OGE ENERGY CORP.
For the period ended Sep 30, 2026. Filed Oct 28, 2026.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Sep 30, 2026 · Filed Oct 28, 2026
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Combined Notes to Condensed Financial Statements
COMBINED NOTES TO THE CONDENSED FINANCIAL STATEMENTS
Index of Combined Notes to Condensed Financial Statements
The Combined Notes to the Condensed Financial Statements are a combined presentation for OGE Energy and OG&E. The following table indicates the Registrant(s) to which each Note applies.
| OGE Energy | OG&E | |
| Note 1. Summary of Significant Accounting Policies | X | X |
|---|---|---|
| Note 2. Accounting Pronouncements | X | X |
| Note 3. Revenue Recognition | X | X |
| Note 4. Fair Value Measurements | X | X |
| Note 5. Stock-Based Compensation | X | X |
| Note 6. Income Taxes | X | X |
| Note 7. Common Equity | X | |
| Note 8. Long-Term Debt | X | X |
| Note 9. Credit Facilities and Short-Term Debt | X | X |
| Note 10. Retirement Plans and Postretirement Benefit Plans | X | X |
| Note 11. Report of Business Segments | X | |
| Note 12. Commitments and Contingencies | X | X |
| Note 13. Rate Matters and Regulation | X | X |
- Summary of Significant Accounting Policies
Organization
OGE Energy is a holding company whose primary investment provides electricity in Oklahoma and western Arkansas. OGE Energy's electric company operations are conducted through its wholly-owned subsidiary, OG&E, which generates, transmits, distributes and sells electric energy in Oklahoma and western Arkansas and are reported through OGE Energy's electric company business segment. OG&E's rates are subject to regulation by the OCC, the APSC and the FERC. OG&E was incorporated in 1902 under the laws of the Oklahoma Territory and is the largest electric company in Oklahoma, with a franchised service territory that includes Fort Smith, Arkansas and the surrounding communities. OG&E sold its retail natural gas business in 1928 and is no longer engaged in the natural gas distribution business.
The accounts of OGE Energy and its wholly-owned subsidiaries, including OG&E, are included in OGE Energy's condensed consolidated financial statements. All intercompany transactions and balances are eliminated in such consolidation.
Basis of Presentation
The condensed financial statements included herein have been prepared by the Registrants, without audit, pursuant to the rules and regulations of the Securities and Exchange Commission. Certain information and footnote disclosures normally included in financial statements prepared in accordance with GAAP have been condensed or omitted pursuant to such rules and regulations; however, the Registrants believe that the disclosures are adequate to prevent the information presented from being misleading.
In the opinion of management, all adjustments necessary to fairly present the financial position of the Registrants at September 30, 2026 and December 31, 2025, the results of the Registrants' operations for the three and nine months ended September 30, 2026 and 2025 and the Registrants' cash flows for the nine months ended September 30, 2026 and 2025 have been included and are of a normal, recurring nature except as otherwise disclosed. Management also has evaluated the impact of events occurring after September 30, 2026 up to the date of issuance of these condensed financial statements, and these statements contain all necessary adjustments and disclosures resulting from that evaluation.
Due to seasonal fluctuations and other factors, the Registrants' operating results for the three and nine months ended September 30, 2026 are not necessarily indicative of the results that may be expected for the year ending December 31, 2026 or for any future period. The condensed financial statements and notes thereto should be read in conjunction with the audited financial statements and notes thereto included in the Registrants'2025 Form 10-K.
Accounting Records
The accounting records of OG&E are maintained in accordance with the Uniform System of Accounts prescribed by the FERC and adopted by the OCC and the APSC. Additionally, OG&E, as a regulated electric company, is subject to accounting principles for certain types of rate-regulated activities, which provide that certain incurred costs that would otherwise be charged to expense can be deferred as regulatory assets, based on the expected recovery from customers in future rates. Likewise, certain actual or anticipated credits that would otherwise reduce expense can be deferred as regulatory liabilities, based on the expected flowback to customers in future rates. Management's expected recovery of deferred costs and flowback of deferred credits generally results from specific decisions by regulators granting such ratemaking treatment.
OG&E records certain incurred costs and obligations as regulatory assets or liabilities if, based on regulatory orders or other available evidence, it is probable that the costs or obligations will be included in amounts allowable for recovery or refund in future rates. The following table presents a summary of OG&E's regulatory assets and liabilities.
| September 30, | December 31, | |
|---|---|---|
| (In millions) | 2026 | 2025 |
| REGULATORY ASSETS | ||
| Current: | ||
| SPP cost tracker under recoveries (A) | $10.5 | $7.1 |
| Other (A) | 2.8 | 4.3 |
| Total current regulatory assets | $13.3 | $11.4 |
| Non-current: | ||
| Oklahoma deferred storm expenses | $193.2 | $224.7 |
| Oklahoma PISA deferred costs, net | 87.9 | 22.9 |
| Pension tracker | 82.0 | 88.7 |
| Benefit obligations regulatory asset | 81.3 | 85.6 |
| Arkansas Winter Storm Uri costs | 46.7 | 54.2 |
| Oklahoma SAP S/4 HANA deferred expenses | 16.2 | 16.5 |
| Sooner Dry Scrubbers | 14.9 | 15.5 |
| Oklahoma vegetation management program deferred costs | 14.8 | 13.9 |
| Arkansas capacity purchase power agreements | 10.7 | 6.7 |
| Arkansas deferred pension expenses | 7.9 | 9.3 |
| Unamortized loss on reacquired debt | 4.5 | 5.5 |
| COVID-19 impacts | 3.2 | 4.1 |
| Other | 8.9 | 9.6 |
| Total non-current regulatory assets | $572.2 | $557.2 |
| REGULATORY LIABILITIES | ||
| Current: | ||
| Oklahoma fuel clause over recoveries | $37.3 | $15.7 |
| Arkansas fuel clause over recoveries | 21.7 | 11.4 |
| Oklahoma Energy Efficiency Rider over recoveries (B) | 21.4 | 5.8 |
| Other (B) | 9.4 | 2.0 |
| Total current regulatory liabilities | $89.8 | $34.9 |
| Non-current: | ||
| Income taxes refundable to customers, net | $672.3 | $718.9 |
| Accrued removal obligations, net | 228.8 | 234.7 |
| Other | 4.5 | 3.5 |
| Total non-current regulatory liabilities | $905.6 | $957.1 |
(A)
Included in Other Current Assets in the condensed balance sheets.
(B)
Included in Other Current Liabilities in the condensed balance sheets.
Management continuously monitors the future recoverability of regulatory assets. When in management's judgment future recovery becomes impaired, the amount of the regulatory asset is adjusted, as appropriate. If OG&E were required to discontinue the applicationof accounting principles for certain types of rate-regulated activities for some or all of its operations, it could result in writing off the related regulatory assets or liabilities, which could have significant financial effects.
Allowance for Uncollectible Accounts Receivable
Customer balances are generally written off if not collected within six months after the final billing date. The allowance for uncollectible accounts receivable for OG&E is generally calculated by multiplying the last six months of electric revenue by the provision rate, which is based on a historical average of actual balances written off and is adjusted for current conditions and supportable forecasts as necessary. To the extent the historical collection rates, when incorporating forecasted conditions, are not representative of future collections, there could be an effect on the amount of uncollectible expense recognized. Also, a portion of the uncollectible provision related to fuel within the Oklahoma jurisdiction is being recovered through the fuel adjustment clause. The allowance for uncollectible accounts receivable is a reduction to Accounts Receivable in the condensed balance sheets and is included in Other Operation and Maintenance Expense in the condensed statements of income.
