Skip to main content

EXELON CORP

For the period ended Dec 31, 2024. Filed Feb 12, 2025.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2024 · Filed Feb 12, 2025

EXC$45.53-0.3%Stored close · as of Nov 10, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

Other Key Business Drivers and Management Strategies

Utility Rates and Rate Proceedings

The Utility Registrants file rate cases with their regulatory commissions seeking increases or decreases to their electric transmission and distribution and gas distribution rates to recover their costs and earn a fair return on their investments. The outcomes of these regulatory proceedings impact the Utility Registrants’ current and future results of operations, cash flows, and financial positions. See Note 3 — Regulatory Matters of the Combined Notes to Consolidated Financial Statements for additional information on these regulatory proceedings.

Allocation of Income Taxes to Regulated Utilities (All Registrants)

In Q2 2024, the IRS issued a series of PLRs, to another taxpayer, providing guidance with respect to the application of the tax normalization rules to the allocation of consolidated tax benefits among the members of a consolidated group associated with NOLC for ratemaking purposes. The rulings provide that for ratemaking purposes the tax benefit of NOLC should be reflected on a separate company basis not taking into consideration the utilization of losses by other affiliates. A PLR issued to another taxpayer may not be relied on as precedent.

For the Registrants, except for PECO, the methodology prescribed by the IRS in these PLRs could result in a reduction of the regulatory liability established for EDITs arising from the TCJA corporate tax rate change that is being amortized and flowed through to customers as well as a reduction in the accumulated deferred income taxes included in rate base for ratemaking purposes of approximately $1.2 billion - $1.7 billion.

Management will continue to work collaboratively with the Registrants’ regulatory commissions to file PLR requests with the IRS confirming the treatment of NOLC for ratemaking purposes. The Registrants will record the impact, if any, upon receiving their own PLRs from the IRS.

Legislative and Regulatory Developments

Infrastructure Investment and Jobs Act

On November 15, 2021, President Biden signed the $1.2 trillion IIJA into law. IIJA provides for approximately $550 billion in new federal spending. Categories of funding include funding for a variety of infrastructure needs, including but not limited to: (1) power and grid reliability and resilience, (2) resilience for cybersecurity to address critical infrastructure needs, and (3) electric vehicle charging infrastructure for alternative fuel corridors. The Registrants continue to evaluate programs under the legislation and consider possible opportunities to apply for funding, either directly or in potential collaborations with state and/or local agencies and key stakeholders. The Registrants cannot predict the ultimate timing and success of securing funding from programs under IIJA.

In March 2023, Exelon, ComEd, and PHI submitted three applications related to the Smart Grid Grants program under section 40107 of IIJA. These applications are focused on replacing existing Advanced Distribution Management Systems (ADMS) in support of DERs and grid-edged technologies, strengthening interoperability and data architecture of systems in support of two-way power flows and accelerating advanced metering deployment in disadvantaged communities. In October 2023, ComEd’s project, Deployment of a Community-Oriented Interoperable Control Framework for Aggregating and Integrating Distributed Energy Resources and Other Grid-Edge Devices, was recommended by the Grid Deployment Office (GDO) for negotiation of a final award up to $50 million. This project will enable ComEd and its local partners to deploy the next generation of grid technologies that support the growth of solar and electric vehicles (EVs), while piloting new local workforce training initiatives to support job creation connected to the clean energy transition. The award negotiation process is complete and funding has been obligated.

In April 2023, ComEd, PECO, BGE, and PHI submitted seven applications related to the Grid Resilience Grants program under section 40101(c) of IIJA. These applications are broadly focused on improving grid resilience with an emphasis on disadvantaged communities, relief of capacity constraints and modernizing infrastructure, deployment of DER and microgrid technologies and providing improved resilience through storm hardening projects. In October 2023, PECO’s project, Creating a Resilient, Equitable, and Accessible Transformation in Energy for Greater Philadelphia (CREATE), was recommended by the GDO for negotiation of a final award up to $100 million. This project will support critical electric infrastructure investments to help reduce the impact of extreme weather and historic flooding on the Registrants' electric distribution system. The award negotiation process is complete and funding has been obligated.

The Registrants are supporting three different Regional Clean Hydrogen Hub opportunities, covering all five states that Exelon operates in plus Washington D.C. under a program that will create networks of hydrogen producers, consumers, and local connective infrastructure to accelerate the use of hydrogen as a clean energy carrier that can deliver or store energy. Applications for the three opportunities under this program were submitted in April 2023. In October 2023 the DOE announced it selected two of the projects for further negotiation: (1) the Mid-Atlantic Clean Hydrogen Hub (MACH2), which is being supported by PECO and PHI, and (2) the Midwest Alliance for Clean Hydrogen (MachH2), which is being supported by ComEd.

In November 2023, the GDO announced up to $3.9 billion available through the second-round funding opportunity of the Grid Resilience and Innovation Partnerships (GRIP) Program for fiscal years 2024 and 2025. This funding opportunity focuses on projects that will improve electric transmission by increasing funding and advancing interconnection processes for faster build out of energy projects, create comprehensive solutions that link grid communications systems and operations to increase resilience and reduce power outages and threats, and deploy advanced technologies such as distributed energy resources and battery systems to provide essential grid services to ensure American communities across the country have access to affordable, reliable, clean electricity. In March 2024, Exelon, BGE, PHI, Pepco, DPL, and ACE submitted five applications for Topic Area 2 (Smart Grid Grants). These applications focus on improving resilience of the electric grid and deployment of technologies to enhance grid flexibility and deliver benefits to customers across the Exelon footprint.

In October 2024, Exelon’s project, Renewable-Aware Distribution Operations: Pioneering a cleaner future for all our communities, and BGE’s project, Baltimore Interconnection Readiness & Deployment of Storage (BIRDS), were recommended by the GDO for negotiation of a final award up to $100 million and $50 million, respectively. The Exelon project will deploy advanced Distribution Energy Resource Management System (DERMS) capabilities and pilot technology to increase the flexibility, efficiency, reliability, and resilience of its distribution network. BGE’s project will facilitate a programmatic approach to a flexible and decentralized energy distribution grid while setting an automated and digitized framework for unlocking future clean energy investments. Both the Exelon and BGE projects have been issued conditional awards, subject to final negotiations.

The Trump Administration has issued numerous Executive Orders (EOs), including the Unleashing American Energy Order on January 20, 2025, which requires an immediate pause in the disbursement of funds appropriated through the IRA and IIJA during a 90-day review period. Exelon is currently evaluating this EO and others to determine what, if any, impact they might have on awards selected or received from the Department of Energy.

PJM Regional Transmission Expansion

At the February 4, 2025 Transmission Expansion Advisory Committee meeting, PJM disclosed PECO’s, BGE’s and Pepco’s revised total estimated costs for the planned retirement of the Brandon Shores Generating Station of approximately $154 million, $1.1 billion, and $241 million, respectively.