Skip to main content

PACIFIC GAS & ELECTRIC Co

For the period ended Dec 31, 2025. Filed Feb 12, 2026.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2025 · Filed Feb 12, 2026

PCG$13.14+1.3%Stored close · as of Nov 9, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

REGULATORY MATTERS

The Utility is subject to substantial regulation by the CPUC, the FERC, the OEIS, NRC, and other federal and state regulatory agencies. The resolutions of the proceedings described below and other proceedings may materially affect PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows. Except as otherwise noted, PG&E Corporation and the Utility are unable to predict the timing or outcome of the following proceedings.

Key updates to regulatory matters include the following:

In February 2026, the CPUC issued a final decision in the Utility’s 2023 WMCE proceeding, approving recovery of $1.9 billion of costs.

In February 2026, the OEIS issued a final decision approving the Utility’s 2026–2028 WMP. In December 2025, the Utility submitted its 2025 safety certificate request to OEIS.

In December 2025, the CPUC issued a final decision in the Utility’s 2026 Cost of Capital proceeding that set the Utility’s ROE at 9.98% effective January 1, 2026 and approved a yield spread adjustment.

In December 2025, the CPUC approved a resolution that updated CPUC guidelines for implementation of the SB 884 undergrounding program.

In November 2025, the Utility filed the Kincade and Dixie AB 1054 Wildfire Cost Review and Recovery Proceeding application requesting recovery of approximately $1.59 billion of WEMA costs, review of costs drawn from the Wildfire Fund, and recovery of $314 million of CEMA costs.

In August 2025, the FERC approved an all-party settlement in the Utility’s Transmission Owner Rate Case for 2024 (the “TO21” rate case).

In August 2025, the CPUC issued a final decision that increases the cost cap for 2025 and 2026 by an aggregate $2.38 billion in connection with the Order Instituting Rulemaking (“OIR”) to Establish Energization Timelines.

In September 2025, the CPUC issued a final decision approving $1.06 billion in cost recovery in the 2022 WMCE proceeding.

In May 2025, the Utility filed its 2027 GRC application with the CPUC.

Cost Recovery Proceedings

Periodically, costs arise that could not have been anticipated by the Utility during CPUC GRC proceedings or that have been deliberately excluded from such proceedings. For instance, these costs may result from catastrophic events, changes in regulation, or extraordinary changes in operating practices. The Utility may seek authority to track incremental costs in a memorandum account and the CPUC may later authorize recovery of costs tracked in memorandum accounts if the costs are deemed incremental and prudently incurred. The CPUC may also authorize memorandum and balancing accounts with limitations or caps on cost recovery. These accounts, which include the CEMA, WEMA, FRMMA, WMPMA, VMBA, WMBA, among others, allow the Utility to track the costs associated with work related to disaster and wildfire response, other wildfire prevention-related costs, and certain third-party wildfire claims. While the Utility generally expects such costs to be recoverable, the CPUC may authorize the Utility to recover less than the full amount of its costs.

In recent years, the Utility has recorded significant amounts to these accounts. Because rate recovery may require CPUC authorization of the costs in these accounts, there can be a delay between when the Utility incurs costs and when it may recover those costs. As of December 31, 2025, the Utility had recorded an aggregate amount of approximately $2.2 billion in costs for the CEMA, WEMA, FRMMA, WMPMA, VMBA, and WMBA, substantially all of which was accounted for as long term. See Note 3 of the Notes to the Consolidated Financial Statements in Part II, Item 8.

If the amount of the costs recorded in these accounts increases, or the delay between incurring and recovering costs lengthens, PG&E Corporation and the Utility may incur additional financing costs. If the Utility does not recover the full amount of its recorded costs, the difference between the recorded and recovered amounts would be written off as a non-cash disallowance. Such disallowances could materially affect PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows.

For more information, see Note 3 of the Notes to the Consolidated Financial Statements in Part II, Item 8, and “Wildfire Mitigation and Catastrophic Events Cost Recovery Applications” and “Wildfire and Gas Safety Costs Recovery Application” below.

Key updates to the Utility’s cost recovery proceedings are summarized in the following table:

ProceedingRequest (1)Status
2022 WMCE$1.36 billion of cost recoveryFinal decision authorizing $1.06 billion of total cost recovery issued September 2025.
2023 WMCE$2.18 billion of cost recoveryFinal decision authorizing $1.9 billion of costs issued February 2026.
2024 WMCE$596 million of cost recoveryApplication filed November 2024.
2023 WGSC$2.5 billion of cost recoveryApplication filed June 2023. Decision authorizing $516 million of interim rate relief adopted March 2024.
Kincade and Dixie AB 1054Review of 2019 Kincade fire and 2021 Dixie fire costs, including recovery of approximately $1.9 billionApplication filed November 2025.

