HECLA MINING CO/DE/
For the period ended Jun 30, 2025. Filed Aug 6, 2025.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Jun 30, 2025 · Filed Aug 6, 2025
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Consolidated Results of Operations
Total sales for the three and six months ended June 30, 2025 and 2024 were as follows:
| Three Months EndedJune 30, | Six Months EndedJune 30, | |||
|---|---|---|---|---|
| (in thousands) | 2025 | 2024 | 2025 | 2024 |
| Silver | $122,661 | $112,692 | $240,814 | $198,925 |
| Gold | 123,721 | 82,469 | 210,909 | 149,884 |
| Lead | 21,476 | 23,928 | 43,582 | 43,411 |
| Zinc | 31,138 | 32,496 | 64,263 | 57,460 |
| Copper | 979 | — | 1,370 | — |
| Less: Smelter and refining charges | (2,544) | (9,282) | (9,256) | (22,296) |
| Total metal sales | 297,431 | 242,303 | 551,682 | 427,384 |
| Environmental remediation services | 6,596 | 3,354 | 13,684 | 7,801 |
| Total sales | $304,027 | $245,657 | $565,366 | $435,185 |
Environmental remediation services revenue is generated by performing remediation work in the historical Yukon Territory mining district on behalf of the Canadian government. The scope and estimated cost of all work is agreed to in advance by the Canadian government, and the expenses incurred are essentially passed through to the government for reimbursement with minimal margin generated by us in performing this work.
Total metal sales for the three and six months ended June 30, 2025 and 2024, and the approximate variances attributed to differences in metals prices, sales volumes and smelter terms, were as follows:
| (in thousands) | Silver | Gold | Base metals | Less: smelter and refining charges | Total sales of products |
|---|---|---|---|---|---|
| Three months ended June 30, 2024 | $112,692 | $82,469 | $56,424 | $(9,282) | $242,303 |
| Variances - 2025 versus 2024: | |||||
| Price | 16,775 | 36,976 | (9,156) | — | 44,595 |
| Volume | (6,806) | 4,276 | 6,325 | (772) | 3,023 |
| Smelter terms | — | — | — | 7,510 | 7,510 |
| Three months ended June 30, 2025 | $122,661 | $123,721 | $53,593 | $(2,544) | $297,431 |
| (in thousands) | Silver | Gold | Base metals | Less: smelter and refining charges | Total sales of products |
|---|---|---|---|---|---|
| Six months ended June 30, 2024 | $198,925 | $149,884 | $100,871 | $(22,296) | $427,384 |
| Variances - 2025 versus 2024: | |||||
| Price | 47,884 | 62,082 | (5,227) | — | 104,739 |
| Volume | (5,995) | (1,057) | 13,571 | — | 6,519 |
| Smelter terms | — | — | — | 13,040 | 13,040 |
| Six months ended June 30, 2025 | $240,814 | $210,909 | $109,215 | $(9,256) | $551,682 |
The fluctuation in sales for the three and six months ended June 30, 2025 compared to the same periods in 2024 was primarily due to the following:
Higher average realized prices for precious metals, partly offset by lower realized lead prices for both periods and zinc for the three months ended June 30, 2025, compared to the same periods in 2024. The table below summarizes average spot prices and our average realized prices for the commodities we sell:
| Three Months EndedJune 30, · Six Months EndedJune 30, | |||||
|---|---|---|---|---|---|
| 2025 · 2024 · 2025 · 2024 | |||||
| Silver – | London PM Fix ($/ounce) | $33.63 | $28.86 | $32.77 | $26.11 |
| Realized price per ounce | $34.82 | $29.77 | $34.20 | $27.37 | |
| Gold – | London PM Fix ($/ounce) | $3,279 | $2,338 | $3,071 | $2,205 |
| Realized price per ounce | $3,314 | $2,338 | $3,148 | $2,222 | |
| Lead – | LME Final Cash Buyer ($/pound) | $0.88 | $0.98 | $0.89 | $0.96 |
| Realized price per pound | $0.92 | $1.06 | $0.92 | $1.02 | |
| Zinc – | LME Final Cash Buyer ($/pound) | $1.20 | $1.29 | $1.24 | $1.20 |
| Realized price per pound | $1.31 | $1.51 | $1.31 | $1.30 | |
| Copper – | LME Final Cash Buyer ($/pound) | $4.32 | $— | $4.28 | $— |
| Realized price per pound | $4.56 | $— | $4.52 | $— | |
Average realized prices typically differ from average market prices primarily because concentrate sales are generally recorded as revenues at the time of shipment at forward prices for the estimated month of settlement, which differ from average market prices. Due to the time elapsed between shipment of concentrates and final settlement with the customers, we must estimate the prices at which sales of our metals will be settled. Previously recorded sales are adjusted to estimated settlement metals prices each period through final settlement. We recorded net positive price adjustments to provisional settlements of $4.2 million and $11.0 million for the three months ended June 30, 2025 and 2024, and $11.1 million and $14.5 million for the six months ended June 30, 2025 and 2024, respectively. The price adjustments related to silver, gold, zinc, lead and copper contained in our concentrate shipments were partially offset by gains and losses on forward contracts for those metals. See Note 8 of Notes to Condensed Consolidated Financial Statements (Unaudited)for more information. The gains and losses on these contracts are included in revenues and impact the realized prices for silver, gold, lead, zinc and copper. Realized prices are calculated by dividing gross revenues for each metal (which include the price adjustments and gains and losses on the forward contracts discussed above) by the payable quantities of each metal included in concentrate, doré and carbon material shipped during the period.
The positive effect of higher metal prices was partially offset by lower silver sales volumes during the three and six months ended June 30, 2025 compared to the comparable 2024 period. Lower silver ounces sold were related to reduced production at
Greens Creek in the first quarter and lower production at Keno Hill due to lower throughput. Though gold production is higher than the comparable 2024 periods, an inventory build at Casa Berardi during the quarter resulted in gold ounces sold being largely consistent with 2024. See The Greens Creek Segment, The Lucky Friday Segment, The Keno Hill Segment, and Casa Berardi Segment sections below for more information on metal production and sales volumes at each of our operating segments. Total metals production and sales volumes for each period are shown in the following table:
| Three Months EndedJune 30, · Six Months EndedJune 30, | |||||
|---|---|---|---|---|---|
| 2025 · 2024 · 2025 · 2024 | |||||
| Silver - | Ounces produced | 4,520,510 | 4,458,484 | 8,632,904 | 8,650,582 |
| Payable ounces sold | 3,522,975 | 3,785,285 | 7,040,945 | 7,267,169 | |
| Gold - | Ounces produced | 45,895 | 37,324 | 80,127 | 73,916 |
| Payable ounces sold | 37,333 | 35,276 | 66,988 | 67,465 | |
| Lead - | Tons produced | 14,650 | 13,587 | 28,657 | 25,686 |
| Payable tons sold | 11,663 | 11,338 | 23,653 | 21,359 | |
| Zinc - | Tons produced | 18,479 | 16,191 | 35,414 | 32,402 |
| Payable tons sold | 11,667 | 10,781 | 24,514 | 22,102 | |
| Copper | Tons produced | 499 | 462 | 910 | 957 |
| Payable tons sold | 108 | — | 152 | — | |
The difference between what we report as “ounces/tons produced” and “payable ounces/tons sold” is attributable to the difference between the quantities of metals contained in the concentrates we produce versus the portion of those metals actually paid for by our customers according to the terms of our sales contracts. Differences can also arise from inventory changes incidental to shipping schedules, or variances in ore grades which impact the amount of metals contained in concentrates produced and sold.
Sales, total cost of sales, gross profit (loss), Cash Cost, After By-product Credits, per Ounce (“Cash Cost”) (non-GAAP) and AISC (non-GAAP) at our operating segments for the three and six months ended June 30, 2025 and 2024 were as follows (in thousands, except for Cash Cost and AISC):
| Silver · Gold and Other | |||||||
|---|---|---|---|---|---|---|---|
| Greens Creek | Lucky Friday | Keno Hill | Total Silver (2) | Casa Berardi | Other (3) | Total Gold and Other | |
| Three Months Ended June 30, 2025: | |||||||
| Sales | $122,002 | $64,273 | $26,121 | $212,396 | $85,035 | $6,596 | $91,631 |
| Total cost of sales | (58,921) | (42,286) | (25,881) | (127,088) | (50,790) | $(6,625) | (57,415) |
| Gross profit (loss) | $63,081 | $21,987 | $240 | $85,308 | $34,245 | $(29) | $34,216 |
| Cash Cost (1) | $(11.91) | $6.19 | $— | $(5.46) | $1,578 | $— | $1,578 |
| AISC (1) | $(8.19) | $19.07 | $— | $5.19 | $1,669 | $— | $1,669 |
| Three Months Ended June 30, 2024: | |||||||
| Sales | $95,659 | $59,071 | $28,950 | $183,680 | $58,623 | $3,354 | $61,977 |
| Total cost of sales | (56,786) | (37,523) | (28,950) | (123,259) | (67,340) | (3,628) | (70,968) |
| Gross profit (loss) | $38,873 | $21,548 | $— | $60,421 | $(8,717) | $(274) | $(8,991) |
| Cash Cost (1) | $0.19 | $5.32 | $— | $2.08 | $1,701 | $— | $1,701 |
| AISC (1) | $5.40 | $12.74 | $— | $12.54 | $1,825 | $— | $1,825 |
| Silver · Gold | |||||||
|---|---|---|---|---|---|---|---|
| Greens Creek | Lucky Friday | Keno Hill | Total Silver (2) | Casa Berardi | Other (3) | Total Gold | |
| Sales | $240,145 | $127,467 | $43,030 | $410,642 | $141,040 | $13,684 | $154,724 |
| Total cost of sales | (128,559) | (86,335) | (41,752) | (256,646) | (101,472) | (13,720) | (115,192) |
| Gross profit (loss) | $111,586 | $41,132 | $1,278 | $153,996 | $39,568 | $(36) | $39,532 |
| Cash Cost (1) | $(8.37) | $7.77 | $— | $(2.29) | $1,837 | $— | $1,837 |
| AISC (1) | $(4.50) | $19.57 | $— | $8.35 | $1,935 | $— | $1,935 |
| Sales | $192,969 | $94,411 | $39,797 | $327,177 | $100,207 | $7,801 | 108,008 |
| Total cost of sales | (126,643) | (65,042) | (39,797) | (231,482) | (125,600) | (7,513) | (133,113) |
| Gross profit (loss) | $66,326 | $29,369 | $— | $95,695 | $(25,393) | $288 | $(25,105) |
| Cash Cost (1) | $1.90 | $6.67 | $— | $3.38 | $1,685 | $— | $1,685 |
| AISC (1) | $6.33 | $14.50 | $— | $12.81 | $1,861 | $— | $1,861 |
(1)
A reconciliation of these non-GAAP measures to total cost of sales, the most comparable GAAP measure, can be found below in Reconciliation of Total Cost of Sales (GAAP) to Cash Cost, Before By-product Credits and Cash Cost, After By-product Credits (non-GAAP) and All-In Sustaining Cost, Before By-product Credits and All-In Sustaining Cost, After By-product Credits (non-GAAP).
