CONSOLIDATED EDISON INC
For the period ended Dec 31, 2023. Filed Feb 15, 2024.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2023 · Filed Feb 15, 2024
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Clean Energy Future
New York State’s Climate Leadership and Community Protection Act
In 2019, New York State enacted the Climate Leadership and Community Protection Act (CLCPA) that established a goal of 70 percent of the electricity procured by load serving entities regulated by the NYSPSC to be produced by renewable energy systems by 2030 and requires the statewide electrical demand system to have zero emissions by 2040. The law also codified state targets for energy efficiency (end-use energy savings of 185 trillion British thermal units below 2025 energy-use forecast), offshore wind (9,000 MW by 2035), solar (6,000 MW by 2025) and energy storage (3,000 MW by 2030). The CLCPA established a climate action council that made recommendations for meeting the statewide greenhouse gas (GHG) emission reduction requirements through displacing fossil-fuel fired electricity with renewable electricity, transitioning heating and transportation to lower GHG impact fuels (including substantial electrification), implementing energy efficiency measures and providing 35 percent to 40 percent of the benefits of CLCPA-related investments to disadvantaged communities. As required by the law, the New York State Department of Environmental Conservation (NYSDEC) adopted regulations establishing statewide GHG emissions limits that are 60 percent of 1990 emissions levels by 2030 and 15 percent of 1990 emissions by 2050. The Utilities are unable to predict the impact on them of the implementation of this law.
CECONY and O&R have been required to obtain renewable energy credits (RECs) and zero-emissions credits (ZECs) for their full service customers since 2017. In October 2020, the NYSPSC, in response to the CLCPA, established a new RECs program to support increased renewable energy availability in New York City for which the costs would be borne by load serving entities across New York State on a volumetric basis. Load serving entities may satisfy their REC obligation by either purchasing RECs acquired through central procurement by the New York State Energy Research and Development Authority (NYSERDA), by self-supply through direct purchase of tradable RECs, or by making alternative compliance payments. Load serving entities purchase ZECs from NYSERDA at prices determined by the NYSPSC. In April 2022, the NYSPSC issued an order approving contracts between NYSERDA and two project sponsors selected by NYSERDA to provide RECs directly to New York City (Clean Path New York and H.Q. Energy Services (U.S.) Inc.) that anticipate in-service dates of 2026 and 2027, respectively.
Both projects have submitted requests to the NYISO to interconnect to CECONY’s high-voltage transmission system.
In June 2023, the NYISO selected the Propel NY Energy transmission project that was jointly proposed by New York Transco and the New York Power Authority (NYPA). Con Edison Transmission has a 41.7 percent interest in New York Transco’s share of the Propel NY Energy project, a 90-mile electric transmission project with an in-service date of 2030. The project is expected to enable delivery of a minimum of 3,000 MW of offshore wind electricity, increase high voltage transmission connections between Long Island and the rest of New York State and provide New Yorkers with greater access to diverse energy resources. See "Con Edison Transmission," below.
Also in June 2023, CECONY filed a petition with FERC to add a formula rate to the NYISO tariff to enable CECONY to recover the costs of, and a return on investment for, two types of projects: (1) local transmission upgrades determined by the NYSPSC to be necessary or appropriate to meet the CLCPA goals of New York State and (2) any regulated transmission projects (or portions thereof) eligible for recovery under the NYISO’s public policy transmission planning process. For local transmission upgrades, CECONY proposed the return on equity to be the lower of the NYSPSC-determined rates or 10.87 percent. For NYISO projects, CECONY proposed a return on equity of 11.10 percent. CECONY anticipates that the formula rate, once in place, will be applied to recover the costs of the upgrades associated with the Propel NY Energy offshore wind project.
In November 2023, CECONY and O&R filed their combined gas system long-term plan. The Utilities’ plan has a 20-year horizon to achieve the greenhouse gas emissions reduction targets of the CLCPA and includes three pathways: (1) a reference pathway based on investments approved by the NYSPSC, (2) an alternate hybrid electric generation and low-carbon fuels pathway and (3) an alternate deep electrification pathway. The plan outlines objectives in clean energy, climate resilience, core service, and customer engagement and includes forecasts of annual customer bill charges. The plan concludes that gas sales and emissions in CECONY’s and O&R’s service territories are projected to fall in all three pathways.
