ITEM 2. Properties

Corporate Headquarters

TeraWulf maintains its principal corporate offices in Easton, Maryland and New York, New York. Office space at these locations is provided by Beowulf E&D, a company controlled by TeraWulf’s CEO, under an Administrative and Infrastructure Services Agreement dated April 27, 2021. Since January 1, 2023, the use of TeraWulf’s corporate offices has been covered under the base fee outlined in Amendment No. 1 to the Services Agreement (as amended, the “Services Agreement”). The Company considers its current office space adequate for its existing operations.

TeraWulf owns and operates the Lake Mariner Facility, a high-performance digital infrastructure campus located in Barker, New York, on the site of a former coal-fired power plant. The facility began sustainably mining bitcoin in March 2022 and, as of December 31, 2024, has approximately 195 MW of operational mining capacity. The site is designed for scalable expansion, with the ability to increase capacity up to 500 MW in the near term and potentially 750 MW with targeted transmission upgrades.

The Lake Mariner Facility operates under a lease agreement with Somerset Operating Company, LLC (“Somerset”), a company controlled by TeraWulf’s CEO. Under the agreement, Lake Mariner leases approximately 157 acres in Niagara County, New York, for an initial term of 35 years which automatically renews for up to nine additional periods of five years each, unless Lake Mariner provides written notice to Somerset to terminate the lease at least six months prior to the expiration of the initial term or the then-current renewal term, as applicable. The Lake Mariner site’s strategic location provides access to low-cost, predominantly zero-carbon power, making it an optimal hub for both bitcoin mining and HPC hosting operations.

Nautilus Cryptomine Facility

Prior to divesting its interest, TeraWulf operated bitcoin mining activities at the Nautilus Cryptomine Facility, located in Berwick, Pennsylvania. The facility was operated under a ground lease agreement between Nautilus and Cumulus Data LLC (“Cumulus Data”), an affiliate of Talen Energy Corporation. The lease covered the site of the Nautilus Cryptomine Facility for an initial five-year term, with two three-year extension options and an additional interim extension option of up to six and a half months.

TeraWulf began mining bitcoin at the Nautilus Cryptomine Facility in Q1 2023, with 50 MW of operational capacity as of December 31, 2024. On February 28, 2024, the Company exercised its option to increase its energy allocation by an additional 50 MW, bringing its total attributable capacity to 100 MW.

On March 1, 2024, Cumulus Data sold substantially all its assets to an unaffiliated third party, including the land leased to Nautilus under the ground lease. In connection with the asset sale, the Nautilus ground lease was assigned to the purchaser of the assets, with no changes to its terms and conditions. Subsequently, on October 2, 2024, TeraWulf sold its entire 25% equity interest in Nautilus to Cumulus Coin LLC, allowing the Company to reallocate capital toward the expansion of its wholly owned digital infrastructure at Lake Mariner and its high-performance computing strategy.