Our Company
We are building the first and only global Cellular Broadband network in space to be accessible directly by everyday smartphones (2G/4G-LTE/5G devices) for commercial use, and other applications for government use utilizing our extensive intellectual property (“IP”) and patent portfolio. The SpaceMobile Service is being designed to provide cost-effective, high-speed Cellular Broadband services to end-users who are out of terrestrial cellular coverage using existing mobile devices. The SpaceMobile Service currently is planned to be provided by a constellation of high-powered, large phased-array satellites in low Earth orbit (“LEO”) using low-band and mid-band spectrum controlled by Mobile Network Operators (“MNOs”).
We intend to work with MNOs to offer the SpaceMobile Service to the MNOs’ end-user customers. Our vision is that users will not need to subscribe to the SpaceMobile Service directly through us, nor will they need to purchase any new or additional equipment. Instead, users will be able to access the SpaceMobile Service when prompted on their mobile device that they are no longer within range of the land-based facilities of the MNOs or will be able to purchase a plan directly with their existing mobile provider. We intend to seek to use a revenue-sharing business model for SpaceMobile Service in our agreements with MNOs.
The SpaceMobile Service is expected to be highly attractive to MNOs as it will enable them to improve and differentiate their service offering without significant incremental capital investments. The SpaceMobile Service is expected to enable MNOs to augment and extend their coverage without building towers or other land-based infrastructure, including where it is not cost-justified or is difficult due to geographical challenges. As a result of the incremental coverage created by the planned SpaceMobile Service, we believe that MNOs will have the opportunity to increase subscribers’ average revenue per user (“ARPU”).
We also intend to leverage our patented technology, including large phased array and high power capability of our BlueWalker 3 (“BW3”) test satellite and our BB satellites, for a variety of applications in the government sector. To this end, we have entered into agreements with prime contractors for the United States (“U.S.”) government to perform certain tasks and intend to seek to enter into other similar agreements with the U.S. government, either directly or through prime contractors, to develop and test certain non-communication applications and, once qualified, provide certain non-communication and communication services through our satellites.
On April 1, 2019, we launched our first test satellite, BlueWalker 1 (“BW1”), which was used to validate our satellite to cellular architecture and was capable of managing communications delays from LEO and the effects of doppler in a satellite to ground cellular environment using the 4G-LTE protocol.
We launched our BW3 test satellite on September 10, 2022, and announced the completion of the deployment of the communication phased array antenna of the BW3 test satellite in orbit on November 14, 2022. Using the BW3 test satellite, we successfully completed two-way 5G voice calls directly to standard unmodified smartphones, achieved repeated successful download speeds of above 21 megabits per second (“Mbps”) to standard unmodified smartphones and spectral efficiency of approximately 3 bits per second per hertz. We have also successfully completed initial in-orbit and ground testing for non-communication government applications. We intend to continue testing capabilities of the BW3 test satellite, including further testing with cellular service providers and the U.S. government.
We launched five first generation commercial BB satellites (“Block 1 BB satellites”) on September 12, 2024. The Block 1 BB satellites are of similar size and weight to the BW3 test satellite and have ten times higher throughput than the BW3 test satellite. In October 2024, we completed the deployment of the communication phased array antennas and Q/V antennas in orbit and performed a series of monitoring tests and activities to confirm the successful initial operations of the Block 1 BB satellites. In January 2025, we successfully made the first SpaceMobile video call from space with Vodafone using standard unmodified smartphones. In February 2025, we completed the voice and video call tests on standard unmodified smartphones with AT&T and Verizon in the U.S. and also completed the tests for non-communication applications for the U.S. government. All five Block 1 BB satellites have participated in the tests at various stages. We expect to continue testing for SpaceMobile Service including beta testing prior to rollout of initial noncontinuous SpaceMobile Service in select markets including the United States, Europe and Japan.
Our next generation of commercial BB satellites (“Block 2 BB satellites”) featuring up to approximately 2,400 square feet communication array, the largest communication array to be ever deployed in a LEO for commercial use and more than three times bigger than the communication array of the Block 1 BB satellites in orbit today, are designed to deliver up to 10 times the bandwidth capacity of the Block 1 BB satellites. We believe the larger aperture array is expected to provide greater spectrum reuse, enhanced signal strength and increased capacity, thereby reducing the necessary number of satellites to achieve service coverage as compared to smaller apertures. In addition, when we introduce our own AST5000 Application Specific Integrated Circuit (“ASIC”) chip in the Block 2 BB satellites, we expect to achieve materially greater throughput capacity of up to 40 MHz per beam to support 120 Mbps peak data rates and up to 10,000 MHz of processing bandwidth per Block 2 BB satellite, require less power and offer a lower overall unit cost. We have reached key production milestones and are in initial production phase of the first batch of the ASIC chip. Until we introduce our ASIC chip in Block 2 BB satellites, we expect to continue to manufacture and launch Block 2 BB satellites that are based on a Field Programmable Gate Arrays (“FPGA ”) chip.