(2)
The calculation of AISC for our consolidated silver properties includes corporate costs for general and administrative expense and sustaining capital.
(3)
For the three and six months ended June 30, 2025, Other includes sales of $6.6 million and $13.7 million and total cost of sales of $6.6 million and $13.7 million respectively, from our environmental remediation services in the Yukon. For the three and six months ended June 30, 2024, Other includes sales of $3.4 million and $7.8 million and total cost of sales of $3.6 million and $7.5 million, respectively.
While revenue from zinc, lead, copper and gold by-products is significant, we believe that identification of silver as the primary product of Greens Creek, Lucky Friday and Keno Hill is appropriate because:
silver has historically accounted for a higher proportion of revenue than any other metal and is expected to do so in the future;
we have historically presented Greens Creek and Lucky Friday as primary silver producers, based on the original analysis that justified putting the project into production, and the same analysis applies to Keno Hill. Further we believe that consistency in disclosure is important to our investors regardless of the relationships of metals prices and production from year to year;
metallurgical treatment maximizes silver recovery;
the Greens Creek, Lucky Friday and Keno Hill deposits are massive sulfide deposits containing an unusually high proportion of silver; and
in most of their working areas, Greens Creek, Lucky Friday and Keno Hill utilize selective mining methods in which silver is the metal targeted for highest recovery.
Accordingly, we believe the identification of gold, lead, zinc and copper as by-product credits at Greens Creek, Lucky Friday and Keno Hill is appropriate because of their lower economic value compared to silver and due to the fact that silver is the primary product we intend to produce at those locations. In addition, we have not consistently received sufficient revenue from any single by-product metal to warrant classification of such as a co-product.
We periodically review our revenues to ensure that reporting of primary products and by-products is appropriate. Because for Greens Creek, Lucky Friday and Keno Hill we consider zinc, lead, gold and copper to be by-products of our silver production, the values of these metals offset operating costs within our calculations of Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce. We currently do not report Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce for our Keno Hill operation as it is in the production ramp-up phase and has not met our definition of commercial production. We define an operation as being in commercial production upon achievement of the following criteria:
Completion of operational commissioning of each major mine and mill component;
Demonstrated ability to mine and mill consistently and without significant interruption, defined as 75% of historical production levels or mill design capacity over a period of 90 days;
Silver recoveries are at or near expected steady-state production levels;
All major capital expenditures have been completed; and
A significant portion of available funding is directed towards operating activities.
Currently we meet only one of the above criteria - silver recoveries are at expected steady-state production levels. Determination of when these criteria have been met requires the use of judgment, and our definition of commercial production may differ from that of other mining companies.
As Keno Hill has not yet been determined to be in commercial production, its costs and by-product credits are excluded from our consolidated Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce because (i) by definition it has not reached the sustaining stage and (ii) including its costs and by-product credits we believe would distort consolidated Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce of our operating silver mines that are in commercial production and operating as designed, and would not facilitate a meaningful comparison of our performance versus that of our peers who do not report such metrics for mines that are not in commercial production.
We believe the identification of silver as a by-product credit is appropriate at Casa Berardi because of its lower economic value compared to gold and due to the fact that gold is the primary product we produce there. In addition, we do not receive sufficient revenue from silver at the Casa Berardi mine to warrant classification of such as a co-product. Because we consider silver to be a by-product of our gold production at Casa Berardi, the value of silver offsets operating costs within our calculations of Cash Cost, After By-product Credits, per Gold Ounce and AISC, After By-product Credits, per Gold Ounce.
We reported net income applicable to common stockholders of $57.6 million for the three months ended June 30, 2025, compared to a net income applicable to common stockholders of $27.7 million in the comparable period in 2024. The following were the significant drivers of the change:
Consolidated gross profit increased by $68.1 million. See The Greens Creek Segment, The Lucky Friday Segment, The Keno Hill Segment, and The Casa Berardi Segment sections below for a discussion on the key drivers by operation.
General and administrative expenses decreased by $2.2 million due to the prior period containing compensation costs associated with the former CEO's retirement.
Ramp-up and suspension costs decreased by $1.4 million due to the current period containing no ramp-up costs for Keno Hill, as the site recorded gross profit, whereas in the prior period total cost of sales in excess of sales by $1.8 million were transferred to ramp-up and suspension costs.
Fair value adjustments, net increased by $4.6 million primarily due to $4.9 million in unrealized gains on our marketable equity securities portfolio and gains on undesignated derivative contracts of $4.7 million in the current period.
The positive movements mentioned above were partly offset by:
Other operating expense (income), net increased by $16.7 million primarily due to the prior period containing $17.8 million of insurance proceeds received related to the Lucky Friday fire.
Exploration and pre-development expense increased by $2.1 million in the current period with exploration activity primarily related to Keno Hill, Greens Creek and the Nevada properties.
Net foreign exchange loss increased by $6.2 million to a loss of $3.5 million, compared to a gain of $2.7 million in the comparable period as the US dollar weakened against the Canadian dollar.
Income and mining tax expense increased by $23.5 million due to higher taxable income generated by our US tax group.
We reported net income applicable to common stockholders of $86.3 million for the six months ended June 30, 2025, compared to a net income applicable to common stockholders of $21.8 million in the comparable period in 2024. The following were the significant drivers of the change:
Consolidated gross profit increased by $122.9 million. See The Greens Creek Segment, The Lucky Friday Segment, The Keno Hill Segment, and The Casa Berardi Segment sections below for a discussion on the key drivers by operating unit.
Ramp-up and suspension costs decreased by $12.6 million due to the current period containing no ramp-up costs for Keno Hill, as the site recorded gross profit, whereas in the prior period total cost of sales in excess of sales by $10.4 million were transferred to ramp-up and suspension costs. In addition, the prior period included $2.2 million of suspension costs related to the temporary suspension of operations at Lucky Friday due to the underground fire prior to the restart of operations on January 8, 2024.
Interest expense decreased by $2.5 million due to lower draws on the revolving credit facility during the current year.
Fair value adjustments, net increased by $10.1 million primarily due to $8.5 million in unrealized gains on our marketable equity securities portfolio and $4.7 million of gains on undesignated derivative contracts in the current period.
The positive movements mentioned above were partly offset by:
Other operating (income) expense, net increased by $34.7 million primarily due to the prior period containing $35.2 million of insurance proceeds received related to the Lucky Friday fire.
Net foreign exchange loss increased by $10.5 million, to a loss of $3.9 million compared to a gain of $6.7 million in the comparable period, driven by a weakening of the US dollar against the Canadian dollar during the current year.
Income and mining tax expense increased by $37.8 million due to higher taxable income generated by our US tax group.
