Clean Energy Future
New York State’s Climate Leadership and Community Protection Act
In 2019, New York State enacted the Climate Leadership and Community Protection Act (CLCPA) that established a goal of 70 percent of the electricity procured by load serving entities regulated by the NYSPSC to be produced by renewable energy systems by 2030 and requires the statewide electrical demand system to have zero emissions by 2040. The law also codified state targets for energy efficiency (end-use energy savings of 185 trillion British thermal units below 2025 energy-use forecast), offshore wind (9,000 MW by 2035), solar (6,000 MW by 2025) and energy storage (3,000 MW by 2030, that was subsequently increased by the NYSPSC to 6,000 MW by 2030). See “Energy Storage,” below. The CLCPA established a climate action council that made recommendations for meeting the statewide greenhouse gas (GHG) emission reduction requirements through displacing fossil-fuel fired electricity with renewable electricity, transitioning heating and transportation to lower GHG impact fuels (including substantial electrification), implementing energy efficiency measures and providing 35 percent to 40 percent of the benefits of CLCPA-related investments to disadvantaged communities. As required by the law, the New York State Department of Environmental Conservation (NYSDEC) adopted regulations establishing statewide GHG emissions limits that are 60 percent of 1990 emissions levels by 2030 and 15 percent of 1990 emissions by 2050. The Utilities are unable to predict the impact on them of the implementation of this law.
CECONY and O&R have been required to obtain renewable energy credits (RECs) and zero-emissions credits (ZECs) for their full-service customers since 2017. In October 2020, the NYSPSC, in response to the CLCPA, established a new RECs program to support increased renewable energy availability in New York City for which the costs would be borne by load serving entities across New York State on a volumetric basis. Load serving entities may satisfy their REC obligation by either purchasing RECs acquired through central procurement by the New York State Energy Research and Development Authority (NYSERDA), by self-supply through direct purchase of tradable RECs, or by making alternative compliance payments. Load serving entities purchase ZECs from NYSERDA at prices determined by the NYSPSC. In April 2022, the NYSPSC issued an order approving contracts between NYSERDA and two project sponsors selected by NYSERDA to provide RECs that support transmission lines bringing renewable energy directly to New York City (Clean Path New York and H.Q. Energy Services (U.S.) Inc.) that anticipate in-service dates of 2027 and 2026, respectively. Both projects have submitted requests to the NYISO to interconnect to CECONY’s high-voltage transmission system. In December 2024, NYSERDA and Clean Path NY terminated their REC contract by mutual consent. Also in December 2024, New York Power Authority (NYPA), the project’s sponsor who had proposed to develop the project in partnership with a joint venture filed a petition with the NYSPSC to develop the project as a NYPA priority transmission project.
In May 2024, CECONY filed its inaugural annual Investing in Disadvantaged Communities (DACs) Report, as required by the NYSPSC. The report summarizes the impacts of CECONY's investments in DACs within the company’s service territory, based on 2023 data. The report includes, among other things, building electrification and energy efficiency initiatives, as well as data related to the company’s long-running electric and gas operations. DAC locations were identified by New York State in connection with the implementation process for the CLCPA.
In September 2024, the NYSPSC issued an order evaluating the combined gas system long-term plan (the GSLTP) filed by the Utilities in November 2023. The order directs the Utilities to make additional filings to further the process of decarbonizing their gas systems and achieving the GHG emission reduction targets established in the CLCPA. These additional filings include, among other things, a proposal for a demand response program; a non-pipes alternatives deployment plan; a report on pipeline safety, including records to substantiate maximum allowable operating pressure in certain pipe segments; a definition of hard-to-electrify customers; reports on the benefits to, and impacts on, DACs; and a bill impact analysis that reflects reduced natural gas usage over a 20-year period for every service classification. The order also directs the Utilities to include certain information in their annual updates to the GSLTP and in their next GSLTP, due 2027, such as increases in electric load and associated reliability impacts and a description of a scenario that meets all load growth with non-pipe alternatives rather than additional infrastructure, and for the Utilities to identify a preferred pathway among the three pathways set forth in the GSLTP.