We have entered into launch agreements with multiple launch service providers which will enable us to commence a planned launch campaign during 2025 and 2026 to launch approximately 60 Block 2 BB satellites. We have commenced assembling and testing the Block 2 BB satellites in accordance with our plan to meet this launch campaign to enable Continuous SpaceMobile Service coverage across key markets such as the United States, Europe, Japan and other strategic markets as well as to facilitate U.S. government applications. We expect to ship the first next-generation Block 2 BB satellite to the launch provider by the end of April 2025 for a launch estimated to occur shortly thereafter, which will commence our launch campaign of approximately 60 Block 2 BB satellites in 2025 through 2026. The timing of shipment of the first Block 2 BB satellite is contingent on a number of factors including satisfactory and timely completion of the assembly and testing of the Block 2 BB satellite, regulatory approvals for the launch, readiness of the launch vehicle, logistics and other factors, many of which are beyond our control.
We are headquartered in Texas where we operate 194,000 square feet of satellite assembly, integrating and testing (“AIT”) facilities and operate from multiple locations that include AIT and engineering and development locations elsewhere in the United States, India, Scotland, Spain and Israel.
Competitive Advantage
We believe our planned SpaceMobile Service will have the following competitive advantages:
Large Addressable Market: Our planned SpaceMobile Service is aimed at providing Cellular Broadband to mobile subscribers who are constantly moving in and out of coverage or live or work outside coverage, have no Cellular Broadband coverage, and have no connectivity or mobile cellular coverage. According to Groupe Speciale Mobile Association (“GSMA”), as of December 31, 2024, approximately 5.8 billion mobile subscribers are constantly moving in and out of coverage, approximately 3.4 billion people have no cellular broadband coverage and approximately 350.0 million people have no connectivity or mobile cellular coverage.
Delivery of Cellular Broadband Coverage at a Competitive Cost: We believe MNOs and wireless infrastructure providers will integrate our Cellular Broadband coverage capabilities to more cost effectively deliver wireless services in hard to reach areas and other areas that experience coverage gaps as compared to existing technology. We also believe the SpaceMobile Service could be used as a back up in the event of a disruption of service to the MNO’s terrestrial infrastructure due to a natural disaster such as a hurricane, civil unrest or a cyberattack.
Definitive Commercial Agreements with MNOs Enabling Access to Key Markets and Potentially Large Number of Subscribers: We believe our definitive commercial agreement with AT&T and our plan to enter into an agreement with Verizon provide us a significant opportunity to provide SpaceMobile Service to the majority of end-users in the United States. Similarly, our definitive commercial agreement with Vodafone provides us with an opportunity to provide SpaceMobile Service to a large number of end-users in several international markets outside the United States. These definitive commercial agreements enable access to key markets and large number of end-users, which provides us with a significant advantage to rapidly roll out SpaceMobile Service, when available, and gain a higher market share in the direct-to-device market segment.
Cellular Broadband Directly to Unmodified Devices: Our large phased array, based on our innovative technology backed by more than 3,500 patent and patent pending claims, is designed to provide high speed Cellular Broadband including voice, text, data and video services directly to any off-the-shelf and unmodified 2G/4G-LTE/5G mobile device using low and mid-band cellular spectrum currently used by MNOs. This technology eliminates the need to purchase expensive, specialized equipment or new mobile device or to carry antennas.
Satellites Designed for Great Functionality, Power and Redundancy: Our satellites are designed to have the largest commercial phased array ever deployed in LEO to provide high speed Cellular Broadband for commercial use. Our large phased array aperture is expected to provide greater spectrum reuse, enhanced signal strength and increased capacity, thereby reducing the number of satellites required to achieve service coverage as compared to smaller aperture satellites. Our custom developed ASIC chip is expected to enable materially greater throughput capacity, including peak data rates of up to 120 Mbps per individual spot beam when utilizing 40 MHz of spectrum and two-way back haul capacity which could utilize up to 10,000 MHz of spectrum per satellite, require less power and offer a significantly lower overall unit cost. We believe our large phased array design and custom ASIC chip together with our expansive and technologically diverse intellectual property portfolio consisting of more than 3,500 patent and patent pending claims, including innovations in the direct-to-cell satellite ecosystem from space to Earth, provide significant technological advantages to provide superior coverage and deliver high speed Cellular Broadband versus other direct to device satellite services.
