Legal Proceedings

The Company is not currently involved (and has not been involved in recent periods) in any litigation matters. However, the Company is currently in discussions/negotiations with its creditors, as described in Management’s Discussion and Analysis, Note C. These negotiations could escalate to litigation if a mutually satisfactory resolution is not achieved.

As is described in the Company’s Financial Statements included herein and discussed above in Management’s Discussion and Analysis, Note C, the Company’s on-going difficulties raising needed funds for its operations/activities over the past 2 years has rendered the Company unable to meet its current creditor obligations on a timely basis. The Company has engaged in discussion/negotiation with its larger creditors (including its largest creditor--- the primary contractor on the Initial Project) but has been unable to reach agreements regarding payments due to the uncertainty as to if, when and how much funding the Company will be able to raise in future periods. As a result, Hamstra Builders, the primary contractor filed a mechanics lien in Indiana (as did its largest sub-contractor, Dilling Group) and other creditors are threatening to commence litigation and/or repossess/remove leased equipment.

On April 16, 2025, the Company was served a summons by Hamstra Builders, Inc. (“Hamstra”) along with three other defendants: Bion Technologies, Inc. (“Biontech”), Bion 3G-1, LLC (“3G-1”), both entities of Bion Environmental Technologies, Inc., and North Prairie Holdings, LLC (‘NPHLLC”) the property lessor. The Hamstra suit is related to the Notice of Intent to file a Mechanic’s Lien, that was filed April 16, 2024, and has been disclosed in our public filings since that date. Bion has retained counsel in Indiana to represent the company in these actions. Hamstra is seeking to recover $1,494,513 in unpaid invoices related to the construction of Bion’s Ammonia Recovery System at Fair Oaks, Indiana. This sum includes $653,915 owed to Dilling Group, Inc., a subcontractor of Hamstra. Dilling filed suit to recover that amount on March 31, 2025, which was disclosed in Bion’s 8-k, dated April 7, 2025.

The Company currently is not involved in any other material litigation or similar events.