Liability for Service Interruptions
The tariff provisions under which CECONY provides electric, gas and steam service, and O&R provides electric and gas service, limit each company’s liability to pay for damages resulting from service interruptions to circumstances resulting from its gross negligence or willful misconduct. Under RECO's tariff provisions for electric service, the company is not liable for interruptions that are due to causes beyond its control.
CECONY’s and O&R’s tariffs for electric and gas service also provide for compensation to residential and small business customers that experience widespread prolonged outages lasting more than seventy-two consecutive hours, subject to certain exceptions, including: for residential customers, a bill credit of $25 for each twenty-four hour period of service outage beyond the first seventy-two consecutive hour outage; for residential and small business customers, reimbursement for food spoilage of up to $540; and reimbursement of affected residential customers for prescription medicine spoilage losses without limitation. Any such costs incurred by utilities are not recoverable from customers. Utilities may petition the NYSPSC to request a waiver of the requirement that it compensate customers after widespread prolonged outages. CECONY’s electric tariff requires it to also compensate customers for certain other service outages resulting from malfunctions in the company’s lines and cable of 33 kV or less or associated equipment, including, for residential customers, up to $580 for food spoilage and actual losses for prescription medicine losses, and for all other customers, up to $11,460 for losses of perishable merchandise.
The NYSPSC has approved a scorecard for use as a guide to assess electric utility performance in restoring electric service during outages that result from a major storm. The scorecard could also be applied by the NYSPSC for other outages or actions. The scorecard includes performance metrics in categories for preparation, operations response, and communications.
Each New York electric utility is required to submit to the NYSPSC annually an emergency response plan for the reasonably prompt restoration of service in the case of widespread outages in the utility’s service territory due to storms or other events beyond the control of the utility. If, after evidentiary hearings or other investigatory proceedings, the NYSPSC finds that the utility failed to reasonably implement its plan during an event, the NYSPSC may impose penalties or deny recovery of any part of the service restoration costs caused by such failure. In April 2024, the NYSPSC approved CECONY’s and O&R's emergency response plans. In December 2024, CECONY and O&R each submitted updated emergency response plans for 2025.