Offshore Wind
In an effort to meet the CLCPA’s offshore wind goals, load serving entities, such as CECONY and O&R, will be required to purchase offshore wind renewable energy credits beginning in 2025 when projects are expected to begin operation.
In October 2023, NYSERDA announced that it selected three new offshore wind projects for contract negotiations, representing 4,032 MW of energy by 2030 One of the conditional awards, the Community Offshore Wind project, is expected to connect 1,314 MW of offshore wind electricity through CECONY’s Brooklyn Clean Energy Hub by 2030 (see “Electric Reliability Needs,” above) and another conditional award, the Excelsior Wind project, is expected to connect 1,314 MW of offshore wind electricity using the capability of the Propel NY Energy project. See "Con Edison Transmission," above.
Energy Efficiency
In January 2020, and updated in August 2022, the NYSPSC issued an order directing energy efficiency targets and budgets for New York utilities. The order approved electric and gas energy efficiency programs and heat pump budgets, and associated targets, for the years 2020 through 2025 to meet the NYSPSC’s goal of reducing electric use by 3 percent annually and gas use by 1.3 percent annually by 2025. The order and subsequent update authorized budgets for the years 2020 through 2025 for: electric energy efficiency programs of $688 million and $71 million for CECONY and O&R, respectively; gas energy efficiency programs of $338 million and $17 million for CECONY and O&R, respectively; and heat pump programs of $746 million and $15 million for CECONY and O&R, respectively. CECONY’s current electric and gas rate plans allow it to recover the costs of energy efficiency expenditures, including a full rate of return, in rates from customers. See Note B to the financial statements in Item 8.
In November 2023, and updated in January 2024, CECONY and O&R filed preliminary proposals for energy efficiency and heat pump programs for 2026-2030 with aggregate budgets of approximately $2,744 million and $129 million, respectively. The aggregate amounts are comprised of average annual budgets of up to: $373 million and $22 million for electric energy efficiency and heat pump programs for CECONY and O&R, respectively, $150 million and $4 million for gas energy efficiency programs for CECONY and O&R, respectively, and $26 million for steam energy efficiency programs for CECONY.
Electric Vehicles
In July 2020, the NYSPSC established light-duty electric vehicle make-ready and other infrastructure programs that included budgets of $290 million and $24 million for CECONY and O&R, respectively, through 2025. In November 2023, the light-duty infrastructure and other programs, including medium and heavy-duty make-ready pilot projects and a new micromobility infrastructure incentive program, were expanded to approximately $823 million for CECONY and $56 million for O&R, with the ability to extend beyond 2025. The NYSPSC authorized CECONY and O&R to recover these costs, including a full rate of return, through surcharge mechanisms and subsequently in rates from customers.
In July 2022, the NYSPSC issued an order that provides CECONY and O&R with up to a total of $31 million and $5.8 million, respectively, through 2025, for implementation of residential vehicle managed charging programs and administration costs. The NYSPSC authorized CECONY and O&R to recover these costs through surcharge mechanisms. The order also provides CECONY and O&R with authorization to offer incentives to encourage electric vehicle charging to occur overnight and during off-peak times totaling approximately $71.8 million and $8.2 million, respectively, through 2025, that would be recovered through the respective company’s revenue reconciliation mechanisms.
In October 2022, the NJBPU approved RECO’s electric vehicle make-ready program that includes a budget of $7.6 million through 2026 for electric vehicle infrastructure and related program costs. The NJBPU authorized RECO to recover these costs, including a full rate of return, in rates from customers.
In November 2023, the NYSPSC issued an order that provides CECONY and O&R with up to $432 million and $18 million, respectively, for the implementation of commercial managed charging programs and demand charge rebates, participant incentives and administration costs. The NYSPSC authorized CECONY and O&R to recover these costs, including a full rate of return, through surcharge mechanisms and subsequently in rates from customers.
