REGULATORY MATTERS
The Utility is subject to substantial regulation by the CPUC, the FERC, the OEIS, the Nuclear Regulatory Commission (“NRC”), and other federal and state regulatory agencies. The resolutions of the proceedings described below and other proceedings may materially affect PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows. Except as otherwise noted, PG&E Corporation and the Utility are unable to predict the timing or outcome of the following proceedings.
During the quarter ended June 30, 2025 and through the date of this filing, key updates to regulatory matters include the following:
On July 25, 2025, the CPUC issued a PD that would increase the cost cap for 2025 and 2026 by an aggregate $2.38 billion in connection with the Order Instituting Rulemaking to Establish Energization Timelines.
On June 2, 2025, the Utility filed an unopposed all-party settlement with intervenors for an additional $461 million revenue requirement, which is incremental to the previously approved interim rate relief for the 2023 WMCE.
On May 15, 2025, the Utility filed its 2027 GRC application with the CPUC.
Cost Recovery Proceedings
Periodically, costs arise that could not have been anticipated by the Utility during CPUC GRC proceedings or that have been deliberately excluded from such proceedings. For instance, these costs may result from catastrophic events, changes in regulation, or extraordinary changes in operating practices. The Utility may seek authority to track incremental costs in a memorandum account and the CPUC may later authorize recovery of costs tracked in memorandum accounts if the costs are deemed incremental and prudently incurred. The CPUC may also authorize balancing accounts with limitations or caps on cost recovery. These accounts, which include the CEMA, WEMA, Fire Hazard Prevention Memorandum Account (“FHPMA”), FRMMA, WMPMA,VMBA, Wildfire Mitigation Balancing Account (“WMBA”), and Microgrids Memorandum Account (“MGMA”), among others, allow the Utility to track the costs associated with work related to disaster and wildfire response, other wildfire prevention-related costs, and certain third-party wildfire claims. While the Utility generally expects such costs to be recoverable, the CPUC may authorize the Utility to recover less than the full amount of its costs.
In recent years, the Utility has recorded significant amounts to these accounts. Because rate recovery may require CPUC authorization of the costs in these accounts, there can be a delay between when the Utility incurs costs and when it may recover those costs. As of June 30, 2025, the Utility had recorded an aggregate amount of approximately $3.1 billion in costs for the CEMA, WEMA, FRMMA, WMPMA, VMBA, WMBA, and MGMA. Of these costs, approximately $0.6 billion was authorized for recovery and accounted for as current, and $2.5 billion was accounted for as long term as of June 30, 2025. See Note 3 of the Notes to the Condensed Consolidated Financial Statements in Part I, Item 1.
If the amount of the costs recorded in these accounts continues to increase, or the delay between incurring and recovering costs lengthens, PG&E Corporation and the Utility may incur additional financing costs. If the Utility does not recover the full amount of its recorded costs, the difference between the recorded and recovered amounts would be written off as a non-cash disallowance. Such disallowances could materially affect PG&E Corporation’s and the Utility’s financial condition, results of operations, liquidity, and cash flows.
For more information, see Note 3 of the Notes to the Condensed Consolidated Financial Statements in Part I, Item 1, and “Wildfire Mitigation and Catastrophic Events Cost Recovery Applications” and “Wildfire and Gas Safety Costs Recovery Application” below.
The Utility’s cost recovery proceedings for the costs described above that are pending, have pending appeals, or were completed during the six months ended June 30, 2025 are summarized in the following table:
| Proceeding | Request (1) | Status |
|---|---|---|
| 2022 WMCE | Revenue requirement of approximately $1.29 billion | Filed December 2022. Decision authorizing $1.1 billion of interim rate relief adopted June 2023. Partial settlement filed December 2023. |
| 2023 WMCE | Revenue requirement of approximately $1.86 billion | Application filed December 2023. Decision authorizing $944 million of interim rate relief adopted September 2024. Partial settlement filed June 2025. |
| 2024 WMCE | Revenue requirement of approximately $435 million | Application filed November 2024. |
| 2023 WGSC | Revenue requirement of approximately $688 million | Application filed June 2023. Decision authorizing $516 million of interim rate relief adopted March 2024. |
(1) The revenue requirement amounts requested do not include interest.
Wildfire Mitigation and Catastrophic Events Cost Recovery Applications
2022 WMCE Application
On December 15, 2022, the Utility filed an application with the CPUC requesting cost recovery of approximately $1.36 billion of recorded expenditures, resulting in a proposed revenue requirement of approximately $1.29 billion (the “2022 WMCE application”). The costs addressed in the 2022 WMCE application reflect costs related to wildfire mitigation and certain catastrophic events, as well as implementation of various customer-focused initiatives. These costs were incurred primarily in 2021.
