10. Commitments and contingencies

Lease commitments

The Company’s lease portfolio primarily comprises operating leases for office, laboratory, and manufacturing space. These leases contain various rent abatement periods, after which they require monthly lease payments that may be subject to annual increases throughout the lease term. Certain leases include options to extend the term. The renewal option is considered in the remaining lease term for the lease only when the Company is reasonably certain it will renew the lease. Certain leases provide the Company with the right to make tenant improvements, including the addition of laboratory space or build-out of manufacturing capabilities, and include a lease incentive allowance.

In June 2022, the Company entered into a lease agreement for 79,565 square feet of office, laboratory, and manufacturing space located in Bothell, Washington. The initial term of the lease expires in February 2039, with the option to extend the lease for up to three additional five-year terms. The lease agreement also provides for up to $19.9 million for reimbursement of tenant improvements, as well as an additional $8.0 million loan for tenant improvements, available at the Company’s election (the Tenant Improvement Loan). The Company elected to receive the Tenant Improvement Loan in the second quarter of 2024 and is obligated to repay to the landlord monthly over the initial term of the lease with interest at a rate of 6.5% per year. As of September 30, 2025, $0.4 million was included in accrued expenses and other current liabilities and $7.1 million was included in other non-current liabilities. The Company is obligated to pay base rent of approximately $68.8 million over the initial term of the lease. In accordance with the lease agreement, the Company has obtained a letter of credit in the amount of $1.6 million.

In the second quarter of 2025, the Company recognized non-cash impairment losses for the operating lease right-of-use (ROU) asset, construction in progress, and laboratory equipment for the Bothell facility, and for the operating lease ROU asset, leasehold improvements, and laboratory equipment for the Seattle facility. The Company also recognized additional non-cash impairment losses for other long-lived assets. Refer to Note 11, Impairment of long-lived assets for further information.

The following table contains additional information related to the Company’s operating leases:

LocationUseApproximate Square FootageCommencement DatesExpiration Dates
Seattle, WAOffice/Laboratory48,000March 2019 to September 2020December 2026 to April 2028
Cambridge, MAOffice/Laboratory56,000March 2019 to January 2020June 2027 to February 2028
South San Francisco, CAOffice/Laboratory99,000December 2019 to April 2022April 2030
Rochester, NYOffice/Laboratory3,000January 2022January 2027
Bothell, WAOffice/Laboratory/Manufacturing80,000January 2023January 2039

Throughout the term of each lease agreement, the Company is responsible for paying, in addition to base rent, certain operating costs, such as common area maintenance, taxes, utilities, and insurance. These additional charges are considered variable lease costs and are recognized in the period in which the costs are incurred.

The following table summarizes the Company’s lease costs:

Three Months Ended September 30,Nine Months Ended September 30,
2025202420252024
(in thousands)
Operating lease cost$4,478$4,728$20,558$13,816
Short-term lease cost8461,1082,8273,659
Variable lease cost2,2432,1956,2386,297
Total lease cost$7,567$8,031$29,623$23,772

As of September 30, 2025, the weighted-average remaining lease term was 7.3 years, and the weighted-average incremental borrowing rate was 10.9%.

The following table reconciles the Company’s undiscounted operating lease cash flows by fiscal year to the present value of the operating lease liabilities as of September 30, 2025 (in thousands):

2025 (remaining 3 months)$5,489
202622,473
202719,390
202814,698
202914,071
2030 and thereafter48,701
Total undiscounted lease payments124,822
Less: imputed interest(42,586)
Present value of operating lease liabilities82,236
Less: current portion of operating lease liabilities$(14,368)
Operating lease liabilities, net of current portion$67,868
  1. Impairment of long-lived assets

As a result of changes in business plans and the Company's intention to pursue potential subleases for the Bothell and Seattle facilities, due in part to the Company’s decision to suspend further build-out of its internal manufacturing capabilities at the Bothell facility in the-near term due to increased availability of manufacturing capacity at third-party contract development and manufacturing organizations for cell and gene therapy products, as well as progress in understanding its near-term manufacturing needs, and other factors, the Company determined that during the second quarter of 2025 a triggering event occurred and performed an impairment analysis. For the Bothell facility, the Company determined that the combined operating lease ROU asset and construction in progress were not fully recoverable as the carrying value exceeded the estimated fair value and recorded a non-cash impairment loss of $34.2 million for this asset group. For the Seattle facility, the Company determined that the combined operating lease ROU asset and leasehold improvements were not fully recoverable as the carrying value exceeded the estimated fair value and recorded a non-cash impairment loss of $3.8 million for this asset group. In addition, in connection with the Bothell and Seattle facilities, the Company recognized non-cash impairment losses related to laboratory equipment of $3.8 million and $2.0 million, respectively. The Company also recognized an additional $0.8 million non-cash impairment loss for other long-lived assets. The losses were recorded in operating expenses in the statement of operations in the second quarter of 2025.