New business customers are required to provide a security deposit in the form of cash, bond or irrevocable letter of credit that is refunded when the account is closed or when certain requirements are met. New residential customers whose outside credit scores indicate an elevated risk are required to provide a security deposit that is refunded based on customer protection rules defined by the OCC and the APSC. The payment behavior of all existing customers is continuously monitored, and, if the payment behavior indicates sufficient risk within the meaning of the applicable utility regulation, customers will be required to provide a security deposit.
Accumulated Other Comprehensive Income (Loss)
The following tables present changes in the components of accumulated other comprehensive income (loss) attributable to OGE Energy during thenine months ended September 30, 2026 and 2025. All amounts below are presented net of tax.
| (In millions) | Pension Plan and Restoration of Retirement Income Plan | Postretirement Benefit Plans | Total |
|---|---|---|---|
| Balance at December 31, 2025 | $(10.0) | $7.4 | $(2.6) |
| Amounts reclassified from accumulated other comprehensive income (loss) | 0.4 | (0.3) | 0.1 |
| Balance at September 30, 2026 | $(9.6) | $7.1 | $(2.5) |
| (In millions) | Pension Plan and Restoration of Retirement Income Plan | Postretirement Benefit Plans | Total |
|---|---|---|---|
| Balance at December 31, 2024 | $(8.8) | $6.1 | $(2.7) |
| Amounts reclassified from accumulated other comprehensive income (loss) | 0.4 | (0.1) | 0.3 |
| Balance at September 30, 2025 | $(8.4) | $6.0 | $(2.4) |
The following table presents significant amounts reclassified out of accumulated other comprehensive income (loss) attributable to OGE Energy by the respective line items in net income during thethree and nine months ended September 30, 2026 and 2025.
| Details about Accumulated Other Comprehensive Income (Loss) Components · Amount Reclassified from Accumulated Other Comprehensive Income (Loss) · Affected Line Item in OGE Energy's Statements of Income | |||||
|---|---|---|---|---|---|
| Three Months Ended · Nine Months Ended | |||||
| September 30, · September 30, | |||||
| (In millions) · 2026 · 2025 · 2026 · 2025 | |||||
| Amortization of Pension Plan and Restoration of Retirement Income Plan items: | |||||
| Actuarial losses | $(0.1) | $(0.1) | $(0.3) | $(0.3) | (A) |
| Prior service cost | — | (0.1) | (0.2) | (0.2) | (A) |
| (0.1) | (0.2) | (0.5) | (0.5) | Income Before Taxes | |
| — | — | (0.1) | (0.1) | Income Tax Expense | |
| $(0.1) | $(0.2) | $(0.4) | $(0.4) | Net Income | |
| Amortization of postretirement benefit plans items: | |||||
| Actuarial gains | $0.1 | $0.1 | $0.3 | $0.2 | (A) |
| 0.1 | 0.1 | 0.3 | 0.2 | Income Before Taxes | |
| — | — | — | 0.1 | Income Tax Expense | |
| $0.1 | $0.1 | $0.3 | $0.1 | Net Income | |
| Total reclassifications for the period, net of tax | $— | $(0.1) | $(0.1) | $(0.3) | Net Income |
(A)
These accumulated other comprehensive income (loss) components are included in the computation of net periodic benefit cost (see Note 10 for additional information).
- Accounting Pronouncements
In November 2024, the Financial Accounting Standards Board issued ASU 2024-03, "Income Statement - Reporting Comprehensive Income - Expense Disaggregation Disclosures." The amendments in this update improve financial reporting by requiring disclosure of additional information about specific expense categories in the notes to financial statements on an annual and interim basis. This standard is effective for fiscal years beginning after December 15, 2026 and interim periods beginning after December 15, 2027. Early adoption is permitted. The Registrants are evaluating the impact of this standard and do not believe it will have a material impact on their financial statement disclosures.
In September 2025, the Financial Accounting Standards Board issued ASU 2025-06, "Intangibles - Goodwill and Other - Internal-Use Software." The targeted improvements in this update aim to better align current software development processes when considering capitalization of internal-use software costs. This standard is effective for fiscal years beginning after December 15, 2027 and interim periods within that period. Early adoption is permitted. The Registrants are evaluating the impact of this standard on their financial statements.
In May 2026, the Financial Accounting Standards Board issued ASU 2026-02, "Environmental Credits and Environmental Credit Obligations (Topic 818)." The amendments in this update provide recognition, measurement, presentation, and disclosure requirements for all entities that generate, purchase, or receive environmental credits or have a regulatory compliance obligation that may be settled with environmental credits. This standard is effective for fiscal years beginning after December 15, 2027 and interim periods within that period. Early adoption is permitted. The Registrants are evaluating the impact of this standard on their financial statements and disclosures.
The Registrants believe that other recently adopted and recently issued accounting standards that are not yet effective do not appear to have a material impact on the Registrants' financial position, results of operations or cash flows upon adoption.
- Revenue Recognition
The following table presents OG&E's revenues from contracts with customers disaggregated by customer classification. OG&E's operating revenues disaggregated by customer classification can be found in "OG&E (Electric Company) Results of Operations" within "Item 2. Management's Discussion and Analysis of Financial Condition and Results of Operations."
| Three Months EndedSeptember 30, | Nine Months EndedSeptember 30, | |||
|---|---|---|---|---|
| (In millions) | 2026 | 2025 | 2026 | 2025 |
| Residential | $512.7 | $399.2 | $1,016.9 | $934.1 |
| Commercial | 339.6 | 314.0 | 753.1 | 739.1 |
| Industrial | 86.5 | 80.5 | 200.3 | 200.5 |
| Oilfield | 79.2 | 73.0 | 185.9 | 184.9 |
| Public authorities and street light | 97.7 | 86.2 | 217.9 | 208.9 |
| System sales revenues | 1,115.7 | 952.9 | 2,374.1 | 2,267.5 |
| Provision for rate refund | — | — | — | 3.0 |
| Integrated market | 29.3 | 23.6 | 104.0 | 71.2 |
| Transmission | 12.7 | 38.8 | 83.9 | 120.7 |
| Other | 5.2 | 13.1 | 25.6 | 26.8 |
| Revenues from contracts with customers | $1,162.9 | $1,028.4 | $2,587.6 | $2,489.2 |
- Fair Value Measurements
The classification of the Registrants' fair value measurements requires judgment regarding the degree to which market data is observable or corroborated by observable market data. GAAP establishes a fair value hierarchy that prioritizes the inputs used to measure fair value based on observable and unobservable data. The hierarchy categorizes the inputs into three levels, with the highest priority given to quoted prices in active markets for identical unrestricted assets or liabilities (Level 1) and the lowest priority given to unobservable inputs (Level 3). Financial assets and liabilities are classified in their entirety based on the lowest level of input that is significant to the fair value measurement. The three levels defined in the fair value hierarchy are as follows:
Level 1 inputs are quoted prices in active markets for identical unrestricted assets or liabilities that are accessible at the measurement date.
Level 2 inputs are inputs other than quoted prices in active markets included within Level 1 that are either directly or indirectly observable at the reporting date for the asset or liability for substantially the full term of the asset or liability. Level 2 inputs include quoted prices for similar assets or liabilities in active markets and quoted prices for identical or similar assets or liabilities in markets that are not active.