Energy Storage
In December 2018, the NYSPSC issued an order establishing an energy storage goal of up to 3,000 MW of energy storage by 2030 with an interim objective of 1,500 MW by 2025. The order required CECONY and O&R to file implementation plans for a competitive procurement process to deploy 300 MW and 10 MW, respectively, of energy storage. CECONY and O&R filed their implementation plans in February 2019. CECONY is in contract negotiations with storage developers and O&R is evaluating bids from storage developers. The Utilities expect to recover the cost of energy storage services, including a full rate of return, in rates and surcharges from customers. In December 2022, NYSDPS and NYSERDA issued an updated storage roadmap that proposes to increase the storage goal from 3,000 MW to 6,000 MW by 2030. The proposal includes the recommendation that New York State’s utilities study the potential of energy storage to provide non-market transmission and distribution services and identify services that are cost-effective compared to traditional alternatives.
Thermal Energy Networks
In September 2023, the NYSPSC issued an order providing guidance on the development and implementation of utility-scale thermal energy network pilot projects throughout New York State. The order introduced a framework for the NYSPSC to evaluate whether the proposed pilot projects are in the public interest. In December 2023, CECONY and O&R filed pilot project proposals with budgets of $255 million and $46 million, respectively. The proposed pilots are subject to approval by the NYSPSC.
Distribution System and Distributed Resources
The NYSPSC is directing development by New York electric utilities of a distributed system platform to manage and coordinate distributed energy resources in their service areas under NYSPSC regulation and to provide customers, together with third parties, with data and tools to better manage their energy use. The NYSPSC has required the Utilities to file distributed system implementation plans and ordered the Utilities to develop demonstration projects to inform distributed system platform business models. As of December 31, 2023, CECONY and O&R had one shared active demonstration project, and individually, CECONY had four and O&R had three active demonstration projects.
The NYSPSC approved CECONY’s advanced metering infrastructure (AMI) installation plan for its electric and gas delivery businesses, subject to a cap on capital expenditures of $1,285 million. CECONY substantially completed its smart meter installations in 2023 and expects to complete its AMI installation plan in 2024. The NYSPSC also authorized O&R to expend $98.5 million to install AMI for its New York customers, which work was complete as of December 31, 2020.
The NYSPSC began to change compensation for DERs and place limits on net energy metering (NEM) in 2015. In New York, NEM compensates kilowatt-hours exported to the electric distribution system at the full-service rate for production, delivery, taxes and fees. NYSPSC’s policy is to phase in changes to limit annual bill increases on non-participating customers to two percent. In addition, NEM projects interconnected on or after January 1, 2022 are charged for their share of energy efficiency and other public policy benefit programs.
New York City’s Clean Energy Goals
In 2014, New York City announced a goal to reduce GHG emissions 80 percent below 2005 levels by 2050. In May 2019, New York City enacted a package of legislation known as the Climate Mobilization Act, that includes provisions intended to reduce GHG emissions from large buildings by 40 percent from 2005 levels by 2030. Building owners may achieve compliance through operational changes, building retrofits, the purchase of GHG offsets, the purchase of renewable energy credits and the use of clean distributed energy resources. CECONY is unable to predict the impact on it of the implementation of this law.
Federal Regulation
In June 2022, the U.S. Supreme Court issued a decision that restricts the authority of the United States Environmental Protection Agency (EPA) to establish GHG emission reduction measures under Section 111 of the federal Clean Air Act for technologies that reduce GHG emissions from fossil fuel combustion at the source. Con Edison, as part of a coalition of public and private utilities, was a party in the case and had argued that the U.S. Supreme Court should not adopt this restrictive statutory reading of the Clean Air Act. Depending on how it is implemented in future final EPA regulations, which are currently undergoing federal rulemaking, the U.S. Supreme Court’s decision could have potential cost implications for CECONY because it could limit its flexibility to use measures such as trading emissions allowances from higher emitting sources to lower emitting sources and averaging emissions across different sources, to cost-effectively meet federal GHG emissions limits for its limited portfolio of steam and electric generating assets. The decision could also indirectly impact CECONY's and O&R's initiatives to develop renewable energy sources. Certain CECONY electric generating units could be subject to the final rule, depending on its applicability criteria. The Companies are unable to predict the impact on them as a result of the decision or any final regulations that may be promulgated by the EPA.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.