Advanced-Stage Properties – Fenix Project
We have reached a construction decision for the Phase 1 gold reprocessing project contemplated in our Feasibility Study (previously described as the Fenix project). The Company is waiting for the extension of its Environmental Impact Assessment (Manifestación de Impacto Ambiental) from the Mexican government. McEwen is proceeding with the final detailed engineering plan for the mill, which has been purchased and is onsite. Assuming the extension of the Environmental Impact Assessment is approved, we anticipate beginning construction mid-2026, with production commencing mid-2027.
Phase 1 is expected to produce for 10 years, producing approximately 20,000 GEOs annually once commercial production is achieved. Production will come from the reprocessing of the material currently on the leach pad, through a ball mill with an operating plan optimized for cash flow and recovery. Remaining capital costs to complete construction
are estimated at $25 million. Since the material that will be processed has been previously leached, there will be no significant development or exploration costs are anticipated.
The Company has also started work on Fenix Phase 2, which would primarily be production from the project’s in-situ silver deposits. This would extend the life of Fenix well beyond the initial 10 years contemplated under Phase 1.