(1) The revenue requirement amounts requested do not include interest.

Wildfire Mitigation and Catastrophic Events Cost Recovery Applications

2022 WMCE Application

On December 15, 2022, the Utility filed an application with the CPUC requesting cost recovery of approximately $1.36 billion of recorded expenditures, resulting in a proposed revenue requirement of approximately $1.29 billion (the “2022 WMCE application”). The costs addressed in the 2022 WMCE application reflect costs related to wildfire mitigation and certain catastrophic events, as well as implementation of various customer-focused initiatives. These costs were incurred primarily in 2021. The recorded expenditures consisted of $1.2 billion in expenses and $136 million in capital expenditures.

On September 26, 2025, the CPUC issued a final decision adopting the settlement agreement and authorizing total cost recovery for this matter of $1.06 billion. The final decision disallowed $217 million in VMBA costs.

2023 WMCE Application

On December 1, 2023, the Utility filed an application with the CPUC requesting cost recovery of approximately $2.18 billion of recorded expenditures, resulting in a proposed revenue requirement of approximately $1.86 billion (the “2023 WMCE application”). The costs addressed in the 2023 WMCE application reflect costs related to wildfire mitigation and certain catastrophic events, as well as implementation of various customer-focused initiatives. These costs were incurred primarily in 2022.

The recorded expenditures consist of $1.6 billion in expenses and $559 million in capital expenditures. Of these amounts, approximately 15% of expense, or $239 million, and 30% of capital expenditures, or $167 million, relate to the Utility’s response to the 2022-2023 extreme winter storms CEMA event.

On September 16, 2024, the CPUC issued a final decision on interim rate recovery that grants the Utility interim rate relief of $944 million, plus interest, subject to refund, to be recovered over at least 17 months starting October 1, 2024.

On February 5, 2026, the CPUC voted out a final decision, which approved recovery of $1.9 billion of costs. The final decision denied recovery of $173 million in vegetation management costs.

2024 WMCE Application

On November 21, 2024, the Utility filed an application with the CPUC requesting cost recovery of approximately $596 million of recorded expenditures in the CEMA and other accounts, resulting in a revenue requirement of approximately $435 million (the “2024 WMCE application”). The costs addressed in the 2024 WMCE application include those incurred in connection with rebuild and restoration activities, certain catastrophic wildfire and weather events, and other programs supporting gas, customer, and climate initiatives. These costs were incurred primarily in 2023.

The recorded expenditures consist of $80 million in expense and $516 million in capital expenditures. Of these amounts, approximately $50 million of expense and $396 million of capital expenditures relate to community rebuild and restoration activities and other catastrophic events included in the CEMA.

Wildfire and Gas Safety Costs Recovery Application

On June 15, 2023, the Utility filed a WGSC application with the CPUC requesting cost recovery of approximately $2.5 billion of recorded expenditures related to wildfire mitigation costs and gas safety and electric modernization costs.

The recorded expenditures for wildfire mitigation consist of $726 million in expenses and $1.5 billion in capital expenditures and cover activities during the years 2020 to 2022. The recorded expenditures for gas safety and electric modernization efforts consist of $120 million in expenses and $118 million in capital expenditures and cover activities during the years 2017 to 2022. If approved, the requested cost recovery would result in an aggregate revenue requirement of $688 million. The costs addressed in the WGSC application are incremental to those previously authorized in the Utility’s 2020 GRC and other proceedings.

The Utility recorded these costs to the memorandum and balancing accounts as set forth in the following table:

(in millions)Recorded Costs
WMPMA$2,095
FRMMA165
Gas storage balancing account101
In line inspection memorandum account92
Other45
Total$2,498

In connection with the WGSC application, the Utility also requested interim rate relief of $583 million. The remaining $105 million would be recovered after the CPUC issues a final decision. On March 7, 2024, the CPUC approved a final decision authorizing the Utility to recover $516 million in interim rates to be recovered over at least 12 months starting April 1, 2024.

On June 12, 2025, the CPUC issued a decision extending the statutory deadline in the proceeding from June 30, 2025 to March 31, 2026.

Review and Recovery of Costs Associated with the 2019 Kincade Fire and 2021 Dixie Fire Under AB 1054 Proceeding Application

On November 14, 2025, the Utility filed an application with the CPUC seeking review and recovery of costs associated with the 2019 Kincade fire and 2021 Dixie fire. The application seeks (1) recovery of $1.59 billion of costs recorded to the WEMA and not covered through the Wildfire Fund or insurance, (2) review of the costs recorded to the WEMA and drawn from the Wildfire Fund, and (3) recovery of $314 million of costs recorded to the CEMA.