Greens Creek
| Dollars are in thousands (except per ounce and per ton amounts) | Three Months EndedJune 30, | Six Months EndedJune 30, | ||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| Sales | $122,002 | $95,659 | $240,145 | $192,969 |
| Cost of sales and other direct production costs | (46,024) | (45,470) | (102,073) | (100,884) |
| Depreciation, depletion and amortization | (12,897) | (11,316) | (26,486) | (25,759) |
| Total cost of sales | (58,921) | (56,786) | (128,559) | (126,643) |
| Gross profit | $63,081 | $38,873 | $111,586 | $66,326 |
| Tons of ore milled | 230,221 | 225,746 | 443,120 | 457,934 |
| Production: | ||||
| Silver (ounces) | 2,422,978 | 2,243,551 | 4,425,538 | 4,722,145 |
| Gold (ounces) | 17,750 | 14,137 | 31,509 | 28,725 |
| Lead (tons) | 4,931 | 4,513 | 9,427 | 9,347 |
| Zinc (tons) | 14,024 | 12,400 | 26,859 | 25,462 |
| Copper (tons) | 499 | 462 | 910 | 957 |
| Payable metal quantities sold: | ||||
| Silver (ounces) | 1,591,745 | 1,576,918 | 3,336,397 | 3,667,367 |
| Gold (ounces) | 11,634 | 10,312 | 22,112 | 22,498 |
| Lead (tons) | 2,862 | 2,890 | 6,183 | 6,560 |
| Zinc (tons) | 9,039 | 7,525 | 18,546 | 17,089 |
| Copper (tons) | 108 | — | 152 | — |
| Ore grades: | ||||
| Silver ounces per ton | 13.4 | 12.6 | 12.6 | 13.0 |
| Gold ounces per ton | 0.10 | 0.09 | 0.10 | 0.09 |
| Lead percent | 2.6% | 2.5% | 2.6% | 2.5% |
| Zinc percent | 6.9% | 6.2% | 6.8% | 6.2% |
| Copper percent | 0.3% | 0.3% | 0.3% | 0.3% |
| Total production cost per ton | $225.71 | $218.09 | $232.57 | $215.46 |
| Cash Cost, After By-product Credits, per Silver Ounce (1) | $(11.91) | $0.19 | $(8.37) | $1.90 |
| AISC, After By-Product Credits, per Silver Ounce (1) | $(8.19) | $5.40 | $(4.50) | $6.33 |
| Capital additions | $8,397 | $11,704 | $19,156 | $20,531 |
(1)
A reconciliation of these non-GAAP measures to total cost of sales, the most comparable GAAP measure, can be found below in Reconciliation of Total Cost of Sales (GAAP) to Cash Cost, Before By-product Credits and Cash Cost, After By-product Credits (non-GAAP) and All-In Sustaining Cost, Before By-product Credits and All-In Sustaining Cost, After By-product Credits (non-GAAP).
The $24.2 million increase in gross profit for the three months ended June 30, 2025, compared to the same period in 2024 was primarily due to higher realized sales prices for silver and gold, in addition to higher sales volumes for all metals, except lead.
Capital additions in the current quarter were $3.3 million lower than the prior year period and included $2.8 million for primary ore access development, $2.0 million for mine development and $1.8 million for mining equipment and related costs.
Production of all metals increased during the three months ended June 30, 2025, primarily due to a combination of higher tons milled and higher grades.
The $45.3 million increase in gross profit for the six months ended June 30, 2025, compared to the same period in 2024 was primarily due to higher realized sales prices for silver, gold and lead, partially offset by lower metals sales volumes for all metals, except zinc.
Capital additions during the year were $1.4 million lower than the prior year period and included $6.0 million for primary ore access development, $3.4 million for mine development, $2.8 million for mining equipment and $1.7 million for definition drilling.
Silver production during the six months ended June 30, 2025, declined primarily due to a combination of lower tons milled reflecting a combination of lower heading availability, long hole mining and lower grade ore during the first quarter of 2025 which outweighed an improvement in silver production during the second quarter of 2025. Production of gold, lead and zinc are higher during the current year primarily due to higher grades.
The charts below illustrate the factors contributing to Cash Cost, After By-product Credits, per Silver Ounce for Greens Creek:
| Three Months Ended June 30, | Six Months Ended June 30, | |||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| Cash Cost, Before By-product Credits, per Silver Ounce | $22.42 | $25.83 | $25.15 | $25.46 |
| By-product credits | (34.33) | (25.64) | (33.52) | (23.56) |
| Cash Cost, After By-product Credits, per Silver Ounce | $(11.91) | $0.19 | $(8.37) | $1.90 |
| Three Months Ended June 30, | Six Months Ended June 30, | |||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| AISC, Before By-product Credits, per Silver Ounce | $26.14 | $31.04 | $29.02 | $29.89 |
| By-product credits | (34.33) | (25.64) | (33.52) | (23.56) |
| AISC, After By-product Credits, per Silver Ounce | $(8.19) | $5.40 | $(4.50) | $6.33 |
For the three months ended June 30, 2025, the decrease in Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce was primarily due to an increase in gold by-product credits, reflecting higher realized gold prices and higher silver production.
For the six months ended June 30, 2025, the decrease in Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce was primarily due to an increase in gold by-product credits, reflecting higher realized gold prices, partly offset by lower silver production. AISC, After By-product Credits, per Silver Ounce also benefited from lower sustaining capital expenditures.
Lucky Friday
| Dollars are in thousands (except per ounce and per ton amounts) | Three Months EndedJune 30, | Six Months EndedJune 30, | ||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| Sales | $64,273 | $59,071 | $127,467 | $94,411 |
| Cost of sales and other direct production costs | (29,011) | (26,815) | (59,635) | (46,423) |
| Depreciation, depletion and amortization | (13,275) | (10,708) | (26,700) | (18,619) |
| Total cost of sales | (42,286) | (37,523) | (86,335) | (65,042) |
| Gross profit | $21,987 | $21,548 | $41,132 | $29,369 |
| Tons of ore milled | 114,475 | 107,441 | 223,220 | 193,675 |
| Production: | ||||
| Silver (ounces) | 1,340,877 | 1,308,155 | 2,673,129 | 2,369,220 |
| Lead (tons) | 8,829 | 8,229 | 17,309 | 14,918 |
| Zinc (tons) | 3,911 | 3,320 | 7,592 | 6,171 |
| Payable metal quantities sold: | ||||
| Silver (ounces) | 1,228,493 | 1,220,850 | 2,497,338 | 2,174,741 |
| Lead (tons) | 8,027 | 7,599 | 16,005 | 13,591 |
| Zinc (tons) | 2,887 | 2,919 | 5,968 | 4,560 |
| Ore grades: | ||||
| Silver ounces per ton | 12.5 | 12.9 | 12.7 | 12.9 |
| Lead percent | 8.2% | 8.1% | 8.2% | 8.2% |
| Zinc percent | 4.2% | 3.6% | 4.1% | 3.7% |
| Total production cost per ton | $241.63 | $233.99 | $249.89 | $233.59 |
| Cash Cost, After By-product Credits, per Silver Ounce (1) | $6.19 | $5.32 | $7.77 | $6.67 |
| AISC, After By-product Credits, per Silver Ounce (1) | $19.07 | $12.74 | $19.57 | $14.50 |
| Capital additions | 15,942 | $10,818 | $31,388 | $25,806 |
(1)
A reconciliation of these non-GAAP measures to total cost of sales, the most comparable GAAP measure, can be found below in Reconciliation of Total Cost of Sales (GAAP) to Cash Cost, Before By-product Credits and Cash Cost, After By-product Credits (non-GAAP) and All-In Sustaining Cost, Before By-product Credits and All-In Sustaining Cost, After By-product Credits (non-GAAP).
Gross profit increased by $0.4 million for the three months ended June 30, 2025 compared to the comparable period in 2024, reflecting a combination of higher sales volumes for all metals due to higher milled tons. Higher realized prices for silver and zinc also positively contributed to the higher gross profit, however this benefit was partly offset by higher contractor, consumables and maintenance costs reflecting the higher volumes produced and sold, and higher profit sharing costs under the collective bargaining agreement.
Gross profit increased by $11.8 million for the six months ended June 30, 2025 compared to the comparable period in 2024, reflecting a combination of higher sales volumes for all metals due to a full six months of production in 2025, compared to 2024 when operations did not resume until January 9, 2024, following suspension of operations in August 2023, due to the underground fire in the secondary egress. Higher realized prices for silver and zinc also positively contributed to the higher gross profit, however this benefit was partly offset by lower realized lead prices and higher contractor, drilling, consumables and maintenance costs reflecting the higher volumes produced and sold, and higher profit sharing costs under the collective bargaining agreement.
Capital additions increased by $5.1 million for the three months ended June 30, 2025, compared to the comparable period in 2024. Significant capital expenditures in 2025 included capital development of $6.4 million, the surface cooling project of $5.4 million, pond 5 construction of $1.3 million and definition drilling of $1.9 million.
Capital additions increased by $5.6 million for the six months ended June 30, 2025 and included $12.5 million for capital development, $6.4 million for the surface cooling project, $3.8 million for definition drilling, $1.8 million for shaft renovations and $1.7 million for pond 5 construction.
The charts below illustrate the factors contributing to Cash Cost, After By-product Credits, Per Silver Ounce for Lucky Friday:
| Three Months Ended June 30, | Six Months Ended June 30, | |||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| Cash Cost, Before By-product Credits, per Silver Ounce | $22.47 | $22.27 | $23.79 | $23.08 |
| By-product credits | (16.28) | (16.95) | (16.02) | (16.41) |
| Cash Cost, After By-product Credits, per Silver Ounce | $6.19 | $5.32 | $7.77 | $6.67 |
| Three Months Ended June 30, | Six Months Ended June 30, | |||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| AISC, Before By-product Credits, per Silver Ounce | $35.35 | $29.69 | $35.59 | $30.91 |
| By-product credits | (16.28) | (16.95) | (16.02) | (16.41) |
| AISC, After By-product Credits, per Silver Ounce | $19.07 | $12.74 | $19.57 | $14.50 |
The increase in Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce for the three months ended June 30, 2025, compared to the same period in 2024 was primarily due to higher production costs, partly offset by higher silver production. AISC, After By-product Credits, per Silver Ounce was also negatively impacted by higher sustaining capital.
The increase in Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce for the six months ended June 30, 2025, compared to the same period in 2024 was primarily due to higher production costs, partly offset by higher silver production reflecting a full quarter's production compared to operations only commencing on January 9, 2024 following suspension in August 2023 due to the underground fire in the secondary egress. AISC, After By-product Credits, per Silver Ounce was also negatively impacted by higher sustaining capital.