Level 3 inputs are prices or valuation techniques for the asset or liability that require inputs that are both significant to the fair value measurement and unobservable (i.e., supported by little or no market activity). Unobservable inputs reflect the reporting entity's own assumptions about the assumptions that market participants would use in pricing the asset or liability (including assumptions about risk).
The Registrants hadno financial instruments measured at fair value on a recurring basis at September 30, 2026 and December 31, 2025. The following table presents the carrying amount and fair value of the Registrants' financial instruments at September 30, 2026 and December 31, 2025, as well as the classification level within the fair value hierarchy.
| September 30,2026 · December 31,2025 | |||||
|---|---|---|---|---|---|
| (In millions) | Carrying Amount | Fair Value | Carrying Amount | Fair Value | Classification |
| Long-term Debt (including Long-term Debt due within one year): | |||||
| OGE Energy Senior Notes | $348.2 | $348.9 | $347.6 | $362.5 | Level 2 |
| OGE Energy Term Loan | $59.7 | $60.0 | $59.9 | $60.0 | Level 2 |
| OG&E Senior Notes | $5,192.7 | $4,632.8 | $4,847.2 | $4,644.7 | Level 2 |
| OG&E Industrial Authority Bonds | $103.0 | $103.0 | $103.0 | $103.0 | Level 2 |
| OG&E Tinker Debt | $11.4 | $8.2 | $11.5 | $9.1 | Level 3 |
- Stock-Based Compensation
The following table presents the Registrants' pre-tax compensation expense and related income tax benefit for thethree and nine months ended September 30, 2026 and 2025 related to performance units and restricted stock units for the Registrants' employees.
| Three Months Ended · Nine Months Ended | ||||
|---|---|---|---|---|
| OGE Energy and OG&E | September 30, | September 30, | ||
| (In millions) | 2026 | 2025 | 2026 | 2025 |
| Performance units | $2.7 | $2.4 | $7.9 | $7.0 |
| Restricted stock units | 1.4 | 1.1 | 3.9 | 3.1 |
| Total compensation expense | $4.1 | $3.5 | $11.8 | $10.1 |
| Income tax benefit | $1.0 | $0.8 | $2.9 | $2.4 |
During the nine months ended September 30, 2026, OGE Energy issued 168,659 shares of new common stock pursuant to OGE Energy's Stock Incentive Plan to satisfy payouts of earned performance units and restricted stock unit grants to the Registrants' employees.
During the nine months ended September 30, 2026, OGE Energy granted 220,459 performance units (based on total shareholder return over a three-year period) and 129,233 restricted stock units (primarily with a three-year cliff vesting period) to the Registrants' employees at $56.63 and $46.45 fair value per share, respectively.
- Income Taxes
OGE Energy files consolidated income tax returns in the U.S. federal jurisdiction and various state jurisdictions. OG&E is a part of the consolidated income tax return of OGE Energy. With few exceptions, the Registrants are no longer subject to U.S. federal tax or state and local examinations by tax authorities for years prior to 2022. Income taxes are generally allocated to each company in the affiliated group, including OG&E, based on its stand-alone taxable income or loss. Federal investment tax credits previously claimed on electric utility property have been deferred and will be amortized to income over the life of the related property. Oklahoma investment tax credits are also earned on investments at electric generating facilities which further reduce OG&E's effective tax rate.
- Common Equity
Automatic Dividend Reinvestment and Stock Purchase Plan
OGE Energy issued 144,688 and 417,417 new shares of common stock under its Automatic Dividend Reinvestment and Stock Purchase Plan during thethree and nine months ended September 30, 2026 and received proceeds of $6.8 million and $19.5 million, respectively. OGE Energy may, from time to time, issue additional shares under its Automatic Dividend Reinvestment and Stock Purchase Plan to fund capital requirements or working capital needs. As of September 30, 2026, there were 4,646,611 shares of unissued common stock reserved for issuance under OGE Energy's Automatic Dividend Reinvestment and Stock Purchase Plan.
Common Stock Public Offering and Forward Equity Sale Agreements
In November 2025, OGE Energy entered into FSAs in connection with a completed public offering of 9,226,744 shares of its common stock. The 4,613,372 shares that are subject to the FSAs provide for settlement on a settlement date or dates to be specified at OGE Energy’s discretion on or prior to May 27, 2027. The forward sale price was initially $41.71 per share and is subject to adjustment based on a floating interest rate factor equal to the overnight bank funding rate less a spread and less expected dividends on OGE Energy's common stock during the period the instruments are outstanding. The FSAs will be physically settled with common shares issued by OGE Energy, unless OGE Energy elects to settle the agreements in net cash or net shares, subject to certain conditions. On a settlement date or dates, if OGE Energy elects to physically settle the FSAs, OGE Energy will issue shares of common stock to the various counterparties at the then-applicable forward sale price and receive issuance proceeds at that time.
At September 30, 2026, OGE Energy could have settled the FSAs with physical delivery of 4,613,372 shares of common stock to the counterparties in exchange for cash of $191.3 million. The FSAs could have also been settled at September 30, 2026 with delivery of $25.2 million of cash or approximately 536,535 shares of common stock to the counterparties, if OGE Energy had elected to net cash or net share settle, respectively. The FSAs have been classified as an equity transaction; therefore, no gain or loss will be recognized within earnings due to subsequent changes in the fair value of the FSAs.
Prior to settlement, the potentially issuable shares pursuant to the FSAs will be reflected in OGE Energy's diluted earnings per share calculations using the treasury stock method. Under this method, the number of shares of OGE Energy's common stock used in calculating diluted earnings per share for a reporting period would be increased by the number of shares, if any, that would be issued upon physical settlement of the FSAs, less the number of shares that could be purchased by OGE Energy in the market with the proceeds received from issuance (based on the average market price during that reporting period). Share dilution occurs when the average market price of OGE Energy's stock during the reporting period is higher than the then-applicable forward sale price as of the end of the reporting period. For the three and nine months ended September 30, 2026, approximately 557,305 and 536,535 incremental shares, respectively, were included in the calculation of diluted earnings per share related to the securities under the FSAs.
Earnings Per Share
Basic earnings per share is calculated by dividing net income attributable to OGE Energy by the weighted-average number of OGE Energy's common shares outstanding during the period. In the calculation of diluted earnings per share, weighted-average shares outstanding are increased for additional shares that would be outstanding if potentially dilutive securities were converted to common stock. Potentially dilutive securities for OGE Energy consist of performance units and restricted stock units and shares under the FSAs, as further discussed above.
The following table presents the calculation of basic and diluted earnings per share for OGE Energy.
| Three Months Ended · Nine Months Ended | ||||
|---|---|---|---|---|
| September 30, | September 30, | |||
| (In millions, except per share data) | 2026 | 2025 | 2026 | 2025 |
| Net income | $316.2 | $231.3 | $482.7 | $401.5 |
| Average common shares outstanding: | ||||
| Basic average common shares outstanding | 206.7 | 201.5 | 206.5 | 201.3 |
| Effect of dilutive securities: | ||||
| Contingently issuable shares (performance and restricted stock units) | 0.9 | 0.6 | 0.7 | 0.7 |
| Forward equity sale agreements | 0.6 | — | 0.5 | — |
| Diluted average common shares outstanding | 208.2 | 202.1 | 207.7 | 202.0 |
| Basic earnings per average common share | $1.53 | $1.15 | $2.34 | $1.99 |
| Diluted earnings per average common share | $1.52 | $1.14 | $2.32 | $1.99 |
| Anti-dilutive shares excluded from earnings per share calculation | — | — | — | — |
- Long-Term Debt
At September 30, 2026, the Registrants were in compliance with all of their debt agreements.
