Q2 2025 PROJECT AND CONSTRUCTION HIGHLIGHTS

On April 1, 2025, the JV Partners announced the final investment decision (“FID”) for construction of Phase 1 of Thacker Pass.

During the quarter ended June 30, 2025, $124.8 million of construction capital costs and other project-related costs were capitalized. As of June 30, 2025, a total of $574.1 million of construction capital costs and other project-related costs have been capitalized.

The Company has resolved or secured judicial dismissal of all legal and regulatory actions and proceedings, which arose in the ordinary course of resource development. Those resolutions did not materially impact the Company’s financial position or construction schedule. The Company continues to progress major construction at Thacker Pass. Completion of Phase 1 of Thacker Pass is targeted for late 2027.

Project engineering and procurement continue materially in line with the Project schedule to support construction.

o

As of June 30, 2025, detailed engineering is approximately 70% design complete and expected to increase to over 90% design complete by year end 2025. The higher level of detailed engineering at the early stages of construction helps to de-risk execution in terms of Project schedule and cost.

o

In April 2025, fabrication of the structural steel to be used to build the facilities at Thacker Pass commenced. First steel installation is targeted to commence in September 2025.

o

Manufacturing of long-lead equipment continues to advance with expected delivery in line with the Project schedule.

o

The Company has entered into certain long-term purchase agreements related to long-lead equipment, infrastructure and services related to the construction of the processing plant as well as development and mining services at Thacker Pass. To date, approximately $425 million has been committed.

Major construction at Thacker Pass is progressing, with permanent concrete placement in the processing plant area commencing in early May 2025. Activity at site is focused on key areas to enable peak construction, which is expected in 2026. As of June 30, 2025:

o

There were approximately 300 manual craft workers on site, which is expected to increase to approximately 1,000 workers by year end 2025. At peak construction, approximately 1,800 workers are expected on site.

o

Structural excavation was underway to support the buildout of facilities and structural elements such as pipe racks.

o

Foundation preparation and rebar for concrete for the processing plant facilities continued to progress.

o

Construction of permanent roads and entrances to the processing plant facilities were underway.

o

Worker break tents were nearing completion.

Placement of housing modules at the Company’s all-inclusive housing facility for construction workers in Winnemucca (the “Workforce Hub” or “WFH”) is well advanced. Mechanical, electrical and plumbing work is progressing, with first occupancy targeted for the second half of 2025. The completion of the WFH will enable ramp-up in the number of construction workers at site.