Keno Hill
| Dollars are in thousands (except per ounce and per ton amounts) | Three Months EndedJune 30, | Six Months EndedJune 30, | ||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| Sales | $26,121 | $28,950 | $43,030 | $39,797 |
| Cost of sales and other direct production costs | (20,740) | (24,221) | (33,809) | (31,466) |
| Depreciation, depletion and amortization | (5,141) | (4,729) | (7,943) | (8,331) |
| Total cost of sales | (25,881) | (28,950) | (41,752) | (39,797) |
| Gross profit | $240 | $— | $1,278 | $— |
| Tons of ore milled | 26,771 | 36,977 | 54,182 | 62,142 |
| Production: | ||||
| Silver (ounces) | 750,712 | 900,440 | 1,523,142 | 1,546,752 |
| Lead (tons) | 890 | 845 | 1,921 | 1,421 |
| Zinc (tons) | 544 | 471 | 963 | 769 |
| Payable metal quantities sold: | ||||
| Silver (ounces) | 697,475 | 979,543 | 1,196,727 | 1,411,874 |
| Lead (tons) | 775 | 849 | 1,466 | 1,208 |
| Zinc (tons) (1) | 407 | 337 | 666 | 453 |
| Ore grades: | ||||
| Silver ounces per ton | 28.9 | 25.1 | 29.0 | 25.6 |
| Lead percent | 3.5% | 2.4% | 3.7% | 2.4% |
| Zinc percent | 2.3% | 1.4% | 2.1% | 1.4% |
| Capital additions | $17,045 | $14,533 | $27,481 | $24,879 |
(1)
Zinc tons sold include intersegment sales to Greens Creek.
We have not disclosed cost per ounce statistics for the Keno Hill operation as it is in the production ramp-up phase and has not met our definition of commercial production. See above "Consolidated Results of Operations" for our definition of commercial production. Determination of when those criteria have been met requires the use of judgment, and our definition of commercial production may differ from that of other mining companies.
We acquired our Keno Hill operations as part of the Alexco Resource Corp. acquisition in September 2022 and have focused on development activities and began ramp-up of the mill during the second quarter of 2023. The average mill throughput during the six months ended June 30, 2025, was 299 tons per day (the mine is currently permitted to a maximum of an average of 440 tons per day), with silver grades milled of 29.0 ounces per ton. During the first quarter of the year, the mill relied on the existing ore stockpiles as the mine continues to focus on development and ramp up to higher tonnage rates with mining rates of 263 tons per day during the first six months ended June 30, 2025, with material sourced from both the Bermingham and Flame and Moth deposits. Mill throughput, while currently steady, has been negatively impacted by last year's events as described below.
During the three months ended June 30, 2025 and 2024, Keno Hill recorded sales of $26.1 million and $29.0 million, respectively, with the decrease due to lower metals sales volumes, partly offset by higher realized prices. As a result of higher metals prices, Keno Hill generated a gross profit of $0.2 million during the three months ended June 30, 2025, and did not transfer any total cost of sales to ramp-up and suspension costs. During the second quarter of 2024, total cost of sales in excess of sales of $1.8 million were reclassified to ramp-up and suspension costs in the Condensed Consolidated Statements of Operations and Comprehensive Income, (Unaudited). During the quarter, Keno Hill recorded capital additions of $17.0 million, related to mine development and other mining equipment purchases.
During the six months ended June 30, 2025 and 2024, Keno Hill recorded sales of $43.0 million and $39.8 million, respectively, with the increase in sales attributable to higher realized sales prices, partly offset by lower volumes sold. As a result of higher revenues, Keno Hill generated a gross profit of $1.3 million during the six months ended June 30, 2025, and did not transfer any total cost of sales to ramp-up and suspension costs. During the six months ended June 30, 2024, total cost of sales in excess of sales of $10.4 million were reclassified to ramp-up and suspension costs in the Condensed Consolidated Statements of Operations and Comprehensive Income, (Unaudited). During the six months ended June 30, 2025, Keno Hill recorded capital additions of $27.5 million, primarily related to mine development and the Bermingham backfill plant.
From commencement of production until late August, 2024, ore production and mill throughput generally increased as planned, leading to increased levels of production (though still not reaching the permitted capacity at the mill). However, starting in mid-2024 and continuing today, Keno Hill has been impacted by external events which have affected permitting, projects and production, and delayed our ability to reach sustained, profitable production. In late June 2024, an unrelated, third party, Victoria Gold, experienced a heap leach failure at its Eagle Mine which is located near Keno Hill. This incident had several immediate and ongoing impacts on our operations. The primary impact was we were forced to suspend milling operations at Keno Hill between August 27 and October 26 due to delays in receiving authorizations and permits because the focus of the Yukon Government (“YG”) and the First Nation of Na-Cho Nyäk Dun (“FNNND”) was on the Eagle Mine incident response and not on routine permitting matters. Mill operations and design and construction projects resumed during the fourth quarter of 2024. Our original planned schedule for permitting and projects has been extended, but we are taking steps, including working with regulators, to establish a viable schedule for our operational plans.
An ongoing impact of the Eagle Mine incident is the FNNND's public position on mining, which has evolved from a call to halt all mining activity to support of environmentally responsible mining practices. We continue to strengthen our partnership with the FNNND - which is important because Keno Hill is within their Traditional Territory - through enhanced environmental stewardship and community engagement initiatives, building on their support for responsible mining practices.
Then, starting in late October 2024, Keno Hill began experiencing power curtailments when Yukon Energy experienced a turbine failure at its hydroelectric plant in Whitehorse. That failure and Yukon Energy’s resulting focus on line maintenance, combined with cold temperatures in the Yukon (and the resulting increase in demand for power), caused Yukon Energy to reduce power to Keno Hill, resulting in the operation’s inability to fully power the mine and mill on several occasions in late 2024 and for 8 days in the first quarter of 2025. Temporary power constraints in the Yukon region impacted approximately 130,000 ounces of silver production and labor costs for idled employees of approximately $0.5 million through June 30, 2025. These conditions improved in the second quarter of 2025 when we experienced no power disruptions by Yukon Energy, nor do we expect any disruptions while the weather remains warm, except that we expect a 6-day outage in August 2025 when the turbine at Yukon Energy's hydroelectric plant in Whitehorse is scheduled to be fixed. There can be no assurance that Keno Hill will not face power supply constraints in the future.
Permitting is one of the most important factors in our ability to reach sustainable, profitable production at Keno Hill. Increased production means a need for increased tailings storage, waste storage, water treatment, camp space and reliable power, all of which are typical requirements for mining companies in the expansion phase. These projects require new or modified permits, as well as the capital to implement them. Although we continue to make progress on these normal-course permitting matters, we have yet to make up for the delays described above. We also continue to face operational challenges such as work force availability, dilution, execution of projects, limited camp space, and the ramp-up of the Company's environmental remediation services group activities in the summer (which adds incremental demand on Keno Hill's infrastructure and resources, most notably camp space). As a result, we continue to project 2025 silver production to be comparable to 2024 levels. The projected flat production levels at Keno Hill for 2025 should allow us to focus on (i) permitting, (ii) stakeholder outreach and ensuring we have local support, (iii) projects such as tailings storage expansion and the construction of a cemented tails batch plant, (iv) mine development and (v) meeting the above-mentioned operational challenges.
As stated above, Keno Hill has generated marginal profits for us at current throughput rates and prices. Our immediate focus is to advance permits and successfully execute infrastructure projects, with the goal of putting the mine on a path toward achieving its current permitted capacity of 440 tons per day which, at current prices, we project would generate positive free cash flow, while preserving expansion optionality beyond 440 tons per day. To reach 440 tons per day throughput, we would need to continue to mine ore from both the Bermingham deposit and the lower grade Flame & Moth deposit. Currently Keno Hill is not configured to sustainably produce 440 tons per day (although the mill has achieved that rate for multiple weeks on end during test run periods). Achieving 440 or higher tons per day would require targeted infrastructure investments, obtaining permits, executing projects, mine development and maintaining community support. If any one of these were not to occur, or if prices were to decrease from current prices, Keno Hill as currently configured would not be profitable, and placing the operation on care and maintenance would be an option. See Item 1A. Risk Factors - We may not realize all of the anticipated benefits from our acquisitions, including our 2022 acquisition of Alexco in our 2024 Form 10-K.
Casa Berardi
| Dollars are in thousands (except per ounce and per ton amounts) | Three Months EndedJune 30, | Six Months EndedJune 30, | ||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| Sales | $85,035 | $58,623 | $141,040 | $100,207 |
| Cost of sales and other direct production costs | (44,944) | (40,330) | (87,057) | (75,639) |
| Depreciation, depletion and amortization | (5,846) | (27,010) | (14,415) | (49,961) |
| Total cost of sales | (50,790) | (67,340) | (101,472) | (125,600) |
| Gross profit (loss) | $34,245 | $(8,717) | $39,568 | $(25,393) |
| Tons of ore milled | 393,648 | 366,979 | 784,816 | 748,605 |
| Production: | ||||
| Gold (ounces) | 28,145 | 23,187 | 48,618 | 45,191 |
| Silver (ounces) | 5,943 | 6,338 | 11,095 | 12,465 |
| Payable metal quantities sold: | ||||
| Gold (ounces) | 25,699 | 24,964 | 44,876 | 44,967 |
| Silver (ounces) | 5,262 | 7,974 | 10,483 | 13,187 |
| Ore grades: | ||||
| Gold ounces per ton | 0.08 | 0.07 | 0.07 | 0.07 |
| Silver ounces per ton | 0.02 | 0.02 | 0.02 | 0.02 |
| Total production cost per ton | $113.19 | $107.84 | $114.19 | $102.07 |
| Cash Cost, After By-product Credits, per Gold Ounce (1) | $1,578 | $1,701 | $1,837 | $1,685 |
| AISC, After By-product Credits, per Gold Ounce (1) | $1,669 | $1,825 | $1,935 | $1,861 |
| Capital additions | $15,367 | $12,376 | $31,624 | $25,692 |
(1)
A reconciliation of these non-GAAP measures to total cost of sales, the most comparable GAAP measure, can be found below in Reconciliation of Total Cost of Sales (GAAP) to Cash Cost, Before By-product Credits and Cash Cost, After By-product Credits (non-GAAP) and All-In Sustaining Cost, Before By-product Credits and All-In Sustaining Cost, After By-product Credits (non-GAAP).