As of September 30, 2026, OG&E's $125.0 million senior notes due July 15, 2027 and $56.0 million Muskogee Industrial Authority bonds due June 1, 2027 are presented as Long-term Debt due within One Year in the 2026 condensed balance sheet.
On September 9, 2026, OGE Energy entered into an amended $120.0 million floating rate unsecured three-year credit agreement, of which $60.0 million is considered a revolving loan and $60.0 million is considered a term loan. The agreement extended the maturity date two years to May 24, 2029. At September 30, 2026, OGE Energy had drawn $60.0 million on the term loan under this credit agreement at a weighted-average interest rate of 4.82 percent. For additional information related to this credit agreement, see Note 9.
OG&E Industrial Authority Bonds
OG&E has tax-exempt pollution control bonds with optional redemption provisions that allow the holders to request repayment of the bonds on any business day. The following table presents information about these bonds, which can be tendered at the option of the holder during the next 12 months.
| Series · Date Due · Amount | |||||
|---|---|---|---|---|---|
| (In millions) | |||||
| 1.40% | - | 4.05% | Muskogee Industrial Authority, June 1, 2027 | $56.0 | |
| 1.45% | - | 4.00% | Garfield Industrial Authority, October 1, 2039 | 47.0 | |
| Total (redeemable during next 12 months) | $103.0 | ||||
All of these bonds are subject to an optional tender at the request of the holders, at 100 percent of the principal amount, together with accrued and unpaid interest to the date of purchase. The bond holders, on any business day, can request repayment of the bond by delivering an irrevocable notice to the tender agent stating the principal amount of the bond, payment instructions for the purchase price and the business day the bond is to be purchased. The repayment option may only be exercised by the holder of a bond for the principal amount. When a tender notice has been received by the trustee, a third-party remarketing agent for the bonds will attempt to remarket any bonds tendered for purchase. This process occurs once per week. Since the original issuance of these series of bonds in 1995 and 1997, the remarketing agent has successfully remarketed all tendered bonds. If the remarketing agent is unable to remarket any such bonds, OG&E is obligated to repurchase such unremarketed bonds. As OG&E has both the intent and ability to refinance the bonds on a long-term basis and such ability is supported by an ability to consummate the refinancing, the remarketing of bonds does not result in classification as Short-Term Debt in the condensed balance sheets. OG&E believes that it has sufficient liquidity to meet these obligations.
Issuance of Long-Term Debt
On April 1, 2026, OG&E issued $350.0 million of 5.90 percent senior notes due April 1, 2056. The proceeds from this issuance were added to OG&E's general funds and used for general corporate purposes, including repayment of short-term debt, repayment of borrowings under OG&E's revolving credit facility, and funding of OG&E's capital investment program and working capital needs.
- Credit Facilities and Short-Term Debt
The Registrants borrow, as necessary, by the issuance of commercial paper and by borrowings under their revolving credit agreements.
On June 12, 2026, OGE Energy and OG&E each entered into new $650.0 million unsecured five-year revolving credit facilities to replace existing facilities. Each of these new facilities is scheduled to terminate on June 12, 2031. However, each of OGE Energy and OG&E have the right to request an extension of the revolving credit facility termination date under their respective facility for an additional one-year period, which extension option can be exercised up to two times. All such extension requests are subject to majority lender group approval (and only the commitments of those lenders that consent to such extension (or that agree to replace any non-consenting lender) will be extended for such additional period).
Borrowings under OGE Energy's new facility bear interest at rates equal to either the SOFR, plus a margin of 0.80 percent to 1.475 percent, or an alternate base rate, plus a margin of 0.0 percent to 0.475 percent. OGE Energy's new facility has a facility fee that ranges from 0.075 percent to 0.275 percent. Interest rate margins and facility fees are based on OGE Energy's then-current senior unsecured credit ratings.
Borrowings under OG&E's new facility bear interest at rates equal to either the SOFR, plus a margin of 0.69 percent to 1.275 percent, or an alternate base rate, plus a margin of 0.0 percent to 0.275 percent. OG&E's new facility has a facility fee that ranges from 0.06 percent to 0.225 percent. Interest rate margins and facility fees are based on OG&E's then-current senior unsecured credit ratings.
Each of the new facilities provides for issuance of letters of credit, provided that (i) the aggregate outstanding credit exposure shall not exceed the amount of the revolving credit facilities and (ii) the aggregate outstanding stated amount of letters of credit issued under such facility shall not exceed $100.0 million for each of OGE Energy and OG&E. Advances under the new facilities may be used to refinance existing indebtedness and for working capital and general corporate purposes of the respective borrower and its subsidiaries, including commercial paper liquidity support, letters of credit, acquisitions and distributions.
Each of the facilities is unsecured and, under certain circumstances, may be increased (by up to $150.0 million in each case for OGE Energy and OG&E) to a maximum revolving commitment limit of $800.0 million for each of OGE Energy and OG&E. Advances of revolving loans and letters of credit under the facilities are subject to certain conditions precedent, including the accuracy of certain representations and warranties and the absence of any default or unmatured default.
The following table presents information regarding the Registrants' revolving credit agreements at September 30, 2026.
| Entity | AggregateCommitment | AmountOutstanding (A) | Weighted-AverageInterest Rate (F) | Expiration |
|---|---|---|---|---|
| (In millions) | ||||
| OGE Energy (B) | $650.0 | $135.1 | 4.17% | June 12, 2031 |
| OGE Energy (C) | 60.0 | — | —% | May 24, 2029 |
| OG&E (D)(E) | 650.0 | 0.4 | 1.20% | June 12, 2031 |
| Total | $1,360.0 | $135.5 | 4.16% | |
(A)
Includes direct borrowings under the revolving credit agreements, commercial paper borrowings and letters of credit at September 30, 2026. Typically, OGE Energy issues commercial paper to address consolidated operational activity, and OG&E will borrow from OGE Energy under the intercompany borrowing agreement as discussed below in footnote (E).
(B)
This bank facility is available to back up OGE Energy's commercial paper borrowings and to provide revolving credit borrowings. This bank facility can also be used as a letter of credit facility.
(C)
OGE Energy has a $120.0 million floating rate unsecured three-year credit agreement, of which $60.0 million is considered a revolving loan, which is included in the table above, and $60.0 million is considered a term loan. The credit agreement, under certain circumstances, may be increased to a maximum commitment limit of $155.0 million and includes a maximum leverage ratio of 0.70 to 1.0.
(D)
This bank facility is available to back up OG&E's commercial paper borrowings and to provide revolving credit borrowings. This bank facility can also be used as a letter of credit facility.
(E)
On August 1, 2026, OG&E increased its intercompany borrowing agreement with OGE Energy, under which OG&E may borrow up to $800.0 million. The agreement has a termination date of June 12, 2031. At September 30, 2026, OG&E hadno borrowings under this agreement.
(F)
Represents the weighted-average interest rate for the outstanding borrowings under the revolving credit agreements, commercial paper borrowings and letters of credit.
OG&E must obtain regulatory approval from the FERC in order to borrow on a short-term basis. OG&E has the necessary regulatory approvals to incur up to $1.0 billion in short-term borrowings at any one time for a two-year period beginning January 1, 2025 and ending December 31, 2026. OG&E has requested approval from the FERC to incur up to $1.5 billion for the two-year period beginning January 1, 2027 and ending December 31, 2028 and expects to receive approval prior to the expiration of its current authority.