In November 2024, the FERC approved an August 2024 settlement agreement regarding CECONY’s return on equity for transmission projects. The settlement agreement provides for a formula rate to the NYISO tariff to enable CECONY to recover the costs and a return on equity of: (1) 10.6 percent for transmission projects that CECONY exercises its right of first refusal; (2) 10.85 percent for all other transmission projects selected by the NYISO to meet a public policy transmission need; and (3) the lower of the NYSPSC-determined rates or 10.6 percent for transmission projects needed to meet local New York State climate and renewable energy goals. Parties to the settlement agreement are restricted from seeking to challenge the return on equity levels for five years.
Also in November 2024, CECONY, pursuant to the NYSPSC’s August 2024 order instituting a proceeding that directed New York utilities, including CECONY and O&R, to proactively identify grid upgrades needed to meet new demand from transportation and building heating electrification across New York State (the Proactive Planning Proceeding), requested that the NYSPSC approve nine urgent projects totaling $856 million. CECONY requested that the NYSPSC authorize the urgent projects no later than March 2025. O&R did not make an urgent project filing because its November 2024 Joint Proposal included projects that would have otherwise been considered urgent. See “Rate Plans – O&R New York Electric” in Note B to the financial statements in Item 8.
In November and December 2024, New York utilities, including CECONY and O&R, pursuant to the Proactive Planning Proceeding for building and vehicle electrification: (1) filed a proposed framework for the NYSPSC to use in evaluating proposed urgent projects, cost allocation and cost recovery, (2) proposed (for CECONY) nine urgent projects for approval by the NYSPSC and (3) proposed a long-term coordinated planning process framework to study and identify necessary upgrades to support electrification.
Also in December 2024, the FERC approved a September 2024 settlement agreement regarding O&R’s return on equity for transmission projects. The settlement agreement provides for a formula rate to the NYISO tariff to enable O&R to recover the costs and a return on equity of: (1) 10.5 percent for transmission projects that O&R exercises its right of first refusal; (2) 10.85 percent for all other transmission projects selected by the NYISO to meet a public policy transmission need; and (3) the lower of the NYSPSC-determined rates or 10.6 percent for transmission projects needed to meet local New York State climate and renewable energy goals. Parties to the settlement agreement are restricted from seeking to challenge the return on equity levels for five years.
In January 2025, CECONY published its integrated long-range plan (ILRP) for the clean energy transition. The ILRP sets forth CECONY’s planning and investment strategy to provide safe, reliable and resilient service to customers and to support the decarbonization of energy use for electric, gas and steam customers, aligning with the greenhouse gas emissions reduction targets mandated by the CLCPA. Meeting the goals of the CLCPA will require capital expenditures above historic norms. While the details of CECONY’s investments will continue to be addressed in its rate cases or other filings, subject to the approval of the NYSPSC, CECONY projects that $72 billion of capital expenditures will be needed between 2025 and 2034 to implement its strategy.
Offshore Wind
In an effort to meet the CLCPA’s offshore wind goals, load serving entities, such as CECONY and O&R, will be required to purchase offshore wind renewable energy credits beginning in 2026 when NYSERDA's offshore wind projects are expected to begin operation.
NYSERDA has issued competitive solicitations for offshore wind energy resulting in two projects that are in development, Sunrise Wind (924 MW), a project that began construction in June 2024 and is expected to enter commercial operation in 2026 and Empire Wind 1 (810 MW), a project that is expected to enter commercial operation in 2027 and connect to the New York City electrical grid at CECONY’s Gowanus substation. In March 2024, FERC approved the interconnection agreement among Empire Offshore Wind LLC, the NYISO and CECONY. In May 2024, the NYSPSC approved a certificate of public convenience and necessity to allow construction of Empire Wind 1 to begin. In February 2025, the NYSPSC granted final approval of Empire Offshore Wind LLC's petition to construct and operate the New York offshore and onshore transmission facilities for Empire Wind 1. At December 31, 2024, New York has one operating offshore wind farm that was awarded a contract by LIPA, the South Fork Wind Farm (132 MW). See “Federal Regulation,” above.
