Item 3. Legal Proceedings
The Company purchased substantially all of the assets of CLMBR, Inc. (“CLMBR, Inc.”) in February 2024. On March 7, 2024, a petition was filed by Tung Keng Enterprise Co., Ltd. d/b/a DK City Co., Ltd. (“DK City”) against CLMBR, Inc. and the Company in the United States District Court for the District of Colorado to enforce a monetary arbitration award of approximately $2.25 million against CLMBR, Inc. (the “Petition”). The Company was not involved in that prior arbitration, which involved alleged breaches of an equipment manufacturing agreement between CLMBR, Inc. and DK City and was resolved prior to the Company’s purchase of CLMBR, Inc. On June 25, 2024, CLMBR, Inc. and the Company collectively resolved the dispute via a Confidential Settlement Agreement and Mutual Release with DK City. Pursuant to that agreement, the Company was required to make certain payments to DK City, CLMBR, Inc. and the Company would be released from liability, and the Petition would be voluntarily dismissed without prejudice. The Company subsequently defaulted on this agreement due to not complying with the payment plan, and on September 22, 2025 a new petition was filed alleging breach of the negotiated settlement. The complaint seeks damages in the amount of $2.0 million, plus statutory interest and attorneys' fees. The Company has admitted liability, and the parties have requested a Magistrate Judge settlement conference. The plaintiff has filed a motion for summary judgment, but the parties are engaged in settlement discussions.
Total remaining payments as of December 31, 2025 of $2.1 million, including accrued interest, are reflected in Accrued Expenses and other current liabilities in the accompanying consolidated balance sheet.
On or about February 20, 2025, the Company was sued in the Superior Court of Massachusetts, Suffolk County, by one of its former financial services consultants (“the Plaintiff”), alleging a breach of an agreement between the parties for financial services Plaintiff allegedly provided to the Company. The dispute was fully and amicably resolved and on June 12, 2025, the parties filed a joint stipulation of dismissal with prejudice and settlement amount was $2.2 million. The current portion of the total remaining payments as of December 31, 2025 of $0.3 million is included in accrued expenses and other current liabilities and the non-current portion of $1.8 million is included in other long term liabilities in the condensed consolidated balance sheet.
From time to time, we may become involved in additional regulatory investigations or legal proceedings arising in the ordinary course of our business. With respect to the matters described above, and in particularly the DK City matter in which the Company has acknowledged a payment default, we cannot provide assurance as to the ultimate outcome. An adverse disposition of any pending matter could have a material adverse effect on our business, financial condition or results of operations because of defense and settlement costs, diversion of management resources, and other factors.