- Retirement Plans and Postretirement Benefit Plans
Net Periodic Benefit Cost
The following tables present the net periodic benefit cost components, before consideration of capitalized amounts, of OGE Energy's Pension Plan, Restoration of Retirement Income Plan and postretirement benefit plans that are included in the condensed financial statements. Service cost is presented within Other Operation and Maintenance Expense, and the remaining net periodic benefit cost components as listed in the following tables are presented within Other Net Periodic Benefit Expense in the statements of income. OG&E recovers specific amounts of pension and postretirement medical costs in rates approved in its Oklahoma rate reviews. In accordance with approved orders, OG&E defers the difference between actual pension and postretirement medical expenses and the amount approved in its last Oklahoma rate review as a regulatory asset or regulatory liability. These amounts have been recorded in the Pension tracker in the regulatory assets and liabilities table in Note 1 and within Other Net Periodic Benefit Expense in the statements of income.
| Pension Plan · Restoration of RetirementIncome Plan | ||||||||
|---|---|---|---|---|---|---|---|---|
| Three Months Ended · Nine Months Ended · Three Months Ended · Nine Months Ended | ||||||||
| OGE Energy | September 30, | September 30, | September 30, | September 30, | ||||
| (In millions) | 2026 | 2025 | 2026 | 2025 | 2026 | 2025 | 2026 | 2025 |
| Service cost | $1.4 | $1.3 | $4.0 | $4.0 | $0.3 | $0.3 | $0.9 | $0.8 |
| Interest cost | 3.9 | 4.1 | 11.8 | 12.2 | 0.1 | 0.1 | 0.4 | 0.3 |
| Expected return on plan assets | (4.4) | (4.1) | (13.1) | (12.4) | — | — | — | — |
| Amortization of net loss | 1.5 | 1.5 | 4.5 | 4.6 | 0.1 | — | 0.1 | — |
| Amortization of unrecognized prior service cost (A) | — | — | — | — | 0.1 | — | 0.2 | 0.2 |
| Net periodic benefit cost | $2.4 | $2.8 | $7.2 | $8.4 | $0.6 | $0.4 | $1.6 | $1.3 |
(A)Unamortized prior service cost is amortized on a straight-line basis over the average remaining service period to the first eligibility age of participants who are expected to receive a benefit and are active at the date of the plan amendment.
| Pension Plan · Restoration of RetirementIncome Plan | ||||||||
|---|---|---|---|---|---|---|---|---|
| Three Months Ended · Nine Months Ended · Three Months Ended · Nine Months Ended | ||||||||
| OG&E | September 30, | September 30, | September 30, | September 30, | ||||
| (In millions) | 2026 | 2025 | 2026 | 2025 | 2026 | 2025 | 2026 | 2025 |
| Service cost | $1.4 | $1.3 | $4.0 | $4.0 | $— | $0.1 | $— | $0.1 |
| Interest cost | 3.4 | 3.4 | 10.2 | 10.5 | — | — | 0.1 | 0.1 |
| Expected return on plan assets | (3.8) | (3.5) | (11.3) | (10.6) | — | — | — | — |
| Amortization of net loss | 1.4 | 1.5 | 4.2 | 4.4 | 0.1 | — | 0.1 | — |
| Total net periodic benefit cost | 2.4 | 2.7 | 7.1 | 8.3 | 0.1 | 0.1 | 0.2 | 0.2 |
| Plus: Amount allocated from OGE Energy | (0.1) | — | (0.1) | — | 0.4 | 0.4 | 1.3 | 1.2 |
| Net periodic benefit cost | $2.3 | $2.7 | $7.0 | $8.3 | $0.5 | $0.5 | $1.5 | $1.4 |
In addition to the net periodic benefit cost amounts recognized, as presented in the tables above, for the Pension and Restoration of Retirement Income Plans during the three and nine months ended September 30, 2026 and 2025, the Registrants recognized the following:
| Three Months Ended · Nine Months Ended | ||||
|---|---|---|---|---|
| September 30, | September 30, | |||
| (In millions) | 2026 | 2025 | 2026 | 2025 |
| Change in pension expense to maintain allowed recoverable amount in Oklahoma jurisdiction (A) | $(0.6) | $(0.3) | $(1.7) | $(0.7) |
(A)
Included in the pension regulatory asset, as indicated in the regulatory assets and liabilities table in Note 1.
| OGE Energy · OG&E | ||||||||
|---|---|---|---|---|---|---|---|---|
| Postretirement Benefit Plans · Postretirement Benefit Plans | ||||||||
| Three Months Ended · Nine Months Ended · Three Months Ended · Nine Months Ended | ||||||||
| September 30, | September 30, | September 30, | September 30, | |||||
| (In millions) | 2026 | 2025 | 2026 | 2025 | 2026 | 2025 | 2026 | 2025 |
| Service cost | $— | $— | $— | $— | $— | $0.1 | $— | $0.1 |
| Interest cost | 1.2 | 1.3 | 3.4 | 4.0 | 1.0 | 1.0 | 2.7 | 3.1 |
| Expected return on plan assets | (0.4) | (0.4) | (1.1) | (1.2) | (0.4) | (0.4) | (1.0) | (1.1) |
| Amortization of net (gain) loss | (0.1) | 0.1 | (0.2) | 0.3 | — | 0.1 | — | 0.4 |
| Total net periodic benefit cost | 0.7 | 1.0 | 2.1 | 3.1 | 0.6 | 0.8 | 1.7 | 2.5 |
| Plus: Amount allocated from OGE Energy | 0.1 | 0.1 | 0.3 | 0.3 | ||||
| Net periodic benefit cost | $0.7 | $1.0 | $2.1 | $3.1 | $0.7 | $0.9 | $2.0 | $2.8 |
In addition to the net periodic benefit cost amounts recognized, as presented in the table above, for the postretirement benefit plans during the three and nine months ended September 30, 2026 and 2025, the Registrants recognized the following:
| Three Months Ended · Nine Months Ended | ||||
|---|---|---|---|---|
| September 30, | September 30, | |||
| (In millions) | 2026 | 2025 | 2026 | 2025 |
| Change in postretirement expense to maintain allowed recoverable amount in Oklahoma jurisdiction (A) | $(0.1) | $0.2 | $(0.3) | $0.5 |
(A)
Included in the pension regulatory asset, as indicated in the regulatory assets and liabilities table in Note 1.
The following table presents the amount of net periodic benefit cost capitalized and attributable to each of the Registrants for OGE Energy's Pension Plan and postretirement benefit plans for thethree and nine months ended September 30, 2026 and 2025.
| Three Months Ended · Nine Months Ended | ||||
|---|---|---|---|---|
| OGE Energy and OG&E | September 30, | September 30, | ||
| (In millions) | 2026 | 2025 | 2026 | 2025 |
| Capitalized portion of net periodic pension benefit cost | $0.6 | $0.6 | $1.8 | $1.8 |
| Capitalized portion of net periodic postretirement benefit cost | $— | $— | $— | $— |
Pension Plan Funding
During the nine months ended September 30, 2026, OGE Energy contributed $22.0 million to its Pension Plan related to OG&E employees. The Registrants could be required to make additional contributions if the value of its pension trust and postretirement benefit plan trust assets are adversely impacted by a major market disruption in the future.