The Utility had drawn approximately $674 million from the Wildfire Fund at the time of the application. This amount will increase as the Utility continues to resolve claims and draw from the Wildfire Fund. The CPUC may require the Utility to reimburse the Wildfire Fund to the extent that amounts drawn from the Wildfire Fund are determined not to be just and reasonable. See Note 14 of the Notes to the Consolidated Financial Statements.

The scoping memo indicates that a PD will be issued by November 2026. That deadline could be extended by six months.

Forward-Looking Rate Cases

The Utility routinely participates in forward-looking rate case applications before the CPUC and the FERC. Those applications include GRCs, where the revenue required for general operations (“base revenue”) of the Utility is assessed and reset. In addition, the Utility is periodically involved in “cost of capital” proceedings to adjust its regulated return on rate base. The Utility’s future earnings will depend on the revenue requirements authorized in such rate cases.

Decisions in GRC proceedings have historically been expected prior to the commencement of the period to which the rates would apply. In recent decades, decisions in GRC proceedings have been delayed. Delayed decisions may cause the Utility to develop its budgets based on possible outcomes, rather than authorized amounts. When decisions are delayed, the CPUC typically provides rate relief to the Utility effective as of the commencement of the rate case period (not effective as of the date of the delayed decision). Nonetheless, the Utility’s spending during the period of the delay may exceed the authorized amount, without an ability for the Utility to seek cost recovery of such excess. If the Utility’s spending during the period of the delay is less than the authorized amount, the Utility could be exposed to operational and financial risks associated with the lower level of work achieved compared to that funded by the CPUC.

Key updates to the Utility’s forward-looking rate cases are summarized in the following table:

Rate CaseRequestStatus
2027 GRCRevenue requirement of $16.64 billion for 2027Filed May 2025. A PD is expected by March 2027 and a final decision by May 2027.
2026 Cost of CapitalIncrease ROE to 11.30% and cost of debt to 5.04%Final decision approving ROE of 9.98% and cost of debt of 5.04% issued December 2025.
Transmission Owner Rate Case for 2024 (TO21)Revenue requirement of $2.78 billion for 2024, subject to true-up and refundAccepted December 2023, except as to CAISO adder. All other issues resolved August 2025.

2027 General Rate Case

On May 15, 2025, the Utility filed its 2027 GRC application with the CPUC. In the 2027 GRC, the CPUC will determine the annual amount of revenue requirements that the Utility will be authorized to collect through rates from 2027 through 2030 to recover its anticipated costs for gas distribution, transmission and storage, electric distribution, and electric generation and to provide the Utility an opportunity to earn its authorized rate of return. On November 10, 2025, the Utility submitted errata to update its GRC opening testimony and revenue requirement request.

The table below compares the portion of CPUC jurisdictional revenue requirements and weighted-average rate base that are requested in the GRC proceeding, as updated, from 2027 through 2030 to the amounts adopted for 2026 in the 2023 GRC and other cost recovery proceedings:

YearRequested revenue requirement (in billions)Requested weighted-average GRC rate base
2026 (as adopted)$15.454.0
202716.667.0
202817.673.4
202918.779.4
203019.885.4

In the 2027 GRC application, the Utility proposed various safety, resiliency, and clean energy investments. Among other things, the Utility proposed to invest a total of approximately $45.0 billion between 2027 and 2030 in CPUC-jurisdictional assets. The proposed investments would support wildfire safety (including undergrounding 307 miles of electrical lines in 2027 and 400 miles per year for 2028 through 2030 until a 10-year undergrounding plan is approved), grid modernization, gas system safety, clean energy, and resilience.

In addition, the Utility requested authorization to establish new balancing accounts for new business capital spend and employee medical expenses.

The Utility is not seeking recovery of compensation of PG&E Corporation’s and the Utility’s officers within the scope of 17 Code of Federal Regulations 240.3b-7.

On July 31, 2025, the CPUC issued a scoping memo that modifies the standard rate case plan schedule. The scoping memo indicates that the CPUC will issue a PD by March 2027 and a final decision by May 2027.

Cost of Capital Proceedings

2026 Cost of Capital Application

On March 20, 2025, the Utility (along with the other IOUs in California) submitted its 2026 Cost of Capital application.

On December 18, 2025, the CPUC issued a final decision and approved the following cost of capital rates, which went into effect beginning January 1, 2026:

CostWeightWeighted Cost
Return on Common Equity9.98%52.00%5.19%
Return on Preferred Equity5.52%0.50%0.03%
Return on Long-term debt5.04%47.50%2.39%

The decision approved a revenue credit to return the benefit of potential DOE loan draws to customers and a temporary yield spread adjustment to compensate the Utility for its actual cost of short-term debt above the commercial paper rate. The yield spread adjustment for 2026 is 125 basis points. The decision also continued the Cost of Capital mechanism pursuant to which the Utility’s ROE will be adjusted and the cost of debt will be trued up to the most recent recorded cost of debt upon a significant change in rates.