Cost Advantages due to Greater Control of our Manufacturing: We believe that our significant investments in our manufacturing facilities and equipment, testing facilities including vibration and environment testing facilities, manufacturing processes, and supply chain provide us with a greater degree of control to manufacture our satellites in a timely manner and lower the overall costs of our satellites. We own the IP and control the manufacturing process either internally or through third-party contract manufacturers for approximately 95% of all the sub-systems used in our Block 2 BB satellites. We believe that having these intellectual property rights and controlling the manufacturing of these sub-systems provides flexibility to better secure our supply chain and lower the overall cost of our satellites.
Capability to Support Both Commercial and Government Applications on the Same Satellite or on a Singular Infrastructure: We believe our satellites will be capable of supporting both SpaceMobile Service to end users of the MNOs and a variety of applications in the government sector. We believe that having satellites to support both commercial and governmental applications will enable us to better optimize and monetize the capacity and capabilities of our satellites.
Our Strategy
We intend to build a SpaceMobile Service which leverages our technology to provide Cellular Broadband services to MNO end-user customers around the world using existing mobile devices, and for government use. The principal components of our strategy include the following:
Develop Complementary Relationships with Mobile Network Operators. We intend on partnering with MNOs to offer the SpaceMobile Service to their end-user customers. We believe the strategy will enable our MNO partners to expand the coverage areas of their operations and increase their total addressable market with limited incremental capital investment.
Focus on Providing Wholesale Services to Mobile Network Operators. In addition to seeking complementary relationships with MNOs, we will also seek to sell our services on a wholesale basis to MNOs who then offer this capability directly to their customer base. We believe this focus will enable us to avoid competing with existing incumbent MNOs and reduce the complexity of our operations, thereby significantly reducing our overhead, marketing costs, customer acquisition costs, billing infrastructure and other customer support operations.
Modular Deployment Schedule. We plan to construct and launch satellites in phases to focus our constellation’s initial coverage on targeted geographical areas that provide the most attractive opportunities. This prioritization of coverage is designed to minimize the capital required to initiate commercial service and generate revenue sooner. Focusing on targeted geographical areas will also enable us to concentrate our resources on fewer regulatory and ground infrastructure initiatives.
Continuing to Build and Leverage Relationships with Wireless Infrastructure Providers. We have entered into agreements with wireless infrastructure partners and intend to leverage these relationships to provide the in-country ground infrastructure and telecom facilities necessary for our MNO partners to deliver the SpaceMobile Service to their customers. We also believe that these wireless infrastructure providers will assist us in developing innovative financing techniques to support our infrastructure roll out and help us identify and partner with MNOs around the world.
Maintaining our Focus on Technology and Innovation. We continue to focus on research and development to bring our SpaceMobile Service to market for commercial service to end user customers of the MNOs and for certain government applications. Our continued innovation in the development of our satellite system, components and related technologies and services are supported by a global engineering team of space scientists and consultants. We are also making steady progress in industrializing our component manufacturing and satellite assembly process to automate the assembly, installation and testing of satellites. We are continuing to invest in our supply chain and expand our supplier base, increase the level of vertical integration for manufacturing our BB satellites to reduce dependency on any single supplier, secure the timely supply of materials to meet the production volume of our satellites, and control costs. We protect our innovations by filing numerous patent applications and intellectual property registrations in the U.S. and worldwide. We own most of the intellectual property we use. We also systematically monitor and review potential infringements on our intellectual property.
Developing Relationships with Multiple Launch Vehicle Providers. We have entered into agreements with multiple launch vehicle providers to secure launch contracts that meet our planned launch timelines for the initial BB constellation. In addition, we are continuing to develop strategic relationships with additional launch vehicle providers both in the United States and outside the United States for cost effective future launches. Our BB satellites are designed to be launched in a variety of launch vehicles. Our current launch agreements with multiple launch providers enable us to commence a planned launch campaign during 2025 and 2026 to launch approximately 60 Block 2 BB satellites.