- Report of Business Segments
OGE Energy reports its operations primarily through asingle segment, captioned "electric company," which is engaged in the generation, transmission, distribution and sale of electric energy. The "other operations" caption primarily includes the operations of the holding company and other energy-related investments. Intersegment revenues are recorded at prices comparable to those of unaffiliated customers and are affected by regulatory considerations. The Registrants' chief operating decision maker uses net income as a measure of reportable segment profit or loss to make operating decisions, allocate resources, and assess performance. The following tables, which include significant segment expenses, present the results of OGE Energy's business segments for thethree and nine months ended September 30, 2026 and 2025.
| Three Months Ended September 30, 2026 | Electric Company | OtherOperations | Eliminations | Total |
|---|---|---|---|---|
| (In millions) | ||||
| Operating revenues | $1,182.8 | $— | $— | $1,182.8 |
| Fuel, purchased power and direct transmission expense | 441.2 | — | — | 441.2 |
| Other operation and maintenance | 137.1 | — | — | 137.1 |
| Depreciation and amortization | 149.2 | — | — | 149.2 |
| Taxes other than income | 26.8 | — | — | 26.8 |
| Operating income | 428.5 | — | — | 428.5 |
| Net other income | 12.5 | 4.0 | (5.8) | 10.7 |
| Interest expense | 55.7 | 13.1 | (5.8) | 63.0 |
| Income tax expense (benefit) | 64.4 | (4.4) | — | 60.0 |
| Net income (loss) | $320.9 | $(4.7) | $— | $316.2 |
| Total assets | $15,137.1 | $118.6 | $(315.9) | $14,939.8 |
| Capital expenditures | $279.4 | $— | $— | $279.4 |
| Three Months Ended September 30, 2025 | Electric Company | OtherOperations | Eliminations | Total |
|---|---|---|---|---|
| (In millions) | ||||
| Operating revenues | $1,045.0 | $— | $— | $1,045.0 |
| Fuel, purchased power and direct transmission expense | 388.5 | — | — | 388.5 |
| Other operation and maintenance | 143.5 | (0.2) | — | 143.3 |
| Depreciation and amortization | 146.7 | — | — | 146.7 |
| Taxes other than income | 25.2 | — | — | 25.2 |
| Operating income | 341.1 | 0.2 | — | 341.3 |
| Net other income (expense) | 7.3 | (0.7) | (1.5) | 5.1 |
| Interest expense | 54.2 | 16.9 | (1.5) | 69.6 |
| Income tax expense (benefit) | 51.3 | (5.8) | — | 45.5 |
| Net income (loss) | $242.9 | $(11.6) | $— | $231.3 |
| Total assets | $14,114.7 | $221.4 | $(78.7) | $14,257.4 |
| Capital expenditures | $229.5 | $— | $— | $229.5 |
| Nine Months Ended September 30, 2026 | Electric Company | OtherOperations | Eliminations | Total |
|---|---|---|---|---|
| (In millions) | ||||
| Operating revenues | $2,647.3 | $— | $— | $2,647.3 |
| Fuel, purchased power and direct transmission expense | 995.6 | — | — | 995.6 |
| Other operation and maintenance | 412.5 | (0.2) | — | 412.3 |
| Depreciation and amortization | 423.7 | — | — | 423.7 |
| Taxes other than income | 82.5 | — | — | 82.5 |
| Operating income | 733.0 | 0.2 | — | 733.2 |
| Net other income | 30.0 | 9.5 | (9.7) | 29.8 |
| Interest expense | 164.1 | 35.2 | (9.7) | 189.6 |
| Income tax expense (benefit) | 100.0 | (9.3) | — | 90.7 |
| Net income (loss) | $498.9 | $(16.2) | $— | $482.7 |
| Total assets | $15,137.1 | $118.6 | $(315.9) | $14,939.8 |
| Capital expenditures | $768.0 | $— | $— | $768.0 |
| Nine Months Ended September 30, 2025 | Electric Company | OtherOperations | Eliminations | Total |
|---|---|---|---|---|
| (In millions) | ||||
| Operating revenues | $2,534.3 | $— | $— | $2,534.3 |
| Fuel, purchased power and direct transmission expense | 973.6 | — | — | 973.6 |
| Other operation and maintenance | 391.6 | 0.6 | — | 392.2 |
| Depreciation and amortization | 424.7 | — | — | 424.7 |
| Taxes other than income | 82.6 | — | — | 82.6 |
| Operating income (loss) | 661.8 | (0.6) | — | 661.2 |
| Net other income | 23.2 | 9.5 | (5.6) | 27.1 |
| Interest expense | 174.4 | 40.3 | (5.6) | 209.1 |
| Income tax expense (benefit) | 89.0 | (11.3) | — | 77.7 |
| Net income (loss) | $421.6 | $(20.1) | $— | $401.5 |
| Total assets | $14,114.7 | $221.4 | $(78.7) | $14,257.4 |
| Capital expenditures | $752.7 | $— | $— | $752.7 |
- Commitments and Contingencies
Except as set forth below, in Note 13 and under "Environmental Laws and Regulations" in Item 2 of Part I and in Item 1 of Part II of this Form 10-Q, the circumstances set forth in Notes 13 and 14 to the financial statements included in the Registrants'2025 Form 10-K appropriately represent, in all material respects, the current status of the Registrants' material commitments and contingent liabilities.
Environmental Laws and Regulations
The activities of OG&E are subject to numerous stringent and complex federal, state and local laws and regulations governing environmental protection. These laws and regulations can change, restrict or otherwise impact the Registrants' business activities in many ways, including the handling or disposal of waste material, planning for future construction activities to avoid or mitigate harm to threatened or endangered species and requiring the installation and operation of emissions or pollution control equipment. Failure to comply with these laws and regulations could result in the assessment of administrative, civil and criminal penalties, the imposition of remedial requirements and the issuance of orders enjoining future operations. Management believes that all of the Registrants' operations are in substantial compliance with current federal, state and local environmental standards.
Environmental regulation can increase the cost of planning, design, initial installation and operation of OG&E's facilities. Management continues to evaluate its compliance with existing and proposed environmental legislation and regulations and implement appropriate environmental programs in a competitive market.
Other
In the normal course of business, the Registrants are confronted with issues or events that may result in a contingent liability. These generally relate to lawsuits or claims made by third parties, including governmental agencies. When appropriate, management consults with legal counsel and other experts to assess the claim. If, in management's opinion, the Registrants have incurred a probable loss as set forth by GAAP, an estimate is made of the loss, and the appropriate accounting entries are reflected in the condensed financial statements. If the assessment indicates that a potential loss is not probable but reasonably possible, the nature of the contingent matter, together with an estimate of the range of possible loss if determinable and material, would be disclosed. At the present time, based on currently available information, the Registrants believe that any reasonably possible losses in excess of accrued amounts arising out of pending or threatened lawsuits or claims would not be quantitatively material to their condensed financial statements and would not have a material adverse effect on their financial position, results of operations or cash flows.
In 2023, OG&E was named, along with its contractor, as a defendant in a lawsuit filed by an apartment owner and its insurance companies seeking in excess of $60.0 million in damages related to a fire at an apartment building under construction in Oklahoma City. Several additional defendants have also been named. In October 2026, OG&E settled this lawsuit which did not result in a material impact to its operating results.
- Rate Matters and Regulation
Except as disclosed below, the circumstances set forth in Note 14 to the financial statements included in the Registrants'2025 Form 10-K appropriately represent, in all material respects, the current status of the Registrants' regulatory matters.
