PUBLIC SERVICE ELECTRIC & GAS CO
For the period ended Dec 31, 2025. Filed Feb 26, 2026.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2025 · Filed Feb 26, 2026
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Capital Requirements
We expect that all of our capital requirements over the next three years will come from a combination of internally generated funds and external debt financing. Projected capital construction and investment expenditures, excluding nuclear fuel purchases, for the next three years are presented in the following table. These projections include Allowance for Funds Used During Construction for PSE&G and Interest Capitalized During Construction for PSEG’s other subsidiaries. These amounts are subject to change, based on various factors. Amounts shown below for PSE&G include currently approved programs. We intend to continue to invest in infrastructure modernization and will seek to extend these and related programs as appropriate.
| 2026 · 2027 · 2028 | |||
|---|---|---|---|
| Millions | |||
| PSE&G: | |||
| Transmission | $835 | $950 | $975 |
| Electric Distribution | 1,410 | 1,440 | 1,520 |
| Gas Distribution | 1,130 | 1,115 | 1,165 |
| Clean Energy | 810 | 885 | 700 |
| Total PSE&G | $4,185 | $4,390 | $4,360 |
| Competitively Bid, FERC Regulated Transmission | 20 | 115 | 195 |
| PSEG Power & Other | 435 | 330 | 275 |
| Total PSEG | $4,640 | $4,835 | $4,830 |
PSE&G
PSE&G’s projections for future capital expenditures include material additions and replacements to its T&D systems to meet expected growth and to manage reliability. As project scope and cost estimates develop, PSE&G will modify its current projections to include these required investments. PSE&G’s projected expenditures for the various items reported above are primarily comprised of the following:
Transmission—investments focused on growing demand, reliability improvements and replacement of aging infrastructure.
Electric and Gas Distribution—investments for new business and demand, reliability improvements and modernization and replacement of equipment that has reached the end of its useful life.
Clean Energy—investments associated with customer EE programs, infrastructure supporting EVs and grid-connected solar.
In 2025, PSE&G made $2,731 million of capital expenditures, primarily for T&D system reliability. In addition, PSE&G had $145 million associated with CEF-EE II on-bill repayments included in investing cash flows, as well as cost of removal, net of salvage, of $156 million associated with capital replacements, and expenditures for EE programs of approximately $552 million, which are included in operating cash flows.
In December 2023, PJM awarded us an approximately $424 million project to address increasing load and reliability issues in Maryland and northern Virginia as part of its 2022 Window 3 competitive solicitation.
PSEG’s other projected expenditures are primarily comprised of investments to maintain and enhance current nuclear operations and opportunities to increase nuclear generation at PSEG Power and to purchase hardware, software and office equipment at Services.
In 2025, PSEG Power & Other made capital expenditures of $236 million, excluding $336 million for nuclear fuel, primarily related to various nuclear projects at PSEG Power and various IT projects at Services.
Other Material Cash Requirements
The following table reflects our other material cash requirements which include debt maturities and interest payments, operating lease payments and energy related purchase commitments in the respective periods in which they are due. For additional information, see Item 8. Note 13. Debt and Credit Facilities and Note 6. Leases.
The table below does not reflect any anticipated cash payments for pension and OPEB or AROs due to uncertain timing of payments. See Item 8. Note 11. Pension, Other Postretirement Benefits (OPEB) and Savings Plans and Note 10. Asset Retirement Obligations (AROs) for additional information.
| TotalAmountCommitted · LessThan1 Year · 2 - 3Years · 4 - 5Years · Over5 Years | |||||
|---|---|---|---|---|---|
| Millions | |||||
| Long-Term Recourse Debt Maturities | |||||
| PSEG | $5,346 | $— | $1,300 | $1,900 | $2,146 |
| PSE&G | 16,115 | 875 | 1,125 | 675 | 13,440 |
| PSEG Power | 1,250 | — | — | 750 | 500 |
| Interest on Recourse Debt | |||||
| PSEG | 1,385 | 253 | 466 | 296 | 370 |
| PSE&G | 10,318 | 653 | 1,256 | 1,183 | 7,226 |
| PSEG Power (A) | 449 | 68 | 136 | 116 | 129 |
| Operating Leases | |||||
| PSE&G | 103 | 18 | 26 | 20 | 39 |
| PSEG Power & Other | 76 | 16 | 32 | 28 | — |
| Energy-Related Purchase Commitments | |||||
| PSEG Power (B) | 3,049 | 861 | 997 | 489 | 702 |
| Total | $38,091 | $2,744 | $5,338 | $5,457 | $24,552 |
(A)
Based on a blended rate including effects of floating to fixed rate hedging transacted at the Parent level.
(B)
Represents the nuclear fuel and natural gas commitments for the facilities we operate.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.