Casa Berardi is advancing toward a more streamlined and efficient surface-only operation. The plan was to focus exclusively on the 160 pit by mid-2025, however following the significant increase in the gold price during the year to date, it was decided to continue to mine the easily accessible ore in the west underground mine, potentially through the end of 2025. This transition follows the continued successful extraction of higher-margin stopes from the west underground mine, positioning the mine for continued productivity and cost-effective mining. Our previously announced strategic review is ongoing and includes evaluating the following scenarios (i) sale of the asset, (ii) joint venturing the asset, (iii) spin-out of the asset, (iv) extending the underground mine, and (iv) accelerating future cash flows to capture part of the current record gold prices via a prepayment structure or other financing arrangement. If underground mining is not extended, Casa Berardi is expected to only produce gold from the 160 open pit, and at lower volumes than historic production levels, with production expected to conclude at the 160 open pit in 2027. Casa Berardi is transitioning to a new phase focused on developing the Principal and West Mine Crown Pillar open pits. This strategic repositioning is expected to optimize long-term value, with production anticipated to resume following successful permitting and development during a production gap expected between 2027 and 2032. Upon successful completion of permitting, design, and construction of the new open pits (which is not assured), we expect Casa Berardi to generate substantial free cash flow at current gold prices when production resumes. This long-term approach aligns with our commitment to maximizing the value of our assets through strategic mine planning and operational flexibility.
Gross profit increased by $43.0 million to $34.2 million for the three months ended June 30, 2025, compared to a gross loss of $8.7 million in the comparable period in 2024. The increase in gross profit is primarily related to higher realized prices and gold ounces sold, partly offset by higher contractor costs. The prior period gross loss also included higher depreciation expense related to accelerated depreciation of the west underground mine. Capital additions increased by $3.0 million to $15.4 million during the quarter, compared to the same period in 2024, and primarily related to a tailings dam raise.
Gross profit increased by $65.0 million to $39.6 million for the six months ended June 30, 2025, compared to a gross loss of $25.4 million in the comparable period in 2024. The increase in gross profit is primarily related to higher realized prices and gold ounces sold, partly offset by higher contractor costs. The prior period gross loss also included higher depreciation expense related to accelerated depreciation of the west underground mine and a product inventory net realizable value write down of $6.3 million. Capital additions increased by $5.9 million to $31.6 million during the year, compared to the same period in 2024, and primarily related to a tailings dam raise.
Although Casa Berardi generated gross profits during the last four quarters and free cash flow during the current quarter, it reported gross losses during the prior three fiscal years. This lack of profitability and free cash flow generation, the expected hiatus in future production discussed above, the uncertainty surrounding permitting and pit design and construction, and the time involved to resolve these uncertainties, has caused us to undertake a review of how Casa Berardi fits into the Company's future strategy. While it is possible we may continue down the path towards future production at the Principal and West Mine Crown Pillar pits, we are also examining potential strategic alternatives as described above.
The charts below illustrate the factors contributing to Cash Cost, After By-product Credits, Per Gold Ounce for Casa Berardi:
| Three Months Ended June 30, | Six Months Ended June 30, | |||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| Cash Cost, Before By-product Credits, per Gold Ounce | $1,585 | $1,709 | $1,845 | $1,692 |
| By-product credits | (7) | (8) | (8) | (7) |
| Cash Cost, After By-product Credits, per Gold Ounce | $1,578 | $1,701 | $1,837 | $1,685 |
| Three Months Ended June 30, | Six Months Ended June 30, | |||
|---|---|---|---|---|
| 2025 | 2024 | 2025 | 2024 | |
| AISC, Before By-product Credits, per Gold Ounce | $1,676 | $1,833 | $1,943 | $1,868 |
| By-product credits | (7) | (8) | (8) | (7) |
| AISC, After By-product Credits, per Gold Ounce | $1,669 | $1,825 | $1,935 | $1,861 |
The decrease in Cash Cost After By-product Credits, per Gold Ounce, and AISC, After By-product Credits, per Gold Ounce for the three months ended June 30, 2025, compared to the same period in 2024 was primarily due to higher gold production.
The increase in Cash Cost After By-product Credits, per Gold Ounce, and AISC, After By-product Credits, per Gold Ounce for the three and six months ended June 30, 2025, compared to the same period in 2024 was primarily due to higher production costs, partly offset by higher gold production. AISC, After By-product Credits, per Gold Ounce benefited from lower sustaining capital over the comparable period in 2024.
Corporate Matters
Income Taxes
During the three and six months ended June 30, 2025, an income and mining tax provision of $32.6 million and $48.7 million, resulted in an effective tax rate of 36.1% and 36.0%, respectively. This compares to an income and mining tax provision of $9.1 million and $10.9 million, which resulted in an effective tax rate of 24.6% and 33.0%, respectively, for the three and six months ended June 30, 2024. The comparability of our income and mining tax provision and effective tax rate for the reported periods was impacted by multiple factors, primarily: (i) mining taxes; (ii) variations in our income before income taxes; (iii) geographic distribution of that income; (iv) foreign exchange rates including non-recognition of foreign exchange gains and losses; (v) percentage depletion; and (vi) the non-recognition of tax assets. The effective tax rate will fluctuate, sometimes significantly, period to period. The change in the effective tax rate during the three and six months ended June 30, 2025, compared to the comparable periods in 2024 is primarily related to the reported consolidated income (loss) as well as the losses incurred at our consolidated Alexco subsidiaries, and our Nevada subsidiaries, for which no tax benefit is recognized due to uncertainty surrounding our ability to utilize these future tax benefits.
Each reporting period we assess our deferred tax balances based on a review of long-range forecasts and quarterly activity. A valuation allowance is provided for deferred tax assets for which it is more likely than not the related tax benefits will not be realized. We analyze our deferred tax assets and, if it is determined that we will not realize all or a portion of our deferred tax assets, we record or increase a valuation allowance. Conversely, if it is determined we will ultimately more likely than not be able to realize all or a portion of the related benefits for which a valuation allowance has been provided, all or a portion of the related valuation allowance will be reduced. There are a number of factors that impact our ability to realize our deferred tax assets. Valuation allowances are provided on deferred tax assets in Nevada, Mexico, and certain Canadian jurisdictions. For additional information, please see risk factors Our accounting and other estimates may be imprecise and Our ability to recognize the benefits of deferred tax assets related to net operating loss carryforwards and other items is dependent on future cash flows generating taxable incomein Item 1A - Risk Factors in our 2024 Form 10-K.
Reconciliation of Total Cost of Sales to Cash Cost, Before By-product Credits and Cash Cost, After By-product Credits (non-GAAP) and All-In Sustaining Cost, Before By-product Credits and All-In Sustaining Cost, After By-product Credits (non-GAAP)
The tables below present reconciliations between the most comparable GAAP measure of total cost of sales to the non-GAAP measures of (i) Cash Cost, Before By-product Credits, (ii) Cash Cost, After By-product Credits, (iii) AISC, Before By-product Credits and (iv) AISC, After By-product Credits for our operations and for the Company for the three and six months ended June 30, 2025 and 2024.
Cash Cost, After By-product Credits, per Ounce and AISC, After By-product Credits, per Ounce are measures developed by precious metals companies (including the Silver Institute and the World Gold Council) in an effort to provide a uniform standard for comparison purposes. There can be no assurance, however, that these non-GAAP measures as we report them are the same as those reported by other mining companies.
Cash Cost, After By-product Credits, per Ounce is an important operating statistic that we utilize to measure each mine's operating performance. We use AISC, After By-product Credits, per Ounce as a measure of our mines' net cash flow after costs for reclamation and sustaining capital. This is similar to the Cash Cost, After By-product Credits, per Ounce non-GAAP measure we report, but also includes reclamation and sustaining capital costs. Current GAAP measures used in the mining industry, such as cost of goods sold, do not capture all the expenditures incurred to discover, develop and sustain silver and gold production. Cash Cost, After By-product Credits, per Ounce and AISC, After By-product Credits, per Ounce also allow us to benchmark the performance of each of our mines versus those of our competitors. As a silver and gold mining company, we also use these statistics on an aggregate basis - aggregating the Greens Creek and Lucky Friday mines to compare our performance with that of other silver mining companies. Similarly, these statistics are useful in identifying acquisition and investment opportunities as they provide a common tool for measuring the financial performance of other mines with varying geologic, metallurgical and operating characteristics.
We have not disclosed cost per ounce statistics for the Keno Hill operation as it is in the production ramp-up phase and has not met our definition of commercial production. See above "Consolidated Results of Operations" for our definition of commercial production. Determination of when those criteria have been met requires the use of judgment, and our definition of commercial production may differ from that of other mining companies.
