Skip to main content

SEMPRA

For the period ended Dec 31, 2024. Filed Feb 25, 2025.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2024 · Filed Feb 25, 2025

SRE$78.77+0.8%Stored close · as of Nov 9, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

Environmental and Social Impact Permits

Environmental and Social Impact Permits. Several administrative challenges are pending before Mexico’s Secretariat of Environment and Natural Resources (the Mexican environmental protection agency) and Federal Tax and Administrative Courts, seeking revocation of the environmental impact authorization issued to the ECA Regas Facility in 2003. These cases generally allege that the conditions and mitigation measures in the environmental impact authorization are inadequate and challenge findings that the activities of the terminal are consistent with regional development guidelines.

In 2018 and 2021, three related claimants filed separate challenges in the federal district court in Ensenada, Baja California seeking revocation of the environmental and social impact permits issued by each of ASEA and SENER to ECA LNG authorizing natural gas liquefaction activities at the ECA Regas Facility, as follows:

In the first case, the court issued a provisional injunction against the permits in September 2018. In December 2018, ASEA approved modifications to the environmental permit that facilitate the development of the proposed natural gas liquefaction facility in two phases. In May 2019, the court canceled the provisional injunction. The claimant appealed the court’s decision to cancel the injunction but was not successful. The lower court’s ruling was favorable to the ECA Regas Facility, as the court determined that no harm has been caused to the plaintiff and dismissed the lawsuit. The claimant appealed and the appellate court’s ruling is pending.

In the second case, the initial request for a provisional injunction against the permits was denied. That decision was reversed on appeal in January 2020, resulting in the issuance of a new injunction against the permits that were issued by ASEA and SENER. This injunction has uncertain application absent clarification by the court. The claimants petitioned the court to rule that construction of natural gas liquefaction facilities violated the injunction and, in February 2022, the court ruled in favor of the ECA Regas Facility, holding that the natural gas liquefaction construction activities did not violate the injunction. The claimants appealed this ruling but were not successful. The lower court’s ruling was favorable to the ECA Regas Facility, as the court determined that no harm has been caused to the plaintiffs and dismissed the lawsuit. The claimants appealed and the appellate court’s ruling is pending.

In the third case, a group of residents filed a complaint in June 2021 against various federal and state authorities alleging deficiencies in the public consultation process for the issuance of the permits. The request for an initial injunction was denied. The claimants appealed this ruling but were not successful. The lower court’s ruling was favorable to the ECA Regas Facility, as the court determined that no harm has been caused to the plaintiffs and dismissed the lawsuit. The claimants appealed and the appellate court’s ruling is pending.

Port Arthur LNG

The PA LNG Phase 1 project holds two Clean Air Act Prevention of Significant Deterioration permits issued by the TCEQ, which we refer to as the “2016 Permit” and the “2022 Permit.” The 2022 Permit also governs emissions for the proposed PA LNG Phase 2 project. In November 2023, a panel of the U.S. Court of Appeals for the Fifth Circuit issued a decision to vacate and remand the 2022 Permit to the TCEQ for additional explanation of the agency’s permit decision. In February 2024, the court withdrew its opinion and referred the case to the Supreme Court of Texas to resolve the question of the appropriate standard to be applied by the TCEQ. In February 2025, the Supreme Court of Texas adopted Port Arthur LNG’s interpretation of the standard. Port Arthur LNG continues to litigate this matter before the U.S. Court of Appeals for the Fifth Circuit, which will apply the standard adopted by the Supreme Court of Texas. The 2022 Permit is effective during the pending litigation. The 2016 Permit was not the subject of, and is unaffected by, the pending litigation of the 2022 Permit. Construction of the PA LNG Phase 1 project is proceeding uninterrupted under existing permits, and we do not currently anticipate the pending litigation to materially impact the PA LNG Phase 1 project cost, schedule or expected commercial operations at this stage.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.