CONSOLIDATED EDISON INC
For the period ended Dec 31, 2023. Filed Feb 15, 2024.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2023 · Filed Feb 15, 2024
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Introduction
This introduction contains certain information about Con Edison and its subsidiaries, including CECONY. This introduction is not a summary and should be read together with, and is qualified in its entirety by reference to, the more detailed information appearing elsewhere or incorporated by reference in this report.
Con Edison’s mission is to provide energy services to our customers safely, reliably, efficiently and in keeping with our vision for a clean energy future; to provide a workplace that embraces diversity and inclusion and allows employees to realize their full potential; to provide a fair return to our investors; and to improve the quality of life in the communities we serve. The company has ongoing programs designed to support each component of its mission, including initiatives focused on safety, operational excellence and the customer experience.
Con Edison is a holding company that owns:
Consolidated Edison Company of New York, Inc. (CECONY), which provides electric service and gas service in New York City and Westchester County and steam service in parts of Manhattan;
Orange & Rockland Utilities, Inc., which along with its New Jersey electric utility subsidiary, Rockland Electric Company (together referred to herein as O&R), provides electric service in southeastern New York and northern New Jersey and gas service in southeastern New York (O&R, together with CECONY referred to as the Utilities); and
Con Edison Transmission, Inc., which through its subsidiaries, invests in electric transmission projects supporting Con Edison’s effort to transition to clean, renewable energy and through joint ventures manages both electric and gas assets while seeking to develop electric transmission projects (Con Edison Transmission, Inc., together with its subsidiaries referred to as Con Edison Transmission).
Con Edison anticipates that the Utilities, which are subject to extensive regulation, will continue to provide substantially all of its earnings over the next few years. The Utilities have approved rate plans that are generally designed to cover each company’s cost of service, including capital and other costs of each company’s energy delivery systems. The Utilities recover from their full-service customers (who purchase energy from them), generally on a current basis, the cost the Utilities pay for energy and charge all of their customers the cost of delivery service. See "Utility Regulation" in Item 1, "Risk Factors" in Item 1A and "Rate Plans" in Note B to the financial statements in Item 8.
Significant Developments and Outlook
Con Edison reported 2023 net income of $2,519 million or $7.25 a share compared with $1,660 million or $4.68 a share in 2022. Adjusted earnings were $1,762 millionor $5.07 ashare in 2023 compared with $1,620 million or $4.57 a share in 2022. See “Results of Operations” in Item 7 and “Non-GAAP Financial Measures,” below.
In 2023, the Utilities invested $4,379 million to upgrade and reinforce their energy delivery systems and Con Edison Transmission invested $49 million primarily in electric transmission. For 2024, 2025, 2026, 2027 and 2028, the Utilities expect to invest $4,822 million, $5,212 million, $5,879 million, $5,874 million and $5,867 million, respectively, for their energy delivery systems and Con Edison Transmission expects to invest $27 million, $31 million, $108 million, $113 million and $119 million, respectively, primarily in electric transmission. See "Capital Requirements and Resources - Capital Requirements" in Item 1.
Con Edison plans to meet its capital requirements for 2024 through 2028 through internally-generated funds and the issuance of long-term debt and common equity. See “Capital Requirements and Resources - Capital Requirements” in Item 1. Con Edison's plans include the issuance of up to $3,250 million of long-term debt in 2024 and up to $1,000 million of long-term debt in 2025, including for maturing securities, at the Utilities and approximately $6,000 million in aggregate of long-term debt, including for maturing securities, at the Utilities during 2026 through 2028. Except for equity issued under its dividend reinvestment, employee stock purchase and long-term incentive plans, Con Edison does not plan to issue common equity in 2024 and plans to issue common equity of approximately $1,300 million in 2025 and up to $2,800 million in aggregate during 2026 through 2028. Con Edison’s estimates of its capital requirements and related financing plans reflect information available and assumptions at the time the statements are made and include, among other things, the assumptions that Con Edison’s non-utility gas transmission investments remain unchanged through 2028 and the Utilities’ forecasted capital investments and financing plans through 2028 are approved by the New York State Public Service Commission (NYSPSC). Actual developments and the timing and amount of funding may differ materially.
CECONY forecasts average annual increase in peak demand in its service area at design conditions over the next five years for electricity to be approximately 0.7 percent and an average annual decrease in gas and steam peak demand in its service area at design weather conditions over the next five years to be approximately 0.8 percent and 0.5 percent, respectively. O&R forecasts an average annual increase in electric peak demand in its service area at design conditions over the next five years to be approximately 2.0 percent and average annual decrease in gas peak demand in its service area over the next five years at design conditions to be approximately 0.2 percent. See “The Utilities” in Item 1.
In March 2023, Con Edison completed the sale of all of the stock of Con Edison Clean Energy Businesses, Inc. (the “Clean Energy Businesses”). See Note W and Note X to the financial statements in Item 8.
In June 2023, the New York Independent System Operator selected the Propel NY Energy transmission project that was jointly proposed by New York Transco LLC (New York Transco) and the New York Power Authority. Con Edison Transmission owns a 41.7 percent interest in New York Transco’s share of the Propel NY Energy project, a 90-mile electric transmission project with an in-service date of 2030. See "Con Edison Transmission," below.
During the second quarter of 2023, construction of New York Transco’s New York Energy Solution (NYES) project to relieve transmission congestion between upstate and downstate was completed. Construction of the associated Dover Station, an additional network upgrade to support the NYES project, has not been completed. Con Edison Transmission owns a 45.7 percent interest in NYES. See "Con Edison Transmission," below.
In July 2023, the NYSPSC approved the February 2023 joint proposal among CECONY, the New York State Department of Public Service (NYSDPS) and other parties for electric and gas rate plans for the three-year period January 1, 2023 through December 31, 2025. See "Rate Plans” in Note B to the financial statements in Item 8.
In November 2023, the NYSPSC approved the September 2023 joint proposal among CECONY, the NYSDPS and other parties for a steam rate plan for the three-year period November 1, 2023 through October 31, 2026 that includes, among other provisions, a weather normalization adjustment to reflect normal weather conditions during the heating season. See "Rate Plans” in Note B to the financial statements in Item 8.
In November 2023, CECONY and O&R filed petitions with the NYSPSC for approval to make long-term investments of $903 million and $411 million, respectively, between 2025 and 2029 to protect their electric systems from climate change. See “Clean Energy Future,” below.
In January 2024, O&R filed a request with the NYSPSC for electric and gas rate increases of $18.1 million and $14.4 million, respectively, effective January 2025. See "Rate Plans" in Note B to the financial statements in Item 8.
In January 2024, the NYSPSC approved CECONY's August 2023 petition requesting authorization and cost recovery to construct two new substations in Jamaica, Queens (the Reliable Clean City - Idlewild Project) with an estimated cost of $1,200 million and an estimated in-service date of May 2028. See "Rate Plans" in Note B to the financial statements in Item 8.
The NYSPSC continued its focused operations audit of the Utilities related to income tax accounting. The audit is investigating the Utilities’ inadvertent understatement of a portion, the amount of which may be material, of their calculation of total federal income tax expense for ratemaking purposes. The understatement was related to the calculation of plant retirement-related cost of removal. See "Other Regulatory Matters" in Note B to the financial statements in Item 8.