Cash Cost, Before By-product Credits and AISC, Before By-product Credits include all direct and indirect operating cash costs related directly to the physical activities of producing metals, including mining, processing and other plant costs, third-party refining expense, on-site general and administrative costs, royalties and mining production taxes. AISC, Before By-product Credits for each mine also includes reclamation and sustaining capital costs. AISC, Before By-product Credits for our consolidated silver properties also includes corporate costs for general and administrative expense and sustaining capital costs. By-product credits include revenues earned from all metals other than the primary metal produced at each unit. As depicted in the tables below, by-product credits comprise an essential element of our silver unit cost structure, distinguishing our silver operations due to the polymetallic nature of their orebodies.
In addition to the uses described above, Cash Cost, After By-product Credits, per Ounce and AISC, After By-product Credits, per Ounce provide management and investors an indication of operating cash flow, after consideration of the average price received from production. We also use these measurements for the comparative monitoring of performance of our mining operations period-to-period from a cash flow perspective. We currently do not report Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce for our Keno Hill operation as it is in the ramp-up phase of production and accordingly it is excluded from our consolidated Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce.
Casa Berardi reports Cash Cost, After By-product Credits, per Gold Ounce and AISC, After By-product Credits, per Gold Ounce for the production of gold, their primary product, and by-product revenues earned from silver, which is a by-product at Casa Berardi. Only costs and ounces produced relating to units with the same primary product are combined to represent Cash Cost, After By-product Credits, per Ounce and AISC, After By-product Credits, per Ounce. Thus, the gold produced at Casa Berardi is not included as a by-product credit when calculating Cash Cost, After By-product Credits, per Silver Ounce and AISC, After By-product Credits, per Silver Ounce for the total of Greens Creek and Lucky Friday, our combined silver properties. Similarly, the silver produced at our other three units is not included as a by-product credit when calculating the gold metrics for Casa Berardi.
| In thousands (except per ounce amounts) | Three Months Ended June 30, 2025 | |||||
|---|---|---|---|---|---|---|
| Greens Creek · Lucky Friday · Keno Hill (5) · Corporate (2) · Total Silver | ||||||
| Total cost of sales | $58,921 | $42,286 | $25,881 | $— | $127,088 | |
| Depreciation, depletion and amortization | (12,897) | (13,275) | (5,141) | — | (31,313) | |
| Treatment costs | (1,001) | 1,054 | — | — | 53 | |
| Change in product inventory | 9,234 | 225 | — | — | 9,459 | |
| Reclamation and other costs | 57 | (160) | — | — | (103) | |
| Exclusion of Keno Hill cash costs (5) | — | — | (20,740) | — | (20,740) | |
| Cash Cost, Before By-product Credits (1) | 54,314 | 30,130 | — | — | 84,444 | |
| Reclamation and other costs | 757 | 195 | — | — | 952 | |
| Sustaining capital | 8,268 | 17,069 | — | 1,270 | 26,607 | |
| General and administrative | — | — | — | 12,540 | 12,540 | |
| AISC, Before By-product Credits (1) | 63,339 | 47,394 | — | 13,810 | 124,543 | |
| By-product credits: | ||||||
| Zinc | (23,512) | (7,120) | — | — | (30,632) | |
| Gold | (52,194) | — | — | — | (52,194) | |
| Lead | (6,610) | (14,708) | — | — | (21,318) | |
| Copper | (871) | — | — | — | (871) | |
| Total By-product credits | (83,187) | (21,828) | — | — | (105,015) | |
| Cash Cost, After By-product Credits | $(28,873) | $8,302 | $— | $— | $(20,571) | |
| AISC, After By-product Credits | $(19,848) | $25,566 | $— | $13,810 | $19,528 | |
| Ounces produced | 2,423 | 1,341 | 3,764 | |||
| Cash Cost, Before By-product Credits, per Ounce | $22.42 | $22.47 | $22.44 | |||
| By-product credits per ounce | (34.33) | (16.28) | (27.90) | |||
| Cash Cost, After By-product Credits, per Ounce | $(11.91) | $6.19 | $(5.46) | |||
| AISC, Before By-product Credits, per Ounce | $26.14 | $35.35 | $33.09 | |||
| By-product credits per ounce | (34.33) | (16.28) | (27.90) | |||
| AISC, After By-product Credits, per Ounce | $(8.19) | 19.07 | $5.19 | |||
| In thousands (except per ounce amounts) | Three Months Ended June 30, 2025 | |||
|---|---|---|---|---|
| Gold - Casa Berardi · Other (4) · Total Gold and Other | ||||
| Total cost of sales | $50,790 | $6,625 | $57,415 | |
| Depreciation, depletion and amortization | (5,846) | (5,846) | ||
| Treatment costs | 44 | — | 44 | |
| Change in product inventory | (62) | — | (62) | |
| Reclamation and other costs | (324) | — | (324) | |
| Exclusion of Other costs | — | (6,625) | (6,625) | |
| Cash Cost, Before By-product Credits (1) | 44,602 | — | 44,602 | |
| Reclamation and other costs | 324 | — | 324 | |
| Sustaining capital | 2,242 | — | 2,242 | |
| AISC, Before By-product Credits (1) | 47,168 | — | 47,168 | |
| By-product credits: | ||||
| Silver | (202) | — | (202) | |
| Total By-product credits | (202) | — | (202) | |
| Cash Cost, After By-product Credits | $44,400 | $— | $44,400 | |
| AISC, After By-product Credits | $46,966 | $— | $46,966 | |
| Divided by ounces produced | 28 | — | 28 | |
| Cash Cost, Before By-product Credits, per Ounce | $1,585 | $— | $1,585 | |
| By-product credits per ounce | (7) | — | (7) | |
| Cash Cost, After By-product Credits, per Ounce | $1,578 | $— | $1,578 | |
| AISC, Before By-product Credits, per Ounce | $1,676 | $— | $1,676 | |
| By-product credits per ounce | (7) | — | (7) | |
| AISC, After By-product Credits, per Ounce | $1,669 | $— | $1,669 | |
| In thousands (except per ounce amounts) | Three Months Ended June 30, 2025 | ||
|---|---|---|---|
| Total Silver | Total Gold and Other | Total | |
| Total cost of sales | $127,088 | $57,415 | $184,503 |
| Depreciation, depletion and amortization | (31,313) | (5,846) | (37,159) |
| Treatment costs | 53 | 44 | 97 |
| Change in product inventory | 9,459 | (62) | 9,397 |
| Reclamation and other costs | (103) | (324) | (427) |
| Exclusion of Keno Hill cash costs (5) | (20,740) | — | (20,740) |
| Exclusion of Other costs | — | (6,625) | (6,625) |
| Cash Cost, Before By-product Credits (1) | 84,444 | 44,602 | 129,046 |
| Reclamation and other costs | 952 | 324 | 1,276 |
| Sustaining capital | 26,607 | 2,242 | 28,849 |
| General and administrative | 12,540 | — | 12,540 |
| AISC, Before By-product Credits (1) | 124,543 | 47,168 | 171,711 |
| By-product credits: | |||
| Zinc | (30,632) | — | (30,632) |
| Gold | (52,194) | — | (52,194) |
| Lead | (21,318) | — | (21,318) |
| Silver | — | (202) | (202) |
| Copper | (871) | — | (871) |
| Total By-product credits | (105,015) | (202) | (105,217) |
| Cash Cost, After By-product Credits | $(20,571) | $44,400 | $23,829 |
| AISC, After By-product Credits | $19,528 | $46,966 | $66,494 |
| Divided by ounces produced | 3,764 | 28 | |
| Cash Cost, Before By-product Credits, per Ounce | $22.44 | $1,585 | |
| By-product credits per ounce | (27.90) | (7) | |
| Cash Cost, After By-product Credits, per Ounce | $(5.46) | $1,578 | |
| AISC, Before By-product Credits, per Ounce | $33.09 | $1,676 | |
| By-product credits per ounce | (27.90) | (7) | |
| AISC, After By-product Credits, per Ounce | $5.19 | $1,669 | |
| In thousands (except per ounce amounts) | Three Months Ended June 30, 2024 | |||||
|---|---|---|---|---|---|---|
| Greens Creek · Lucky Friday · Keno Hill (5) · Corporate (2) · Total Silver | ||||||
| Total cost of sales | $56,786 | $37,523 | $28,950 | $— | $123,259 | |
| Depreciation, depletion and amortization | (11,316) | (10,708) | (4,729) | — | (26,753) | |
| Treatment costs | 6,069 | 2,746 | — | — | 8,815 | |
| Change in product inventory | 7,296 | (115) | — | — | 7,181 | |
| Reclamation and other costs | (882) | (311) | — | — | (1,193) | |
| Exclusion of Keno Hill cash costs (5) | — | — | (24,221) | — | (24,221) | |
| Cash Cost, Before By-product Credits (1) | 57,953 | 29,135 | — | — | 87,088 | |