The recorded expenditures consist of $1.2 billion in expenses and $136 million in capital expenditures. On June 8, 2023, the CPUC adopted a final decision granting the Utility interim rate relief of $1.1 billion to be recovered over 12 months, which went into effect July 1, 2023. The remaining $224 million will be recovered to the extent it is approved after the CPUC issues a final decision for such requested rate relief. Cost recovery requested in the 2022 WMCE application is subject to the CPUC’s reasonableness review, which could result in some or all of the interim rate relief being subject to refund. See “2022 WMCE Interim Rate Relief Subject to Refund” in Note 11 of the Notes to the Condensed Consolidated Financial Statements in Part I, Item 1.
On December 22, 2023, the Utility filed an unopposed joint settlement with intervenors for an additional $70 million revenue requirement, which is incremental to the previously approved interim rate relief. If the CPUC adopts the settlement agreement, it would resolve all costs recorded to accounts other than the VMBA and the WMBA. The settlement agreement did not address the Utility’s revenue requirement request of $916 million associated with costs recorded to the VMBA or the WMBA, for which cost recovery will be determined separately by the CPUC.
On December 19, 2024, the CPUC extended the statutory deadline to resolve the remaining issues in the proceeding to September 30, 2025.
2023 WMCE Application
On December 1, 2023, the Utility filed an application with the CPUC requesting cost recovery of approximately $2.18 billion of recorded expenditures, resulting in a proposed revenue requirement of approximately $1.86 billion (the “2023 WMCE application”). The costs addressed in the 2023 WMCE application reflect costs related to wildfire mitigation and certain catastrophic events, as well as implementation of various customer-focused initiatives. These costs were incurred primarily in 2022.
The recorded expenditures consist of $1.6 billion in expenses and $559 million in capital expenditures. Of these amounts, approximately 15% of expense, or $239 million, and 30% of capital expenditures, or $167 million, relate to the Utility’s response to the 2022-2023 extreme winter storms CEMA event.
On September 16, 2024, the CPUC issued a final decision on interim rate recovery that grants the Utility interim rate relief of $944 million, plus interest, subject to refund, to be recovered over at least 17 months starting October 1, 2024. The remaining $914 million, plus interest, would be recovered to the extent it is approved after the CPUC issues a final decision. Cost recovery requested in the 2023 WMCE application is subject to the CPUC’s reasonableness review, which could result in some or all of the interim rate relief being subject to refund.
On April 14, 2025, the CPUC issued a PD that would extend the statutory deadline in this matter to December 1, 2025.
On June 2, 2025, the Utility filed an unopposed all-party settlement with intervenors for an additional $461 million revenue requirement, which is incremental to the previously approved interim rate relief. If the CPUC adopts the settlement agreement, it would resolve all costs recorded to accounts other than the VMBA. The settlement agreement did not address the Utility’s revenue requirement request of $833 million associated with costs recorded to the VMBA, for which cost recovery will be determined separately by the CPUC.
2024 WMCE Application
On November 21, 2024, the Utility filed an application with the CPUC requesting cost recovery of approximately $596 million of recorded expenditures in the CEMA and other accounts, resulting in a revenue requirement of approximately $435 million (the “2024 WMCE application”). The costs addressed in the 2024 WMCE application include those incurred in connection with rebuild and restoration activities, certain catastrophic wildfire and weather events, and other programs supporting gas, customer, and climate initiatives. These costs were incurred primarily in 2023.
The recorded expenditures consist of $80 million in expense and $516 million in capital expenditures. Of these amounts, approximately $50 million of expense and $396 million of capital expenditures relate to community rebuild and restoration activities and other catastrophic events included in the CEMA.
Wildfire and Gas Safety Costs Recovery Application
On June 15, 2023, the Utility filed a WGSC application with the CPUC requesting cost recovery of approximately $2.5 billion of recorded expenditures related to wildfire mitigation costs and gas safety and electric modernization costs.
The recorded expenditures for wildfire mitigation consist of $726 million in expenses and $1.5 billion in capital expenditures and cover activities during the years 2020 to 2022. The recorded expenditures for gas safety and electric modernization efforts consist of $120 million in expenses and $118 million in capital expenditures and cover activities during the years 2017 to 2022. If approved, the requested cost recovery would result in an aggregate revenue requirement of $688 million. The costs addressed in the WGSC application are incremental to those previously authorized in the Utility’s 2020 GRC and other proceedings.
