Q3 2025 PROJECT AND CONSTRUCTION HIGHLIGHTS

During the quarter ended September 30, 2025, $145.9 million of construction capital costs and other project-related costs were capitalized. As of September 30, 2025, a total of $720.0 million of construction capital costs and other project-related costs have been capitalized.

The Company continues to progress major construction at Thacker Pass. Mechanical completion of the Phase 1 processing plant is targeted for late 2027.

o

Engineering design surpassed 80% design complete as of September 30, 2025, and is expected to surpass 90% design complete by year end 2025. The higher level of detailed engineering at the early stages of construction helps to de-risk execution in terms of Project schedule and cost.

o

On site at Thacker Pass, the first steel columns have been installed, and permanent plant roads and entrances, as well as laydown yards to store long-lead equipment have been completed.

o

The fabrication yard in Winnemucca has received steel for pre-assembled pipe-rack sections.

o

The Company has entered into certain purchase agreements related to long-lead equipment, infrastructure and services related to the construction of the processing plant as well as development and mining services at Thacker Pass. As of September 30, 2025, approximately $430 million has been committed.

o

Major long-lead equipment and a substantial amount of other equipment and construction materials are expected to be delivered to either Thacker Pass or the fabrication yard in Winnemucca throughout the first quarter of 2026. Most of this equipment and construction material is sourced from Canada, China, India, UAE, Turkey and the European Union, and may be subject to tariffs. The Company has been working toward limiting the effect of any potential tariffs on our construction supply chain, with approximately 75% of the total capital project cost structure related to labor, contractors and other services not expected to be directly affected by any potential tariffs.

As of September 30, 2025, there were approximately 550 manual craft and 150 additional site workers, for a total of approximately 700 personnel on site. This is expected to increase to approximately 1,000 site personnel by the end of 2025 and approximately 1,800 at peak construction. Placement of housing modules at the Company’s all-inclusive housing facility for construction workers in Winnemucca (the “Workforce Hub” or “WFH”) is complete and the occupancy permit was received for the first phase. The first residents took occupancy in late September 2025.