Building Electrification and Energy Efficiency
In January 2020, and updated in August 2022, the NYSPSC issued an order directing energy efficiency targets and budgets for New York utilities. The order approved electric and gas energy efficiency programs and heat pump budgets for building electrification, and associated targets, for the years 2020 through 2025 to meet the NYSPSC’s goal of reducing electric use by 3 percent annually and gas use by 1.3 percent annually by 2025. The order and subsequent update authorized budgets for the years 2020 through 2025 for: electric energy efficiency programs of $688 million and $71 million for CECONY and O&R, respectively; gas energy efficiency programs of $338 million and $17 million for CECONY and O&R, respectively; and heat pump programs of $1,106 million and $15 million for CECONY and O&R, respectively. CECONY’s current electric and gas rate plans allow it to recover the costs of heat pumps for building electrification and energy efficiency expenditures, including a full rate of return, in rates from customers. See Note B to the financial statements in Item 8.
In November 2023, and updated in January 2024, CECONY and O&R filed preliminary proposals for energy efficiency and heat pump programs for 2026-2030 with aggregate budgets of approximately $2,744 million and $129 million, respectively. The aggregate amounts are comprised of average annual budgets of up to: $373 million and $22 million for electric energy efficiency and heat pump programs for CECONY and O&R, respectively, $150 million and $4 million for gas energy efficiency programs for CECONY and O&R, respectively, and $26 million for steam energy efficiency programs for CECONY. These amounts are subject to approval by the NYSPSC.
Electric Vehicles
In July 2020, the NYSPSC established light-duty electric vehicle make-ready and other infrastructure programs that included budgets of $290 million and $24 million for CECONY and O&R, respectively, through 2025. In November 2023, the light-duty infrastructure and other programs, including medium and heavy-duty make-ready pilot projects and a new micromobility infrastructure incentive program, were expanded to approximately $823 million for CECONY and $56 million for O&R, with the ability to extend beyond 2025. The NYSPSC authorized CECONY and O&R to recover these costs, including a full rate of return, through surcharge mechanisms and subsequently in rates from customers.
In July 2022, the NYSPSC issued an order that provides CECONY and O&R with up to a total of $31 million and $5.8 million, respectively, through 2025, for implementation of residential vehicle managed charging programs and administration costs. The NYSPSC authorized CECONY and O&R to recover these costs through surcharge mechanisms. The order also provides CECONY and O&R with authorization to offer incentives to encourage electric vehicle charging to occur overnight and during off-peak times totaling approximately $71.8 million and $8.2 million, respectively, through 2025, that would be recovered through the respective company’s revenue reconciliation mechanisms.
In October 2022, the NJBPU approved RECO’s electric vehicle make-ready program that includes a budget of $7.6 million through 2026 for electric vehicle infrastructure and related program costs. The NJBPU authorized RECO to recover these costs, including a full rate of return, in rates from customers.
In November 2023, the NYSPSC issued an order that provides CECONY and O&R with up to $432 million and $18 million through 2026, respectively, for the implementation of commercial managed charging programs and demand charge rebates, participant incentives and administration costs. The NYSPSC authorized CECONY and O&R to recover these costs, including a full rate of return, through surcharge mechanisms and subsequently in rates from customers.
Energy Storage
In June 2024, the NYSPSC issued an order adopting an updated roadmap for achieving 6,000 MW of statewide energy storage resource deployment by 2030 and recognized the need for additional statewide energy storage of 12,000 MW by 2040 and 17,000 MW by 2050. The NYSPSC directed New York utilities, including CECONY and O&R, to study the potential of energy storage to provide non-market transmission and distribution services and identify services for which energy storage is suitable.
CECONY owns and operates two energy storage projects located in Ozone Park, Queens and Fox Hills, Staten Island that are designed to store 1.5 MW/12 MWh and 7.5 MW/30 MWh of energy, respectively. A third energy storage project is under construction in Brownsville, Brooklyn that is designed to store 5.8 MW of energy and that is expected to be completed in 2025. CECONY has procured 115 MW of utility dispatch rights from energy storage projects, is negotiating contracts for additional storage projects and has released a request for proposal for additional utility dispatch rights. The long-term contracts provide CECONY with the right to dispatch energy from the storage projects for both wholesale market and grid purposes. O&R owns and operates an energy storage project located in Pomona, New York that is designed to store 3 MW of energy. O&R is evaluating bids from storage developers for utility dispatch rights. The Utilities expect to recover the cost of energy storage services, including a full rate of return, in rates and surcharges from customers.