Explore opportunities for variety of applications in government sector. We intend to leverage our patented technology, including large phased array and high power capability of our BW3 test satellite and our BB satellites, for a variety of applications in the government sector. To this end, we have entered into agreements with prime contractors for the U.S. government to perform certain tasks and intend to seek to enter into other similar agreements with the U.S. government or prime contractors for the U.S government. We are also selected by the Space Development Agency (“SDA”) for an Other Transaction agreement to compete for upcoming prototype demonstration projects under the Hybrid Acquisition for proliferated Low-earth Orbit (HALO) program. We will now have the opportunity to compete directly as a prime contractor for specific prototype orders, demonstrating the feasibility and scalability of our technology for various government applications.
Technology Development Activities
The industry in which we compete is subject to rapid technological developments, evolving standards, changes in customer requirements and continuing developments in the communications and networking environment area. We believe our ability to adapt to these changes and to develop the SpaceMobile Service will be an important factor in our ability to execute our business plan.
Satellite design and development
Our BB satellite primarily consists of a phased array and a spacecraft bus (also referred to as a Control sat). The phased array consists of building blocks called microns. Each micron contains multiple antennas, front-end modules, a distributed digital processing and data transfer unit, and a thermal and electrical power system consisting of a solar panel, batteries and a power distribution unit. The Control sat is the main body and structural component of our BB satellite in which the payload and various subsystems, such as propulsion system, reaction wheels, avionics, power control and distribution unit, and QV antennas, are held.
As part of our strategy, we aim to own and control the IP of all major sub systems of our BB satellites, and design and assemble our own constellation of BB satellites. We conduct a majority of our satellite design and development activities by utilizing our global engineering team, including space scientists, mechanical and electronics engineers, semi-conductor engineers, RF and communications engineers, software developers, system engineers, and consultants on various aspects of our satellite system development efforts. Our design and development activities primarily take place in our engineering and development centers located in the United States, Scotland, Spain, India and Israel. In addition, we utilize third-party technology partners to assist in the development of certain satellite technology.
We have invested a substantial amount and hundreds of man-years in development of key sub systems including our solar power system for power generation at relatively lower cost than space industry standard power generation cost, battery packs, power control and distribution unit, flight software, ASIC chip, payload system, mechanisms and structures. We have devoted over four years of dedicated research, development and engineering expertise, equivalent to an estimated 150 man-years of intensive work, in design and development of our custom ASIC chip. We own the IP of our ASIC chip. While our initial Block 2 BB satellites currently in production are designed to support low-band spectrum only, we continue to make progress towards the completion of the design and development of our Block 2 BB satellites supporting mid-band spectrum.
Our Block 2 BB satellites are expected to be approximately 2,400 square feet in size and more than three times bigger than the communication array of the Block 1 BB satellites, which, by themselves, are the largest satellites in LEO. The Block 2 BB satellites will have the largest phased array ever deployed in a LEO for commercial use. We expect that the Block 2 BB satellites will benefit from the advantages of a larger aperture array and our own ASIC chip. We believe the larger aperture array of the Block 2 BB satellites is expected to provide greater spectrum reuse, enhanced signal strength and increased capacity thereby reducing the number of satellites required to achieve service coverage as compared to smaller aperture. We believe our ASIC chip, through our collaboration with a leading semiconductor design company, will enable materially greater throughput capacity of up to 40 MHz per beam to support up to 120 Mbps peak data rates and up to 10,000 MHz of processing bandwidth per Block 2 BB satellite, require less power and offer a significantly lower overall unit cost. Until we introduce our ASIC chip in Block 2 BB satellites, we expect to continue to manufacture and launch Block 2 BB satellites that are based on a FPGA chip.
Satellite deployment and coverage plans
We are developing a phased satellite deployment plan and corresponding commercial launch plan of the SpaceMobile Service based on targeted geographical areas to provide the SpaceMobile Service to the most commercially attractive MNO markets. This prioritization of coverage is designed to minimize the capital required to initiate and operate commercial service that generates cash flows from operating activities. We expect that such a successful commercial service would enable us to attract additional capital to continue to assemble and launch additional BB satellites to expand our capacity and geographic coverage area, although there can be no assurance that such capital would be available on terms acceptable to us, or at all.