The Utility recorded these costs to the memorandum and balancing accounts as set forth in the following table:
| (in millions) | Recorded Costs |
|---|---|
| WMPMA | $2,095 |
| FRMMA | 165 |
| Gas storage balancing account | 101 |
| In line inspection memorandum account | 92 |
| Other | 45 |
| Total | $2,498 |
In connection with the WGSC application, the Utility also requested interim rate relief of $583 million. The remaining $105 million would be recovered after the CPUC issues a final decision. On March 7, 2024, the CPUC approved a final decision authorizing the Utility to recover $516 million in interim rates to be recovered over at least 12 months starting April 1, 2024.
On June 12, 2025, the CPUC issued a decision extending the statutory deadline in the proceeding from June 30, 2025 to March 31, 2026.
Forward-Looking Rate Cases
The Utility routinely participates in forward-looking rate case applications before the CPUC and the FERC. Those applications include GRCs, where the revenue required for general operations (“base revenue”) of the Utility is assessed and reset. In addition, the Utility is periodically involved in “cost of capital” proceedings to adjust its regulated return on rate base. The Utility’s future earnings will depend on the revenue requirements authorized in such rate cases. The Utility also expects to file its SB 884 cost application with the CPUC after the OEIS approves guidelines. See “SB 884 10-Year Distribution Undergrounding Program” below.
Decisions in GRC proceedings have historically been expected prior to the commencement of the period to which the rates would apply. In recent decades, decisions in GRC proceedings have been delayed. Delayed decisions may cause the Utility to develop its budgets based on possible outcomes, rather than authorized amounts. When decisions are delayed, the CPUC typically provides rate relief to the Utility effective as of the commencement of the rate case period (not effective as of the date of the delayed decision). Nonetheless, the Utility’s spending during the period of the delay may exceed the authorized amount, without an ability for the Utility to seek cost recovery of such excess. If the Utility’s spending during the period of the delay is less than the authorized amount, the Utility could be exposed to operational and financial risks associated with the lower level of work achieved compared to that funded by the CPUC.
The Utility’s forward-looking rate cases that are pending, have pending appeals, or were completed during the quarter ended June 30, 2025 are summarized in the following table:
| Rate Case | Request | Status |
|---|---|---|
| Energization Timelines OIR | Capital cost cap increase of $3.13 billion for 2025 and 2026 | PD authorizing $2.38 billion increase for 2025 and 2026 cost cap issued in July 2025. |
| 2027 GRC | Revenue requirement of $16.64 billion for 2027 | Filed May 2025. A decision is requested by the fourth quarter of 2026. |
| 2026 Cost of Capital | Increase ROE to 11.30% and cost of debt to 5.05% | Filed March 2025. |
| Transmission Owner Rate Case for 2024 | Revenue requirement of $2.78 billion for 2024 | Accepted December 2023, except as to CAISO adder. Appeal of FERC’s order regarding CAISO adder denied July 2025. All other issues settled March 2025. |
Energization Timelines Order Instituting Rulemaking
As previously disclosed, on July 16, 2024, the CPUC issued a final decision approving a memorandum account with interim rate relief for the Utility to recover energization costs incremental to the forecasts of the Utility’s Phase 1 2023 GRC, subject to annual caps and reasonableness review in the 2027 GRC application. The overall expenditure cap was set at $2.26 billion for the period of 2024 to 2026. The decision also permitted the Utility to request revisions to the 2025 and 2026 cap amounts under certain conditions. On October 4, 2024, the Utility filed a motion to increase the 2025 and 2026 cap amounts by an aggregate $3.13 billion.
On July 25, 2025, the administrative law judge issued a PD that would increase the cost cap for 2025 and 2026 by an aggregate $2.38 billion.
2027 General Rate Case
On May 15, 2025, the Utility filed its 2027 GRC application with the CPUC. In the 2027 GRC, the CPUC will determine the annual amount of revenue requirements that the Utility will be authorized to collect through rates from 2027 through 2030 to recover its anticipated costs for gas distribution, transmission and storage, electric distribution, and electric generation and to provide the Utility an opportunity to earn its authorized rate of return.
The table below compares the portion of CPUC jurisdictional revenue requirements and weighted-average rate base that are requested in the GRC proceeding from 2027 through 2030 to the amounts adopted for 2026 in the 2023 GRC and other cost recovery proceedings:
| Year | Requested revenue requirement (in billions) | Requested weighted-average GRC rate base |
|---|---|---|
| 2026 (as adopted) | $15.4 | 54.0 |
| 2027 | 16.6 | 67.0 |
| 2028 | 17.7 | 73.4 |
| 2029 | 18.7 | 79.4 |
| 2030 | 19.9 | 85.4 |
In the 2027 GRC application, the Utility proposed various safety, resiliency, and clean energy investments. Among other things, the Utility proposed to invest a total of approximately $45.0 billion between 2027 and 2030 in CPUC-jurisdictional assets. The proposed investments would support wildfire safety (including undergrounding 307 miles of electrical lines each year until a 10-year undergrounding plan is approved), grid modernization, gas system safety, clean energy, and resilience.