| Reclamation and other costs | 785 | 183 | — | — | 968 | |
| Sustaining capital | 10,911 | 9,517 | — | 1,035 | 21,463 | |
| General and administrative | — | — | — | 14,740 | 14,740 | |
| AISC, Before By-product Credits (1) | 69,649 | 38,835 | — | 15,775 | 124,259 | |
| By-product credits: | ||||||
| Zinc | (21,873) | (6,706) | — | — | (28,579) | |
| Gold | (28,844) | — | — | — | (28,844) | |
| Lead | (6,818) | (15,466) | — | — | (22,284) | |
| Total By-product credits | (57,535) | (22,172) | — | — | (79,707) | |
| Cash Cost, After By-product Credits | $418 | $6,963 | $— | $— | $7,381 | |
| AISC, After By-product Credits | $12,114 | $16,663 | $— | $15,775 | $44,552 | |
| Divided by ounces produced | 2,244 | 1,308 | 3,552 | |||
| Cash Cost, Before By-product Credits, per Ounce | $25.83 | $22.27 | $24.52 | |||
| By-product credits per ounce | (25.64) | (16.95) | (22.44) | |||
| Cash Cost, After By-product Credits, per Ounce | $0.19 | $5.32 | $2.08 | |||
| AISC, Before By-product Credits, per Ounce | $31.04 | $29.69 | $34.98 | |||
| By-product credits per ounce | (25.64) | (16.95) | (22.44) | |||
| AISC, After By-product Credits, per Ounce | $5.40 | $12.74 | $12.54 | |||
| In thousands (except per ounce amounts) | Three Months Ended June 30, 2024 | ||
|---|---|---|---|
| Gold - Casa Berardi | Other (4) | Total Gold and Other | |
| Total cost of sales | $67,340 | $3,628 | $70,968 |
| Depreciation, depletion and amortization | (27,010) | — | (27,010) |
| Treatment costs | 52 | — | 52 |
| Change in product inventory | (550) | — | (550) |
| Reclamation and other costs | (206) | — | (206) |
| Exclusion of Other costs | — | (3,628) | (3,628) |
| Cash Cost, Before By-product Credits (1) | 39,626 | — | 39,626 |
| Reclamation and other costs | 206 | — | 206 |
| Sustaining capital | 2,667 | — | 2,667 |
| AISC, Before By-product Credits (1) | 42,499 | — | 42,499 |
| By-product credits: | |||
| Silver | (183) | — | (183) |
| Total By-product credits | (183) | — | (183) |
| Cash Cost, After By-product Credits | $39,443 | $— | $39,443 |
| AISC, After By-product Credits | $42,316 | $— | $42,316 |
| Divided by ounces produced | 23 | — | 23 |
| Cash Cost, Before By-product Credits, per Ounce | $1,709 | $— | $1,709 |
| By-product credits per ounce | (8) | — | (8) |
| Cash Cost, After By-product Credits, per Ounce | $1,701 | $— | $1,701 |
| AISC, Before By-product Credits, per Ounce | $1,833 | $— | $1,833 |
| By-product credits per ounce | (8) | — | (8) |
| AISC, After By-product Credits, per Ounce | $1,825 | $— | $1,825 |
| In thousands (except per ounce amounts) | Three Months Ended June 30, 2024 | ||
|---|---|---|---|
| Total Silver | Total Gold and Other | Total | |
| Total cost of sales | $123,259 | $70,968 | $194,227 |
| Depreciation, depletion and amortization | (26,753) | (27,010) | (53,763) |
| Treatment costs | 8,815 | 52 | 8,867 |
| Change in product inventory | 7,181 | (550) | 6,631 |
| Reclamation and other costs | (1,193) | (206) | (1,399) |
| Exclusion of Other costs | — | (3,628) | (3,628) |
| Exclusion of Keno Hill cash costs (5) | (24,221) | — | (24,221) |
| Cash Cost, Before By-product Credits (1) | 87,088 | 39,626 | 126,714 |
| Reclamation and other costs | 968 | 206 | 1,174 |
| Sustaining capital | 21,463 | 2,667 | 24,130 |
| General and administrative | 14,740 | — | 14,740 |
| AISC, Before By-product Credits (1) | 124,259 | 42,499 | 166,758 |
| By-product credits: | |||
| Zinc | (28,579) | — | (28,579) |
| Gold | (28,844) | — | (28,844) |
| Lead | (22,284) | — | (22,284) |
| Silver | — | (183) | (183) |
| Total By-product credits | (79,707) | (183) | (79,890) |
| Cash Cost, After By-product Credits | $7,381 | $39,443 | $46,824 |
| AISC, After By-product Credits | $44,552 | $42,316 | $86,868 |
| Divided by ounces produced | 3,552 | 23 | |
| Cash Cost, Before By-product Credits, per Ounce | $24.52 | $1,709 | |
| By-product credits per ounce | (22.44) | (8) | |
| Cash Cost, After By-product Credits, per Ounce | $2.08 | $1,701 | |
| AISC, Before By-product Credits, per Ounce | $34.98 | $1,833 | |
| By-product credits per ounce | (22.44) | (8) | |
| AISC, After By-product Credits, per Ounce | $12.54 | $1,825 | |
| In thousands (except per ounce amounts) | Six Months Ended June 30, 2025 | ||||||
|---|---|---|---|---|---|---|---|
| Greens Creek · Lucky Friday · Keno Hill (5) · Corporate (2) · Total Silver | |||||||
| Total cost of sales | $128,559 | $86,335 | $41,752 | $— | $256,646 | ||
| Depreciation, depletion and amortization | (26,486) | (26,700) | (7,943) | — | (61,129) | ||
| Treatment costs | 1,142 | 5,017 | — | — | 6,159 | ||
| Change in product inventory | 8,333 | (614) | — | — | 7,719 | ||
| Reclamation and other costs | (250) | (433) | — | — | (683) | ||
| Exclusion of Keno Hill cash costs (5) | — | — | (33,809) | — | (33,809) | ||
| Cash Cost, Before By-product Credits (1) | 111,298 | 63,605 | — | — | 174,903 | ||
| Reclamation and other costs | 1,514 | 390 | — | 1,904 | |||
| Sustaining capital | 15,636 | 31,139 | — | 2,295 | 49,070 | ||
| General and administrative | — | — | — | 24,539 | 24,539 | ||
| AISC, Before By-product Credits (1) | 128,448 | 95,134 | — | 26,834 | 250,416 | ||
| By-product credits: | |||||||
| Zinc | (46,886) | (14,070) | — | — | (60,956) | ||
| Gold | (87,171) | — | — | — | (87,171) | ||
| Lead | (12,701) | (28,751) | — | — | (41,452) | ||
| Copper | (1,600) | — | — | — | (1,600) | ||
| Total By-product credits | (148,358) | (42,821) | — | — | (191,179) | ||
| Cash Cost, After By-product Credits | $(37,060) | $20,784 | $— | $— | $(16,276) | ||
| AISC, After By-product Credits | $(19,910) | $52,313 | $— | $26,834 | $59,237 | ||
| Divided by ounces produced | 4,426 | 2,673 | 7,099 | ||||
| Cash Cost, Before By-product Credits, per Ounce | $25.15 | $23.79 | $24.64 | ||||
| By-product credits per ounce | (33.52) | (16.02) | (26.93) | ||||
| Cash Cost, After By-product Credits, per Ounce | $(8.37) | $7.77 | $(2.29) | ||||
| AISC, Before By-product Credits, per Ounce | $29.02 | $35.59 | $35.28 | ||||
| By-product credits per ounce | (33.52) | (16.02) | (26.93) | ||||
| AISC, After By-product Credits, per Ounce | $(4.50) | $19.57 | $8.35 | ||||
| In thousands (except per ounce amounts) | Six Months Ended June 30, 2025 | ||
|---|---|---|---|
| Casa Berardi | Other (4) | Total Gold | |
| Total cost of sales | $101,472 | $13,720 | $115,192 |
| Depreciation, depletion and amortization | (14,415) | — | (14,415) |
| Treatment costs | 89 | — | 89 |
| Change in product inventory | 3,196 | — | 3,196 |
| Reclamation and other costs | (636) | — | (636) |
| Exclusion of Other costs | — | (13,720) | (13,720) |
| Cash Cost, Before By-product Credits (1) | 89,706 | — | 89,706 |
| Reclamation and other costs | 636 | — | 636 |
| Sustaining capital | 4,136 | — | 4,136 |
| AISC, Before By-product Credits (1) | 94,478 | — | 94,478 |
| By-product credits: | |||
| Silver | (367) | — | (367) |
| Total By-product credits | (367) | — | (367) |
| Cash Cost, After By-product Credits | $89,339 | $— | $89,339 |
| AISC, After By-product Credits | $94,111 | $— | $94,111 |
| Divided by ounces produced | 49 | — | 49 |
| Cash Cost, Before By-product Credits, per Ounce | $1,845 | $— | $1,845 |
| By-product credits per ounce | (8) | — | (8) |
| Cash Cost, After By-product Credits, per Ounce | $1,837 | $— | $1,837 |
| AISC, Before By-product Credits, per Ounce | $1,943 | $— | $1,943 |
| By-product credits per ounce | (8) | — | (8) |
| AISC, After By-product Credits, per Ounce | $1,935 | $— | $1,935 |
| In thousands (except per ounce amounts) | Six Months Ended June 30, 2025 | ||
|---|---|---|---|
| Total Silver | Total Gold and Other | Total | |
| Total cost of sales | $256,646 | $115,192 | $371,838 |
| Depreciation, depletion and amortization | (61,129) | (14,415) | (75,544) |
| Treatment costs | 6,159 | 89 | 6,248 |
| Change in product inventory | 7,719 | 3,196 | 10,915 |
| Reclamation and other costs | (683) | (636) | (1,319) |
| Exclusion of Keno Hill cash costs (5) | (33,809) | — | (33,809) |
| Exclusion of Other costs | — | (13,720) | (13,720) |
| Cash Cost, Before By-product Credits (1) | 174,903 | 89,706 | 264,609 |
| Reclamation and other costs | 1,904 | 636 | 2,540 |
