Land Disputes

Pending - Sempra Infrastructure has been engaged in a long-running land dispute relating to property adjacent to and owned by its ECA Regas Facility (the facility, however, is not situated on the land that is the subject of this dispute). A claimant to the adjacent property filed suit to reinitiate an administrative procedure at SEDATU to obtain the property title for the disputed property, which title had previously been issued in a ruling by the federal Agrarian Court and subsequently reversed by a federal court in Mexico. In April 2021, the proceeding in the Agrarian Court concluded with the court ordering that the administrative procedure be restarted. The administrative procedure at SEDATU may continue if SEDATU decides to reopen the matter.

Resolved - A plaintiff filed a claim in the federal Agrarian Court that seeks to annul the property title for a portion of the land on which the ECA Regas Facility is situated and to obtain possession of a different parcel that allegedly overlaps with the site of the ECA Regas Facility. The proceeding, which seeks an order that SEDATU annul the ECA Regas Facility’s competing property title, was initiated in 2006 and, in July 2021, a decision was issued in favor of the ECA Regas Facility. The plaintiff appealed and, in February 2022, the appellate court confirmed the ruling in favor of the ECA Regas Facility and dismissed the appeal. The plaintiff filed a federal appeal against the appellate court ruling. In August 2024, the Federal Collegiate Circuit Court ruled in favor of the ECA Regas Facility. The plaintiff filed an appeal and, in May 2025, the Mexican Supreme Court dismissed the appeal, definitively resolving this matter.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.