In addition, the Utility requested authorization to establish new balancing accounts for new business capital spend and employee medical expenses.
The Utility is not seeking recovery of compensation of PG&E Corporation’s and the Utility’s officers within the scope of 17 Code of Federal Regulations 240.3b-7.
In its application, in accordance with the CPUC’s standard rate case plan schedule, the Utility requests that the CPUC issue a PD by November 1, 2026. It also requests that the 2027 GRC rates be effective January 1, 2027.
Cost of Capital Proceedings
2026 Cost of Capital Application
On March 20, 2025, the Utility (along with the other IOUs in California) submitted its 2026 Cost of Capital application. These applications set the cost of capital, ROE, cost of preferred stock, and cost of debt for the Utility’s electric generation, electric distribution, natural gas distribution, and natural gas transmission and storage rate base beginning on January 1, 2026.
In the application, the Utility requests the following cost of capital rates:
| Cost | Weight | Weighted Cost | |
|---|---|---|---|
| Return on Common Equity | 11.30% | 52.00% | 5.88% |
| Return on Preferred Equity | 5.52% | 0.30% | 0.02% |
| Return on Long-term debt | 5.05% | 47.70% | 2.41% |
The application also requests CPUC approval of a revenue credit to return the benefit of potential DOE loan draws to customers, and a temporary yield spread adjustment to compensate the Utility for its actual cost of short-term debt. The scoping memo issued by the CPUC provides for a procedural schedule that would provide a final decision in 2025.
Transmission Owner Rate Cases
Transmission Owner Rate Case for 2024 (the “TO21” rate case)
On October 13, 2023, the Utility filed its TO21 rate case with the FERC. In the filing, the Utility forecasted a 2024 retail electric transmission revenue requirement of $2.83 billion. The Utility requested that FERC approve a 12.37% base ROE as well as a 0.5% adder for its participation in the CAISO. The TO21 filing also addresses the Utility’s capital structure and several new issues including wildfire self-insurance recovery from transmission customers.
On December 29, 2023, the FERC issued an order accepting the TO21 filing subject to refund, establishing a January 1, 2024 effective date, and establishing a settlement and hearing process, but denying the 0.5% ROE adder for participation in the CAISO, which results in a forecast transmission revenue requirement of $2.78 billion. On January 29, 2024, the Utility filed a request for rehearing of the FERC’s denial of the 0.5% ROE adder for participation in the CAISO. On June 12, 2024, the FERC issued an order denying the Utility’s request for rehearing. On June 18, 2024, the Utility and other California IOUs filed an appeal of the FERC’s order denying the Utility’s request for rehearing. On July 11, 2025, the Ninth Circuit Court of Appeals denied the utilities’ joint appeal.
On March 21, 2025, the Utility filed with the FERC a settlement in the TO21 rate case. The settlement would resolve all contested issues in the proceeding, as well as specific wildfire cost recovery issues raised by stakeholders in prior proceedings related to the Utility’s TO tariff. The settlement would set a base ROE of 10.38%. The settlement would set a fixed capital structure with common equity weighted at 50.0%, preferred equity at 0.3%, and long-term debt at 49.7%.
Other Regulatory Proceedings
2023-2025 Wildfire Mitigation Plan
The Utility submitted an updated 2025 WMP on April 2, 2024, as directed by the OEIS. On November 19, 2024, the OEIS issued a final approval of the Utility’s 2025 WMP update. On January 16, 2025, the CPUC ratified the OEIS’s approval.
On December 5, 2024, the Utility filed a change order request to update some of the forecasted work in the WMP for 2025. On February 10, 2025, the OEIS issued a decision approving both initiatives in the change order request.
2026-2028 Wildfire Mitigation Plan
On April 4, 2025, the Utility submitted its 2026-2028 WMP to the OEIS. The 2026-2028 WMP provides a comprehensive overview of the Utility’s wildfire mitigation strategy and incorporates lessons learned from previous years and emerging best practices.
SB 884 10-Year Distribution Undergrounding Program
On March 7, 2024, the CPUC approved a resolution that establishes an expedited utility distribution infrastructure undergrounding program pursuant to Public Utilities Code Section 8388.5. The resolution addresses the process and requirements for the CPUC’s review of any large electrical corporation’s 10-year distribution infrastructure undergrounding plan and conditional approval of its related costs.
On February 20, 2025, the OEIS adopted final program guidelines. The OEIS has indicated that it will issue separate compliance guidelines.
The Utility expects to submit its undergrounding plan to the OEIS in late 2025, before submitting its cost application to the CPUC, as directed in Public Utilities Code Section 8388.5.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.