Thermal Energy Networks
In April 2024, the NYSDPS approved CECONY’s and O&R’s December 2023 Stage 1 filings (Project Scope, Feasibility, and Stakeholder Engagement) for utility-scale thermal energy network pilot projects. The NYSDPS also confirmed CECONY and O&R are authorized to incur costs of $17.1 million and $4.6 million, respectively, through the completion of Stage 2 (Pilot Project Engineering Design and Customer Protection Plan). These projected costs are within the budgets previously proposed by CECONY and O&R in December 2023 of $255 million and $46 million, respectively. In December 2024, the NYSPSC issued an order approving CECONY’s May 2024 petition seeking $6 million for certain unaddressed costs that are necessary to complete Stage 2 of its utility thermal energy network pilot projects, in addition to the $17.1 million described above. The remaining proposed budget amounts are subject to approval by the NYSPSC.
Distribution System and Distributed Resources
The NYSPSC is directing development by New York electric utilities of a distributed system platform to manage and coordinate distributed energy resources in their service areas under NYSPSC regulation and to provide customers, together with third parties, with data and tools to better manage their energy use. The NYSPSC has required the Utilities to file distributed system implementation plans and ordered the Utilities to develop demonstration projects to inform distributed system platform business models. As of December 31, 2024, CECONY and O&R had three and one active demonstration projects, respectively.
The NYSPSC approved CECONY’s and O&R’s advanced metering infrastructure (AMI) installation plans for their electric and gas delivery businesses, at a cost of $1,285 million and $98.5 million, respectively, and such work was completed in 2024 and 2020, respectively.
The NYSPSC began to change compensation for DERs and place limits on net energy metering (NEM) in 2015. In New York, NEM compensates kilowatt-hours exported to the electric distribution system at the full-service rate for production, delivery, taxes and fees. NYSPSC’s policy is to phase in changes to limit annual bill increases on non-participating customers to two percent. In addition, NEM projects interconnected on or after January 1, 2022 are charged for their share of energy efficiency and other public policy benefit programs.
New York City’s Clean Energy Goals
In 2014, New York City announced a goal to reduce GHG emissions 80 percent below 2005 levels by 2050. In May 2019, New York City enacted a package of legislation known as the Climate Mobilization Act, that includes provisions intended to reduce GHG emissions from large buildings by 40 percent from 2005 levels by 2030. Building owners may achieve compliance through operational changes, building retrofits, the purchase of GHG offsets, the purchase of renewable energy credits and the use of clean distributed energy resources. CECONY is unable to predict the impact on it of the implementation of this law.
Federal Regulation of GHG Emissions
Section 111 of the Clean Air Act authorizes the United States Environmental Protection Agency (EPA) to set standards of performance (emissions limits) for new sources of air pollution, including GHG emissions, and establish guidelines for states to issue standards of performance for existing sources. These standards of performance are based on technology that the EPA determines to be the best system of emission reduction (BSER).
In April 2024, the EPA issued a final Section 111 rule (Section 111 Rule) regulating GHG emissions from new electric-generating gas-fired combustion turbines and existing coal, oil, and gas-fired boilers used to generate electricity. The Section 111 Rule did not cover existing electric-generating gas-fired combustion turbines, which the EPA deferred to a potential future rulemaking. The Section 111 Rule included carbon capture and sequestration (CCS) at a 90% capture rate as the BSER for certain new gas-fired combustion turbines and certain existing coal-fired boilers beginning in 2032. A future rule covering existing gas-fired combustion turbines could include this CCS BSER and impact CECONY’s existing gas-fired combustion turbines. After the EPA issued the Section 111 Rule, petitioners challenged it in the United States Court of Appeals for the District of Columbia Circuit (D.C. Circuit) on a number of grounds. Con Edison, as part of a coalition of public and private utilities, intervened in this litigation, arguing that the EPA had the authority to set the BSER, but the coalition took no position as to whether CCS was achievable in the timeframe set forth in the Section 111 Rule. In December 2024, the D.C. Circuit heard oral argument in the case. Given the pending litigation over the Section 111 Rule, the Companies are unable to predict the rule’s impact, if any, on them.
See "Federal Regulation," above.