Transmission Owner Rate Case for 2024

On October 13, 2023, the Utility filed its TO21 rate case with the FERC. In the filing, the Utility forecasted a 2024 retail electric transmission revenue requirement of $2.83 billion. The Utility requested that FERC approve a 12.37% base ROE as well as a 0.5% adder for its participation in the CAISO. The TO21 filing also addresses the Utility’s capital structure and several new issues including wildfire self-insurance recovery from transmission customers.

On December 29, 2023, the FERC issued an order accepting the TO21 filing subject to refund, establishing a January 1, 2024 effective date, and establishing a settlement and hearing process, but denying the 0.5% ROE adder for participation in the CAISO, which results in a forecast transmission revenue requirement of $2.78 billion. On January 29, 2024, the Utility filed a request for rehearing of the FERC’s denial of the 0.5% ROE adder for participation in the CAISO. On June 12, 2024, the FERC issued an order denying the Utility’s request for rehearing. On June 18, 2024, the Utility and other California IOUs filed an appeal of the FERC’s order denying the Utility’s request for rehearing. On July 11, 2025, the Ninth Circuit Court of Appeals denied the utilities’ joint appeal. On August 20, 2025, the Utility and California IOUs sought en banc review from the Ninth Circuit. On September 15, 2025, the Ninth Circuit denied en banc review. On October 7, 2025, the Utility and California IOUs filed a petition for certiorari with the Supreme Court.

On March 21, 2025, the Utility filed with the FERC a settlement in the TO21 rate case. On August 5, 2025, the FERC issued a decision approving the settlement and resolving all contested issues in the proceeding, as well as specific wildfire cost recovery issues raised by stakeholders in prior proceedings related to the Utility’s TO tariff. The decision sets a base ROE of 10.38%, a fixed capital structure with common equity weighted at 50.0%, preferred equity at 0.3%, and long-term debt at 49.7%.

On December 1, 2025, the Utility filed with the FERC the TO annual update for rate year 2026, which included the provisions of the TO21 settlement. The revenue requirement for rates that went into effect on January 1, 2026 is $2.6 billion, which represents a decrease from the 2025 revenue requirement of $2.9 billion.

Other Regulatory Proceedings

2026-2028 Wildfire Mitigation Plan

On April 4, 2025, the Utility submitted to the OEIS its 2026-2028 WMP, which it revised on July 28, 2025. The 2026-2028 WMP provides a comprehensive overview of the Utility’s wildfire mitigation strategy and incorporates lessons learned from previous years and emerging best practices. On February 5, 2026, the OEIS issued a final decision approving the Utility’s 2026–2028 WMP.

Extension of Diablo Canyon Operations

On September 2, 2022, SB 846 became law. SB 846 supports the extension of operations at DCPP through no later than 2030, with the potential for an earlier retirement date. Under the legislation, the Utility continues to operate DCPP on behalf of all CPUC-jurisdictional LSEs, and all customers of those LSEs are responsible for the cost of extended operations.

The key steps to continued operations are NRC license renewal and approvals from several California state agencies. As of December 31, 2025, the Utility has received all necessary state approvals except for approval from the Central Coast Region Water Quality Control Board. The CPUC’s approval is subject to the following conditions: (1) the NRC continues to authorize DCPP operations; (2) the loan agreement authorized by SB 846 is not terminated; and (3) the CPUC does not make a future determination that DCPP extended operations are imprudent or unreasonable.

On November 7, 2023, the Utility submitted an application for license renewal with the NRC. On December 19, 2023, the NRC deemed the application sufficient, which allows continued operations at DCPP past the plant’s current licenses until the relicensing review is complete. In June 2025, the NRC issued the final safety evaluation report and supplemental environmental impact statement.

SB 884 10-Year Distribution Undergrounding Program

On March 7, 2024, the CPUC approved a resolution that establishes an expedited utility distribution infrastructure undergrounding program pursuant to Public Utilities Code Section 8388.5. The resolution addressed the process and requirements for the CPUC’s review of any large electrical corporation’s 10-year distribution infrastructure undergrounding plan and conditional approval of its related costs. On December 4, 2025, the CPUC approved a resolution that updated and refined the prior resolution and instructed the Utility to file a joint application with SCE and SDGE requesting approval of a proposal to resolve several cost recovery issues, including the benefit-cost ratio and audit methodologies, not addressed in the resolution. On February 9, 2026, the utilities submitted that filing.

On February 20, 2025, the OEIS adopted final program guidelines. The OEIS has indicated that it will issue separate compliance guidelines.