Advanced-Stage Properties – El Gallo

El Gallo HLM

We have reached a construction decision for the Phase 1 heap leach material reprocessing project contemplated in our Feasibility Study (previously described as the Fenix project). In December 2025, the Company was granted the extension of its Environmental Impact Assessment (Manifestación de Impacto Ambiental) from the Mexican government. The

Company is currently proceeding with the final detailed engineering plan for the mill, which has been purchased and is onsite. We anticipate beginning construction late-2026, with production commencing late-2027.

Phase 1 is expected to produce for 10 years, producing approximately 20,000 GEOs annually once commercial production is achieved. Production will come from the reprocessing of the material currently on the leach pad, through a ball mill with an operating plan optimized for cash flow and recovery. Remaining capital costs to complete construction are estimated at $30 million. Since the material that will be processed has been previously leached, there will be no significant development or exploration costs anticipated.