Skip to main content

AMEREN CORP

For the period ended Dec 31, 2024. Filed Feb 18, 2025.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2024 · Filed Feb 18, 2025

AEE$114.02+1.0%Stored close · as of Nov 9, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

Supply of Electric Power

Capacity

Ameren Missouri sells all of its capacity to the MISO and purchases the capacity it needs to supply its native load sales from the MISO. Ameren Illinois purchases capacity from the MISO and through bilateral contracts resulting from IPA procurement events. In 2022, the FERC issued an order approving changes to the annual MISO capacity auction. Historically, the auctions were designed to cover annual peak demand plus a target reserve margin. Beginning with the April 2023 auction for the June 2023 to May 2024 planning year, auctions include four seasonal load forecasts and available capacity levels and are designed to cover each season’s peak demand plus a target reserve margin. The seasonal auction structure was established to help to address variability in resources as the MISO begins to rely more heavily on renewable generation.

Ameren Missouri’s electric supply is primarily generated from its energy centers. Factors that could cause Ameren Missouri to purchase power include, among other things, energy center outages, the fulfillment of renewable energy requirements, extreme weather conditions, the availability of power at a cost lower than its generation cost, and the lack of sufficient owned generation availability.

Ameren Missouri files a long-term nonbinding preferred resource plan with the MoPSC every three years. The most recent preferred resource plan was filed in September 2023. Ameren Missouri expects to file a notice of change in its preferred resource plan with the MoPSC in February 2025 to address new load growth opportunities resulting from entities in various industries, including data center and manufacturing, that are considering either locating or expanding their operations within Ameren Missouri’s service territory. The 2025 Change to the 2023 PRP is expected to include, among other things, the following:

adding 1,600 MWs of natural gas-fired simple-cycle generation by 2030, which includes the 800-MW Castle Bluff Natural Gas Project discussed in Note 2 – Rate and Regulatory Matters under Part II, Item 8, of this report, and an additional 1,200 MWs by 2043;

adding 2,100 MWs of natural gas-fired combined-cycle generation by 2035 and an additional 1,200 MWs by 2040;

adding 3,200 MWs of renewable generation by 2030, which includes the 900 MWs of solar generation projects discussed in Note 2 – Rate and Regulatory Matters under Part II, Item 8, of this report, and an additional 1,500 MWs by 2035;

adding 1,000 MWs of battery storage by 2030 and an additional 800 MWs by 2042;

adding 1,500 MWs of nuclear generation by 2040;

retiring all of Ameren Missouri’s coal-fired energy centers by 2042;

retiring 1,800 MWs of Ameren Missouri’s natural gas-fired energy centers by 2040 to comply with Illinois law;

the continued implementation of customer energy-efficiency and demand response programs; and

the expectation that Ameren Missouri will seek and receive NRC approval for an extension of the operating license for the Callaway Energy Center beyond its current 2044 expiration date.

The addition of renewable, natural gas-fired, or nuclear generation facilities is subject to obtaining necessary project approvals, including FERC approval and the issuance of a CCN by the MoPSC, as applicable. Ameren Missouri would be adversely affected if the MoPSC does not allow recovery of the remaining investment and decommissioning costs associated with the retirement of an energy center, as well as the ability to earn a return on that remaining investment and those decommissioning costs. The next preferred resource plan is required to be filed by October 2026.

Ameren Missouri continues to evaluate its longer-term needs for new generating capacity. The need for investment in new sources of energy is dependent on several key factors, including continuation of and customer participation in energy-efficiency programs, the amount of distributed generation from customers, load growth, including demand from data centers, technological advancements, costs of generation alternatives, environmental regulation of coal-fired and natural gas-fired power plants, changes in United States energy policy and priorities under the current federal administration, and state renewable energy requirements, which could lead to the retirement of current baseload assets before the end of their current useful lives or alterations in the way those assets operate, which could result in increased capital expenditures and/or increased operations and maintenance expenses. Because of the significant time required to plan, acquire permits for, and build a baseload energy center, Ameren Missouri continues to study alternatives and to take steps to preserve options to meet future demand. Steps include evaluating the potential for further diversification of Ameren Missouri’s generation portfolio through renewable energy generation, including wind and solar generation, natural gas-fired generation, including the potential to switch to hydrogen fuel and/or blend hydrogen fuel with natural gas and install carbon capture technology, extending the operating license for the Callaway Energy Center, additional customer energy-efficiency and demand response programs, distributed energy resources, and energy storage.

Missouri law required Ameren Missouri to offer solar rebates through December 2023 and currently requires Ameren Missouri to offer net metering to certain customers that install renewable generation at their premises. The difference between the cost of the solar rebates and the amount set in base rates was deferred as a regulatory asset or liability under the RESRAM, and earns carrying costs at short-term interest rates. Customers that elect to enroll in net metering are allowed to net their generation against their distribution usage within each billing month.

In Illinois, while electric transmission and distribution service rates are regulated, power supply prices are not. Although electric customers are allowed to purchase power from an alternative retail electric supplier, Ameren Illinois is required to be the provider of last resort for its electric distribution customers. In 2024, 2023, and 2022, Ameren Illinois procured power on behalf of its customers for 25%, 28%, and 28%, respectively, of its total kilowatthour sales. Power purchased by Ameren Illinois for its electric distribution customers who do not elect to purchase their power from an alternative retail electric supplier comes either through procurement processes conducted by the IPA or through markets operated by the MISO. The IPA administers an RFP process through which Ameren Illinois procures its expected supply. The purchased power and related procurement costs incurred by Ameren Illinois are passed directly to its electric distribution customers through a cost recovery mechanism. Transmission costs are charged to customers who purchase electricity from Ameren Illinois through a cost recovery mechanism. The purchased power, power procurement, and transmission costs are reflected in Ameren Illinois Electric Distribution’s results of operations, but do not affect Ameren Illinois Electric Distribution’s earnings because these costs are offset by corresponding revenues. Ameren Illinois charges distribution service rates to electric distribution customers who purchase electricity, regardless of supplier, which does affect Ameren Illinois Electric Distribution’s earnings.

Pursuant to the CEJA, Ameren Illinois is required to file a Grid Plan with the ICC every four years. In December 2024, the ICC issued an order approving Ameren Illinois’ revised Grid Plan under its MYRP proceeding for electric distribution service for 2024 through 2027. For additional information regarding Ameren Illinois’ MYRP proceeding, see Note 2 – Rate and Regulatory Matters under Part II, Item 8, of this report. The Grid Plan outlines how Ameren Illinois expects to invest in electric distribution infrastructure in order to support grid modernization, clean energy, energy efficiency, and the state of Illinois’ renewable energy, equity, climate, electrification, and environmental goals. Ameren Illinois’ next Grid Plan is required to be filed by mid-January 2026.

Illinois law requires Ameren Illinois to offer rebates and net metering to certain customers who install renewable generation or paired energy storage systems at their premises. The cost of the customer generation rebate program is deferred as a regulatory asset, which earns a return at the applicable WACC. Customers that elect to receive a generation rebate and are enrolled in net metering are allowed to net their power supply service charges, but not their distribution service charges. Customers that elect to receive energy storage rebates and have not received generation rebates are allowed to net their power supply and distribution service charges. By law, Ameren Illinois’ electric distribution revenues are decoupled from sales volumes, which ensures that the electric distribution revenues authorized in a regulatory rate review are not affected by changes in sales volumes.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.