| Sustaining capital | 49,070 | 4,136 | 53,206 |
| General and administrative | 24,539 | — | 24,539 |
| AISC, Before By-product Credits (1) | 250,416 | 94,478 | 344,894 |
| By-product credits: | |||
| Zinc | (60,956) | — | (60,956) |
| Gold | (87,171) | — | (87,171) |
| Lead | (41,452) | — | (41,452) |
| Copper | (1,600) | — | (1,600) |
| Silver | — | (367) | (367) |
| Total By-product credits | (191,179) | (367) | (191,546) |
| Cash Cost, After By-product Credits | $(16,276) | $89,339 | $73,063 |
| AISC, After By-product Credits | $59,237 | $94,111 | $153,348 |
| Divided by ounces produced | 7,099 | 49 | |
| Cash Cost, Before By-product Credits, per Ounce | $24.64 | $1,845 | |
| By-product credits per ounce | (26.93) | (8) | |
| Cash Cost, After By-product Credits, per Ounce | $(2.29) | $1,837 | |
| AISC, Before By-product Credits, per Ounce | $35.28 | $1,943 | |
| By-product credits per ounce | (26.93) | (8) | |
| AISC, After By-product Credits, per Ounce | $8.35 | $1,935 | |
| In thousands (except per ounce amounts) | Six Months Ended June 30, 2024 | |||||
|---|---|---|---|---|---|---|
| Greens Creek · Lucky Friday · Keno Hill(5) · Corporate (2) · Total Silver | ||||||
| Total cost of sales | $126,643 | $65,042 | $39,797 | $— | $231,482 | |
| Depreciation, depletion and amortization | (25,759) | (18,619) | (8,331) | — | (52,709) | |
| Treatment costs | 15,793 | 5,969 | — | — | 21,762 | |
| Change in product inventory | 5,100 | 496 | — | — | 5,596 | |
| Reclamation and other costs | (1,537) | (413) | — | — | (1,950) | |
| Exclusion of Lucky Friday cash costs (3) | — | (3,634) | — | — | (3,634) | |
| Exclusion of Keno Hill cash costs (5) | — | — | (31,466) | — | (31,466) | |
| Cash Cost, Before By-product Credits (1) | 120,240 | 48,841 | — | — | 169,081 | |
| Reclamation and other costs | 1,570 | 405 | — | — | 1,975 | |
| Sustaining capital | 19,327 | 21,568 | — | 1,101 | 41,996 | |
| Exclusion of Lucky Friday sustaining costs | — | (5,396) | — | — | (5,396) | |
| General and administrative | — | — | — | 25,956 | 25,956 | |
| AISC, Before By-product Credits (1) | 141,137 | 65,418 | — | 27,057 | 233,612 | |
| By-product credits: | ||||||
| Zinc | (42,079) | (11,491) | — | — | (53,570) | |
| Gold | (55,395) | — | — | — | (55,395) | |
| Lead | (13,799) | (27,187) | — | — | (40,986) | |
| Exclusion of Lucky Friday by-product credits | — | 3,943 | — | — | 3,943 | |
| Total By-product credits | (111,273) | (34,735) | — | — | (146,008) | |
| Cash Cost, After By-product Credits | $8,967 | $14,106 | $— | $— | $23,073 | |
| AISC, After By-product Credits | $29,864 | $30,683 | $— | $27,057 | $87,604 | |
| Ounces produced | 4,722 | 2,369 | 7,091 | |||
| Exclusion of Lucky Friday ounces produced | — | (253) | (253) | |||
| Divided by ounces produced | 4,722 | 2,116 | 6,838 | |||
| Cash Cost, Before By-product Credits, per Ounce | $25.46 | $23.08 | $24.73 | |||
| By-product credits per ounce | (23.56) | (16.41) | (21.35) | |||
| Cash Cost, After By-product Credits, per Ounce | $1.90 | $6.67 | $3.38 | |||
| AISC, Before By-product Credits, per Ounce | $29.89 | $30.91 | $34.16 | |||
| By-product credits per ounce | (23.56) | (16.41) | (21.35) | |||
| AISC, After By-product Credits, per Ounce | $6.33 | $14.50 | $12.81 | |||
| In thousands (except per ounce amounts) | Six Months Ended June 30, 2024 | ||
|---|---|---|---|
| Casa Berardi | Other (4) | Total Gold | |
| Total cost of sales | $125,600 | $7,513 | $133,113 |
| Depreciation, depletion and amortization | (49,961) | — | (49,961) |
| Treatment costs | 76 | — | 76 |
| Change in product inventory | 1,189 | — | 1,189 |
| Reclamation and other costs | (415) | — | (415) |
| Exclusion of Other costs | — | (7,513) | (7,513) |
| Cash Cost, Before By-product Credits (1) | 76,489 | — | 76,489 |
| Reclamation and other costs | 415 | — | 415 |
| Sustaining capital | 7,528 | — | 7,528 |
| AISC, Before By-product Credits (1) | 84,432 | — | 84,432 |
| By-product credits: | |||
| Silver | (326) | — | (326) |
| Total By-product credits | (326) | — | (326) |
| Cash Cost, After By-product Credits | $76,163 | $— | $76,163 |
| AISC, After By-product Credits | $84,106 | $— | $84,106 |
| Divided by ounces produced | 45 | — | 45 |
| Cash Cost, Before By-product Credits, per Ounce | $1,692 | $— | $1,692 |
| By-product credits per ounce | (7) | — | (7) |
| Cash Cost, After By-product Credits, per Ounce | $1,685 | $— | $1,685 |
| AISC, Before By-product Credits, per Ounce | $1,868 | $— | $1,868 |
| By-product credits per ounce | (7) | — | (7) |
| AISC, After By-product Credits, per Ounce | $1,861 | $— | $1,861 |
| In thousands (except per ounce amounts) | Six Months Ended June 30, 2024 | ||
|---|---|---|---|
| Total Silver | Total Gold | Total | |
| Total cost of sales | $231,482 | $133,113 | $364,595 |
| Depreciation, depletion and amortization | (52,709) | (49,961) | (102,670) |
| Treatment costs | 21,762 | 76 | 21,838 |
| Change in product inventory | 5,596 | 1,189 | 6,785 |
| Reclamation and other costs | (1,950) | (415) | (2,365) |
| Exclusion of Lucky Friday cash costs | (3,634) | — | (3,634) |
| Exclusion of Keno Hill cash costs | (31,466) | — | (31,466) |
| Exclusion of Other costs | — | (7,513) | (7,513) |
| Cash Cost, Before By-product Credits (1) | 169,081 | 76,489 | 245,570 |
| Reclamation and other costs | 1,975 | 415 | 2,390 |
| Sustaining capital | 41,996 | 7,528 | 49,524 |
| Exclusion of Lucky Friday sustaining costs | (5,396) | — | (5,396) |
| General and administrative | 25,956 | — | 25,956 |
| AISC, Before By-product Credits (1) | 233,612 | 84,432 | 318,044 |
| By-product credits: | |||
| Zinc | (53,570) | — | (53,570) |
| Gold | (55,395) | — | (55,395) |
| Lead | (40,986) | — | (40,986) |
| Silver | — | (326) | (326) |
| Exclusion of Lucky Friday by-product credits | 3,943 | — | 3,943 |
| Total By-product credits | (146,008) | (326) | (146,334) |
| Cash Cost, After By-product Credits | $23,073 | $76,163 | $99,236 |
| AISC, After By-product Credits | $87,604 | $84,106 | $171,710 |
| Ounces produced | $7,091 | $45 | |
| Exclusion of Lucky Friday ounces produced | $(253) | $— | |
| Divided by ounces produced | 6,838 | 45 | |
| Cash Cost, Before By-product Credits, per Ounce | $24.73 | $1,692 | |
| By-product credits per ounce | (21.35) | (7) | |
| Cash Cost, After By-product Credits, per Ounce | $3.38 | $1,685 | |
| AISC, Before By-product Credits, per Ounce | $34.16 | $1,868 | |
| By-product credits per ounce | (21.35) | (7) | |
| AISC, After By-product Credits, per Ounce | $12.81 | $1,861 | |
(1)
Includes all direct and indirect operating costs related to the physical activities of producing metals, including mining, processing and other plant costs, third-party refining and marketing expense, on-site general and administrative costs and royalties, before by-product revenues earned from all metals other than the primary metal produced at each operation. AISC, Before By-product Credits also includes reclamation and sustaining capital costs.
(2)
AISC, Before By-product Credits for our consolidated silver properties includes corporate costs for general and administrative expense and sustaining capital.
(3)
Lucky Friday operations were suspended in August 2023 following the underground fire in the #2 shaft secondary egress and resumed on January 9, 2024. The portion of cash costs, sustaining costs, by-product credits, and silver production incurred during the suspension period are excluded from the calculation of total cost of sales, Cash Cost, Before By-product Credits, Cash Cost, After By-product Credits, AISC, Before By-product Credits, and AISC, After By-product Credits.
(4)
Other includes $6.6 million and $13.7 million of total cost of sales for the three and six months ended June 30, 2025, respectively related to our environmental remediation services business, and $3.6 million and $7.5 million of total cost of sales for the three and six months ended June 30, 2024.
(5)
Keno Hill is in the ramp-up phase of production and is excluded from the calculation of Cash Cost, Before By-product Credits, Cash Cost, After By-product Credits, AISC, Before By-product Credits, and AISC, After By-product Credits.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.