Completed Regulatory Matters
Integrated Resource Plans
As a result of the 2024 request for proposal process, OG&E has executed contracts for approximately 1,000 MWs of generation capacity, and regulatory approvals have been received or are currently being pursued, as further discussed below. In January 2026, OG&E issued additional requests for proposals for resources to meet projected capacity needs while maintaining affordability and reliability for OG&E's customers. Independent evaluators have been engaged on behalf of the OCC and Oklahoma Attorney General to oversee this 2026 request for proposal process. Bids into the 2026 request for proposal process have been received and evaluated, and OG&E is currently negotiating for generation resources with a number of selected parties. In April 2026, OG&E issued its final 2026 IRP to the OCC and APSC, which is intended to address OG&E's updated load forecast as well as updated SPP Resource Adequacy policies. The 2026 IRP identifies capacity needs of 1,922 MWs by the 2031/2032 winter season, which is inclusive of approximately 800 MWs of capacity needs driven by changes in the SPP Resource Adequacy policies. On October 27, 2026, OG&E filed a preapproval case seeking OCC approval of a generation capacity construction project to install a natural gas combined cycle unit at OG&E’s existing Horseshoe Lake generating facility (Unit 15). This project is expected to add approximately 755 MW of nameplate capacity to the OG&E portfolio at a cost of approximately $1.7 billion. OG&E is currently evaluating additional request for proposal responses associated with its 2026 IRP and expects to file for additional preapprovals beginning as early as the fourth quarter of 2026. OG&E intends to evaluate incremental capacity needs beyond what is identified in the 2026 IRP through future IRPs and to continue to seek capacity additions, as needed.
APSC Proceedings
2025 Arkansas Act 373 Tariff Filing
In December 2025, OG&E filed an application for approval of an Act 373 tariff to recover return on CWIP and revenue requirement for Horseshoe Lake and Tinker generation facilities. Recovery under the Act 373 tariff is dependent on a finding of eligibility for the Horseshoe Lake Units 11 and 12 and Tinker generation facilities in the prudence case disclosed below. In April 2026, the APSC issued an order approving OG&E's Act 373 tariff.
Arkansas Prudence of Horseshoe Lake and Tinker Generation Facilities
In December 2024, pursuant to orders in the generation construction notice filings, OG&E filed an application requesting a determination of prudence of action and initial contract costs for the generating units being constructed at Horseshoe Lake (Units 11 and 12) and Tinker Air Force Base. In May 2025, OG&E filed a supplemental application to serve as notice to the APSC of OG&E’s intent to recover the costs of these projects through a rider under the newly enacted Act 373. On September 8, 2026, the APSC issued a final order approving the prudence of action and initial contract costs for construction of the Tinker Air Force Base units and Horseshoe Lake Units 11 and 12. The APSC denied the portion of the settlement which addressed recognition of the projects as strategic investments and eligibility for recovery through a rider.
Arkansas Frontier Energy Storage Project Preapproval Filing
In February 2026, OG&E filed a preapproval case for the Frontier Energy Storage Project, which involves a purchase and sale agreement for a 300 MW battery storage facility in Oklahoma. The Frontier Energy Storage Project is the final project resulting from OG&E's 2024 request for proposals and subsequent negotiations. In this proceeding, OG&E sought authorization to commence construction of the Frontier Energy Storage Project and to later acquire the facility pursuant to the purchase and sale agreement, a prudency determination for the project, and all other findings and approvals needed under Arkansas law. On July 31, 2026, the APSC issued a final order, which granted prudence of action and initial costs of the Frontier Energy Storage Project.
FERC Proceedings
Order for Sponsored Transmission Upgrades within SPP
Under Attachment Z2 of the SPP Open Access Transmission Tariff, OG&E and others who built participant-funded, or "sponsored," transmission upgrades may recover the costs of the upgrade from other SPP customers who benefit from it. The FERC approved a waiver of a time limitation in the SPP tariff to allow the SPP in 2016 to bill for the 2008 through 2015 period due to information system limitations that had delayed that billing. The SPP then both billed users and credited sponsors, including OG&E, for Z2 charges during the period. OG&E refunded most of the net credits to customers through its various rate riders that include SPP activity and retained the remaining amounts.
Net payers of Z2 credits contested the waiver, leading the FERC to reverse its decision, deny the waiver, and instruct the SPP to refund payments made for charges from 2008 to 2015. OG&E and other net creditors challenged this reversal. However, the FERC upheld its reversal, and in August 2021 and September 2024, federal appeals courts upheld the FERC’s decisions to deny the waivers and to deny relief to OG&E and the other creditors against SPP. All appellate options have now been exhausted.
On July 16, 2026, the FERC ordered the SPP to begin invoicing OG&E and other parties for refund amounts owed. The Registrants had previously reserved $14 million plus estimated interest for this refund, and in September 2026, OG&E remitted the net funds invoiced by the SPP. Of therefund amount, the Registrants recognized approximately $4 million, plus interest, in expense in 2021 that initially benefited the Registrants in 2016, and OG&E customers will incur a net impact of approximately $10 million, plus interest, in expense through rider mechanisms or the FERC formula rate now that the refunds have been paid to the SPP. The SPP must also submit a refund report within 60 days after issuing the initial invoices, including the recoupment amounts and complete interest calculations.
After the initiation of the disputes discussed above, the FERC approved an SPP proposal to eliminate Attachment Z2 revenue crediting and replace it with a different rate mechanism that would provide project sponsors, such as OG&E, the same level of recovery. This elimination of the Attachment Z2 revenue crediting would only impact OG&E and its recovery of any future upgrade costs that it may incur as a project sponsor after July 2020. All projects initiated prior to July 2020 remain eligible to receive revenue credits under Attachment Z2.
OCC Proceedings
Oklahoma Distribution Interconnection Agreement
In May 2026, OG&E filed an application requesting approval of a pro forma Distribution Interconnection Agreement to be used for certain interconnections to OG&E’s distribution system for generators that do not have a purchase agreement for the output with OG&E and are larger than 300 kW. On August 6, 2026, the OCC issued a final order approving OG&E's application.
Oklahoma Frontier Energy Storage Project Preapproval Filing
In December 2025, OG&E filed a preapproval case for the Frontier Energy Storage Project, which involves a purchase and sale agreement for a 300 MW battery storage facility in Oklahoma. The Frontier Energy Storage Project is the final project resulting from OG&E's 2024 request for proposals and subsequent negotiations. In June 2026, the ALJ issued a report recommending approval of the Frontier Energy Storage Project, and on August 6, 2026, the OCC issued a final order granting preapproval of the Frontier Energy Storage Project. The final order was subsequently appealed at the Oklahoma Supreme Court by a third party.
Pending Regulatory Matters
Various proceedings pending before state or federal regulatory agencies are described below. Unless stated otherwise, the Registrants cannot predict when the regulatory agency will act or what action the regulatory agency will take. The Registrants' financial results are dependent in part on timely and constructive decisions by the regulatory agencies that set OG&E's rates.
SPP Proceedings
Demand Response Accreditation and Peak Demand Assessment
The SPP has proposed performance-based demand response accreditation and a peak demand assessment that would compare each LRE's forecasted peak demand with its actual peak demand. An LRE that under-forecasts its peak demand could be required to make a deficiency payment. Demand response resources would qualify through market or reliability registration and dispatch, while programs included in an LRE's forecast as load modifiers could reduce its planning reserve margin requirements. In February 2026, the SPP Regional State Committee and the SPP Board of Directors approved implementation of a load modifier cap in 2027 and full implementation of the demand response accreditation and peak demand assessment policies in 2028. These policies are subject to FERC review and approval prior to implementation. In August 2026, the FERC issued a Deficiency Letter requiring the SPP to address questions and concerns regarding the lack of detail in the proposed tariff change and potential inequities in its administration. On October 9, 2026, several LREs, including OG&E, filed comments requesting that the proposal be rejected or, at minimum, delayed. If approved by the FERC, the demand response changes would require OG&E to alter its current load reduction program and may require OG&E to procure additional capacity resources, and the peak demand assessment could create deficiency payment risk, as discussed above, if OG&E’s peak demand is under-forecasted.