We plan to achieve noncontinuous SpaceMobile Service in the selected, targeted geographical markets with the launch and operation of a total of 25 BB satellites (five Block 1 BB satellites and 20 Block 2 BB satellites). We believe the operation of a constellation of 25 BB satellites will enable us to potentially generate cash flows from operating activities to further support the buildup of the remaining constellation. We believe we can enable Continuous SpaceMobile Service coverage across key markets such as the United States, Europe, Japan and other strategic markets with the launch and operation of a total of approximately 45 to 60 BB satellites, and achieve Continuous SpaceMobile Service in all targeted geographical markets to meet our long term business goals with the launch and operation of a total of approximately 90 BB satellites. We anticipate launching and deploying additional satellites beyond the initial 90 satellites in order to enhance coverage and system capacity in response to incremental market demand. Continuous coverage is not expected to be available at all times in certain areas due to numerous factors, including number of active satellites in the region, latitude coverage range, and other factors. Our current plan is subject to numerous uncertainties, many of which are beyond our control, including satisfactory and timely completion of assembly and testing of the satellites, regulatory approvals, readiness of launch vehicles, availability of launch windows by the launch providers, logistics, our ability to raise additional capital for manufacturing of satellites and launch payments, proposed orbits and resulting satellite coverage, launch costs, ability to enter into agreements with MNOs and other factors, many of which are beyond our control. We may adopt a strategy for commercial launch of the SpaceMobile Service, including the nature and type of services offered and the geographic markets where we may launch such services, that may differ materially from our current plan.
Customers, Sales and Marketing
We have developed relationships with companies, such as Vodafone, Rakuten, AT&T, Verizon, Google, American Tower, and others that have innovative technologies and products, skilled personnel, and potential end-user customers that complement our strategy. We believe that our business model is attractive to MNOs who will be able to augment and extend their Cellular Broadband coverage to customers without having to build additional towers, infrastructure, or purchase additional spectrum. In addition, we believe that the SpaceMobile Service will provide MNOs the opportunity to increase monthly ARPU through the sales of additional services.
We believe our patented technology leveraging our large phased array antenna could also be used in certain mission-critical communication capabilities in the government sector. We have entered into agreements with prime contractors for the U.S. government to perform certain tasks on our BW3 test satellite and our Block 1 BB satellites in orbit today and intend to seek to enter into other similar agreements with the U.S. government or prime contractors for the U.S government. We are also selected by the Space Development Agency (“SDA”) for an Other Transaction agreement to compete for upcoming prototype demonstration projects under the Hybrid Acquisition for proliferated Low-earth Orbit (HALO) program. We will now have the opportunity to compete directly as a prime contractor for specific prototype orders, demonstrating the feasibility and scalability of our technology for various government applications.
The SpaceMobile Service is being designed to offer Cellular Broadband under our wholesale business model with MNOs. We expect the MNOs will market our SpaceMobile Service to their existing customers, who will be the ultimate end-users. We generally seek to negotiate a revenue-sharing model in our agreements with MNOs. To date, we have entered into definitive commercial agreements with AT&T and Vodafone and approximately 50 preliminary agreements and understandings with other MNOs. We will need to execute definitive commercial agreements with those MNOs that will supersede the preliminary agreements and understandings before we can offer our SpaceMobile Service in jurisdictions where they operate.
We expect that the MNOs will market and sell the enhanced coverage of the SpaceMobile Service directly to their customers and offer the service at a differentiated price to the current terrestrial coverage using the following illustrative service offerings, among others.
| Service Offering | Service Offering Details | |
|---|---|---|
| Day Pass (Ad-Hoc) | ● | Upon leaving the terrestrial cellular coverage area, mobile subscribers will receive a text on their phone asking if they would like to turn on the SpaceMobile Service. |
| Monthly Add-on Subscription (Consumer) | ● | Subscribers can pay a fixed monthly fee to add the SpaceMobile Service as a supplemental service to their current wireless plan. |
| ● | Roaming onto the SpaceMobile Service’s network upon entering an area without cell tower coverage. | |
| Monthly Add-on Subscription (Enterprise) | ● | Same as monthly add-on for consumers, but with more data targeting commercial enterprises. |
| Standalone Get Connected Plan | ● | In areas without cellular coverage today, subscribers will use and pay for the SpaceMobile Service as their primary network through an MNO partner. |
| Aeronautical and Maritime | ● | Connect end users travelling in aircraft and vessels for Cellular Broadband service. |
| Military and Government | ● | Service for military and governmental operations |
We expect that the majority of our revenue will be generated from SpaceMobile Service offerings, once available, similar to those described above through revenue-sharing arrangements with MNOs; however, the ultimate offerings and pricing will be subject to mutual agreement with the MNOs and there can be no assurance as to what model any MNO ultimately offers its customers and the level of customer acceptance of these models.
