Capital Expenditures

We have continued to make capital investments designed to increase pulp, green energy and chemical production, reduce costs and improve efficiency and environmental performance at our pulp mills. The improvements made over the years have increased the competitive position of our pulp mills. Since the acquisitions, we have also made capital investments to optimize sawmill production at the Friesau mill and Torgau facility.

The following table sets out the total capital expenditures by segment (excluding any related governmental grants) for the periods indicated:

Year Ended December 31,
20252024
(in thousands)
Pulp segment$63,059$46,400
Solid wood segment25,41737,732
Total$88,476$84,132

For our pulp segment, in addition to maintenance projects, capital investments in 2025 at the Stendal mill were primarily related to improvements to the lime kiln. For the Rosenthal mill, capital investments in 2025 were primarily related to upgrades to the digester evaporator and a new turbine generator. For our Canadian mills, capital investments in 2025 were primarily related to completion of the wood room at the Celgar mill. In 2024, in addition to maintenance projects, capital investments at the Stendal mill were primarily related to completing the rebuild of the wood chip conveying system that was damaged by a fire in 2022. For the Rosenthal mill, capital investments in 2024 were primarily related to the purchase of a digester evaporator. For our Canadian mills, capital investments in 2024 were primarily related to enhancements to soot blowers at the Peace River mill, and for both mills, improvements to the wood rooms.

For our solid wood segment, in addition to maintenance projects, capital investments at the Torgau facility and Friesau mill in 2025 were primarily related to log yard improvements. For our mass timber facilities, capital investments in 2025 were primarily related to sorting line upgrades and other strategic projects. In 2024, in addition to maintenance projects, capital investments at the Torgau facility were primarily related to log yard improvements and sawing and planer machine upgrades. For the Friesau mill, capital investments in 2024 were primarily related to sorter line upgrades. For our mass timber facilities, capital investments in 2024 were primarily related to production and sorter line upgrades.

Qualifying capital investments at industrial facilities in Germany that reduce pollutants in the effluent discharge can be used to offset wastewater fees that would otherwise be required to be paid. For more information about our environmental capital expenditures, see “– Environmental”.

In 2026, excluding amounts being financed through government grants, we currently expect our total capital expenditures to be approximately $60.0 million to $80.0 million, principally comprised of maintenance projects.