities and materials with higher confidence. The Company will use current data to assess remaining labor needs and productivity rates for the estimate and will incorporate recent and unexpected developments, including implications from tariffs, conflicts in the Middle East, fuel prices, and other inflationary increases not included in the total Capex estimate of $2.93 billion per the Company’s Technical Report. During Q2 2026, the cost environment for activities associated with Thacker Pass was also unfavorably impacted by items such as: reduced open sea lane availability, reductions in the availability of U.S. fabrication capacity, constraints in U.S. logistics, further inflationary pressures as well as an increasingly competitive skilled labor market. Further, total associated tariff exposure, the majority of which is expected to be incurred during 2026, is estimated between $80 million and $100 million.

Construction at the Company’s Transload Terminal (“TLT”) west of Winnemucca continues. In Q2 2026, the general site and railroad grading were completed and installation of rail stabilization (geo-membrane) and sub-ballast commenced. Completion of the TLT is targeted in 2027 to align with startup at Thacker Pass. The TLT is approximately 60 miles from Thacker Pass, adjacent to the rail line, and is intended to support operations by serving as a critical logistics hub for the operation’s reagents.

During Q2 2026, the Company delivered a $5.0 million commitment to the Fort McDermitt Paiute and Shoshone Tribe’s Building Fund, in accordance with its obligations under the Community Benefits Agreement. The funds will support plans to rebuild a Travel Plaza, which was lost to fire in September 2020. An additional $0.4 million has been contributed to the tribe for workforce training, cultural monitoring and administrative purposes.