LITHIUM AMERICAS CORP.
For the period ended Mar 31, 2026. Filed May 14, 2026.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Mar 31, 2026 · Filed May 14, 2026
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Q1 2026 AND SUBSEQUENT TO Q1 2026 HIGHLIGHTS
As of March 31, 2026, the Company had approximately $1.2 billion total cash and restricted cash, including $529 million at the Thacker Pass JV level.
o
On January 26, 2026, the Company completed an at-the-market (“ATM”) equity program established on November 13, 2025 (the “November 2025 ATM Program”). The Company issued and sold an aggregate total of 43.3 million common shares at an average price of $5.78 per share pursuant to the November 2025 ATM Program, for aggregate net proceeds of $246.7 million after sales agent’s commission and other expenses. Of these amounts, during Q1 2026, the Company issued and sold 32.5 million common shares at an average price of $5.92 per share, for aggregate net proceeds of $189.7 million after sales agent commission and other expenses.
o
On February 24, 2026, the Company received its second advance on the U.S. Department of Energy (the “DOE”) loan (“DOE Loan”) of $432 million.
o
On March 19, 2026, the Company entered into an ATM equity program, pursuant to which the Company may sell its common shares, no par value, up to a maximum aggregate offering price of $250 million (the “March 2026 ATM Program”). Use of net proceeds for the March 2026 ATM Program includes general corporate purposes, which may include funding of corporate and project overhead expenses, financing of capital expenditures, repayment of indebtedness and additions to working capital. As of March 31, 2026, the Company did not issue or sell any common shares nor receive any net proceeds pursuant to the March 2026 ATM Program. Subsequent to March 31, 2026, the Company issued and sold an aggregate total of 2.3 million common shares at an average price of $5.20 per share pursuant to the March 2026 ATM Program, for aggregate net proceeds of $11.2 million after sales agent commission and other expenses.
o
As of May 13, 2026, the Company had 351,062,478 shares issued and outstanding.
On January 30, 2026 (the “Issuance Date”), pursuant to the omnibus waiver, consent and amendment (as amended, the “OWCA”) entered into by the Company and the DOE on October 7, 2025, the Company issued to the DOE a warrant to purchase up to 18,268,687 common shares, which was equal to 5% of the Company’s outstanding total shares as of the Issuance Date, at an exercise price of $0.01 per share (the “LAC Warrant”), exercisable for ten years from the Issuance Date, subject to customary anti-dilution adjustments and other terms set forth in the LAC Warrant. Additionally, the JV issued to the DOE a warrant to purchase 8,656,509,695 non-voting units of the JV, which was equal to a 5% economic interest in the JV as of the Issuance Date, at an exercise price of $0.0001 per unit (the “JV Warrant”), exercisable for ten years from the Issuance Date, subject to customary anti-dilution adjustments and other terms set forth in the JV Warrant.
The Company continues to progress major construction of the processing plant at Thacker Pass Phase 1, targeting mechanical completion in late 2027. As of March 31, 2026:
o
A total of 2.43 million workhours completed at Thacker Pass without a serious injury or lost-time incident, and a total recordable incident frequency rate of 0.25.
o
A total of $1.3 billion of construction capital costs and other project-related costs have been capitalized, of which $1.1 billion is part of the total capital expenditure (“Capex”) estimate of $2.93 billion per the Company’s Technical Report entitled “NI 43-101 Technical Report on the Thacker Pass Project Humboldt County, Nevada, USA,” effective December 31, 2024 (“Technical Report”). The Company continues to target a total capex range of $1.3 billion to $1.6 billion for Thacker Pass Phase 1 for fiscal year 2026. See the Capital Expenditure and 2026 Capex Guidance section below for more details.
o
Detailed engineering design completed surpassed 95%, while procurement was over 70% complete, including the shipment of major plant materials and equipment.
o
There were approximately 1,065 personnel on site, expected to increase to over 2,000 in the second half of 2026.
o
There were over 1,000 workers residing at the Company’s all-inclusive housing facility for construction workers in Winnemucca (the “Workforce Hub” or “WFH”).
Long-lead equipment has been arriving to either Thacker Pass or the fabrication yard in Winnemucca, including the 115KV Main Transformer, Auxiliary Boiler, Air Cooled Heat Exchangers, Fin Fan Cooler, Duplex Stack and Bicarbonate Reactors. Additional long-lead items that have started their delivery to site include the Thickener Steel and Shell Plates, Filter Presses, Steam Turbine Generator and SS Converter. Outstanding long-lead items are expected to be delivered throughout 2026, along with other equipment and construction materials.
o
Over 75% of the structural steel for Thacker Pass, which is sourced from the United Arab Emirates, is in transit or has arrived on site at Thacker Pass or the laydown yard in Winnemucca. The Company and Bechtel have worked with the steel supplier to attempt to limit the effects of the Middle East conflict, including the closure of the Strait of Hormuz, to minimize impacts on the fabrication and shipment of steel to Thacker Pass. Predominantly, the Company has successfully re-routed steel through the Port of Jeddah.
Development milestones achieved to date at Thacker Pass include:
o
The first cable pulls on the module pipe racks commenced in March 2026.
o
Structural steel at the Filter Building progresses, with the second floor being installed.
o
Installation of key equipment commenced at the following facilities: Bicarbonate Reactors for the Lithium Carbonate Crystallizer, Pillers for Magnesium Sulfate, Air Compressors and Conveyor Tail Pulley’s for the
Filter Building, Thickener Steel and Shell Plants in the Countercurrent Decantation and Run-of-Mine areas, and Fin Fan Coolers and SS Converter for the Sulfuric Acid Plant.
o
Given the advanced level of detailed engineering, the Company has commenced a definitive capital estimate, targeting completion in the second half of 2026. Advanced levels of engineering and procurement is expected to enable the team to estimate remaining quantities and materials with higher confidence. The Company will use current data to assess remaining labor needs and productivity rates for the estimate and will incorporate recent unexpected developments including the implications of tariffs, the Middle East conflict impacts, fuel price increases and other inflationary increases that were not included in the total Capex estimate of $2.93 billion per the Company’s Technical Report. The total Capex estimate of $2.93 billion did not include any exposure to tariffs. The Company estimates the total potential exposure to tariffs for Thacker Pass Phase 1 construction costs to be approximately $80 million to $120 million, the majority of which is expected to be incurred during 2026.
o
Work to enhance reliability for grid power from the local electric utility cooperative, by upgrading six regional substations and switching stations, was completed in March 2026, ahead of schedule.
Construction at the Company’s Transload Terminal (“TLT”) west of Winnemucca commenced in March 2026, with completion targeted in 2027 to align with start up at Thacker Pass. The TLT is approximately 60 miles from Thacker Pass, adjacent to the rail line, and is intended to support operations by serving as a critical logistics hub for the Project’s reagents.