Seminole to Longwood Transmission Line
At the end of 2025, the SPP Board of Directors adopted their 2025 Integrated Transmission Plan. This plan included a new 765 kV transmission line running from Konawa, Oklahoma to Shreveport, Louisiana. OG&E will construct and own a significant portion of the line. The project is pending OG&E's receipt and acceptance of a notice to construct, which is expected in the coming months.
APSC Proceedings
2025 Arkansas Preapproval Case
In July 2025, OG&E filed an application requesting several approvals from the APSC relating to three capacity projects arising from the 2024 request for proposals for generating capacity: (i) the Black Kettle Battery Storage CPA; (ii) the Kiamichi natural gas CPA; and (iii) construction of two additional combustion turbines at the Horseshoe Lake generating facility (Units 13 and 14). OG&E sought authority to begin construction of the Horseshoe Lake units, a prudency determination of those new Horseshoe Lake units, authorization to enter into the Black Kettle Battery Storage CPA and other findings needed under Arkansas law, including eligibility to recover costs of the new Horseshoe Lake units through a rider under the newly enacted Act 373. In November 2025, OG&E and the
APSC staff filed a settlement agreement approving OG&E’s application with some additional reporting requirements and allowing an additional return on the Black Kettle Battery Storage CPA at the 20-year U.S. treasury rate. In December 2025, the Attorney General filed testimony in opposition to the settlement. In January 2026, the APSC issued an order denying the settlement agreement and denying preapproval of Horseshoe Lake Units 13 and 14 but approving the Black Kettle Battery Storage CPA. The APSC also found that OG&E did not need to seek approval of the Kiamichi natural gas CPA since the term is shorter than five years. In the order, the APSC stated OG&E could still seek a prudence determination and cost recovery of Horseshoe Lake Units 13 and 14 after they are placed into service. In February 2026, OG&E filed additional evidence pursuant to Arkansas law and requested that the APSC consider the additional evidence in finding that Horseshoe Lake Units 13 and 14 are reasonable, necessary and in the public interest. In March 2026, the APSC issued an order which again declined to grant prudence of Horseshoe Lake Units 13 and 14 but clarified that OG&E is authorized to begin construction and the APSC's previous order should not be construed to indicate prudence or imprudence. The APSC re-stated that OG&E may request approval for Horseshoe Lake Units 13 and 14 in a future rate case. Parties have filed comments in response to questions posed by the APSC's March 2026 order, and OG&E is awaiting further action from the APSC.
Arkansas Long-term CPAs
In July 2026, OG&E filed its application and direct testimony to seek approval for two long-term CPAs as presented in the Oklahoma Google special contract case, which is further discussed below. On October 15, 2026, the APSC Staff filed direct testimony recommending denial of the CPAs, stating that OG&E did not provide sufficient evidence that the pricing is reasonable and prudent. OG&E is preparing rebuttal testimony and awaiting a procedural schedule from the APSC.
FERC Proceedings
Integration of Large and Co-Located Loads
In June 2026, the FERC issued an order instituting a Section 206 show cause proceeding directed at the SPP and named the SPP transmission owners, including OG&E, preliminarily finding that the SPP’s tariff appears to be unjust, unreasonable, or unduly discriminatory or preferential regarding the integration of large and co-located loads onto the SPP transmission system. The SPP and the SPP transmission owners were directed to either: (i) show cause why the tariff remains just and reasonable; or (ii) explain what tariff changes would remedy the concerns identified by the FERC. The FERC’s concerns involved transmission service for large loads, cost transparency, cost recovery agreements, co-location arrangements and eligible load, flexible large loads, and resource adequacy/generation sufficiency. In August 2026, certain SPP transmission owners, including OG&E, filed a motion requesting the FERC hold the show cause proceeding in abeyance to November 20, 2026, pending completion of the SPP’s stakeholder proceedings and the submittal of a Section 205 filing to address the FERC’s preliminary findings. In August 2026, the FERC granted the motion of holding the proceeding in abeyance, with responses to the June 2026 order due on November 20, 2026, and answers to responses due on December 21, 2026. The FERC's final determination could result in changes to certain OG&E tariff provisions.
OCC Proceedings
Oklahoma CWIP Filing
In December 2025, OG&E filed an application for CWIP treatment for Horseshoe Lake combustion turbines Units 13 and 14, as allowed by Oklahoma Senate Bill 998. A motion to dismiss the case was filed by the Oklahoma Industrial Energy Consumers, as well as the Public Utility Division Staff. OG&E filed a response as well as motions to move the case and all outstanding motions to be heard en banc. These motions were heard before the OCC in January 2026. In March 2026, the OCC issued an order dismissing the case, and on the same day, OG&E filed an appeal at the Oklahoma Supreme Court. The case is now fully briefed and is awaiting a decision from the Oklahoma Supreme Court.
Oklahoma 2025 Fuel Prudence
In April 2026, the Public Utility Division Staff filed their application initiating the prudence review of the 2025 fuel adjustment clause. OG&E filed its direct testimony and minimum filing requirements in June 2026. Responsive testimony from the OCC Staff was filed in August 2026, and a hearing occurred on October 8, 2026. At the conclusion of the hearing, the ALJ recommended the OCC find OG&E's fuel procurement policies and practices prudent and costs calculated accurately for the calendar year 2025.
Oklahoma Google Special Contract
In May 2026, OG&E filed an application requesting approval of a special contract with Google and preapproval of two CPAs. The special contract includes provisions such as long-term contract commitments, minimum billing demand and energy charges, funding of upfront costs, and recognizing OCC authority to review and address any potential adverse rate impact in future rate proceedings through cost-of-service adjustments. Further, as part of the special contract, OG&E secured power generation capacity agreements from two solar facilities that Google currently has under construction. On September 9, 2026, a non-contested settlement agreement was reached between OG&E, the Oklahoma Attorney General, the Public Utility Division and Google. At the hearing on the merits, the ALJ recommended approval of the special contract and the two CPAs.
Oklahoma Large Load Tariff
Separately from the Google special contract, in June 2026, OG&E filed an application requesting approval of its new proposed XLPL tariff and terms and conditions of service for extra large load customers and for approval of a regulatory asset to recover costs associated with portfolio optimization software. If approved, this tariff would establish a framework to serve large load customers (75 MWs or higher) and include provisions such as long-term contract commitments, minimum billing demand and energy charges, funding of upfront costs, a customer protection charge that addresses any potential adverse rate impact to other customer classes, and a customer affordability charge that would be credited to residential customers through a regulatory liability. In September 2026, OG&E filed a motion to amend the procedural schedule and order briefing, and in October 2026, the OCC approved OG&E's motion. A hearing is scheduled for January 12, 2027.
2026 Oklahoma General Rate Review
On September 30, 2026, OG&E filed a general rate review in Oklahoma seeking a rate increase of $395.0 million and a 10.5 percent return on equity based on a common equity percentage of 53.42 percent. The rate review includes a request for recovery of approximately $2.4 billion of total plant investment since the last general rate review.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.