The operation of SpaceMobile Service will require mobile traffic to be transmitted by our constellation of BB satellites and connected via high-throughput Q/V-band links to ground station gateways which will be collocated with the MNOs’ cellular network infrastructure. We are expanding our efforts on ground infrastructure development for commercial readiness and integrating our SpaceMobile Service into the MNOs’ infrastructure to initiate commercial services. We have entered into agreements for sale of gateway equipment and associated services to MNOs in development of our global network infrastructure.
Manufacturing, Assembly and Launch
Our strategy is to control the manufacturing and supply chain of the components used in our BB satellites, and assemble, integrate and test BB satellites primarily in our AIT facilities in Texas. We believe this strategy will result in a faster turn to market, greater control and lower overall costs. Our primary AIT facilities include approximately 194,000 square feet facilities in Texas for assembly and testing of our BB satellites, as well as an approximately 59,000 square foot new facility in Spain for assembly and testing of avionics and reliability components which will replace the existing 10,500 square foot facility when the lease ends in April 2025, and an approximately 33,000 square foot facility in Israel for assembly and testing of electronic components. We have made, and are continuing to make, significant capital investments in buildings and equipment both at our AIT facilities and at certain suppliers to increase the capacity to manufacture satellite components to reach our target capacity of assembling, integrating, and testing six BB satellites per month by the second quarter of 2025; streamline the assembly, integration and testing processes for BB satellites; and conduct various testing of satellites including vibration and environment testing at our facilities.
We utilize a range of domestic and international contract manufacturers and vendors to manufacture specific components, subsystems, software and other electronic components used in our BB satellites. As we have transitioned into mass production of our satellite components to meet our planned launches, we have entered into several long-term supply agreements and are seeking to enter into more long-term supply agreements with our suppliers to both secure supply of components to meet our demand and optimize the overall cost. Some components, subsystems and services necessary for the assembly of our satellites are currently obtained from a sole source supplier or a limited group of suppliers. Where feasible, we seek to evaluate and qualify new suppliers to mitigate our risk of dependency on sole source suppliers and increase the capacity and availability of components. We have made significant investments in the design, development, supply chain, and manufacturing and assembly processes of our BB satellites including various sub systems and components. We own the IP and control the manufacturing process, either internally at our AIT facilities or with contract manufacturers, for approximately 95% of the sub-systems used in our Block 2 BB satellites. In certain cases where we have invested or co-invested with our suppliers in the design and development of satellite components and subsystems but do not own the IP design and in cases where we select suppliers to manufacture our own custom designed components and subsystems, we generally have contractual restrictions on the suppliers prohibiting the use of these design, development, and manufacturing processes for certain number of years to supply the same or similar satellite components and subsystems to any other third parties. We continuously aim to increase, where feasible, vertical integration for manufacturing of satellite components and subsystems at our AIT facilities to reduce our dependency on suppliers, ensure timely supply of satellite components and subsystems to meet our launch timeline, and lower the overall cost of BB satellites.
We have designed and developed our own ASIC chip. We have invested a substantial amount in completing the design of the ASIC chip and we own the IP of our ASIC chip. We entered into an agreement with a leading semiconductor manufacturer for tape-out and fabrication of our ASIC chip. We have reached a key production milestone and are in initial production phase of the first batch of our ASIC chip. Until we introduce our ASIC chip in Block 2 BB satellites, we expect to continue to manufacture and launch Block 2 BB satellites that are based on a FPGA chip.
We are leveraging the technological expertise and manufacturing know-how derived from the assembly and testing of our Block 1 BB satellite in the development and assembly of our Block 2 BB satellites. We are actively engaged in planning and procurement of materials needed for assembly and readiness of the Block 2 BB satellites to meet our planned launches in 2025 and 2026. As of the date of this Annual Report, we have placed orders for procurement of substantially all materials and components needed, in accordance with our production plan, for the assembly, integration and testing of the next 20 Block 2 BB satellites. In addition, we have also accelerated the procurement of components and materials needed for us to complete fully assembled microns and phased array for 53 Block 2 BB satellites and complete 40 fully integrated and assembled Block 2 BB satellites. Our manufacturing, assembly, and testing strategy for Block 2 BB satellites includes continuous production and assembly of various components and sub systems for economies of scale, cost efficiencies, and unlocking capacity constraints, to build sufficient quantity of components and sub systems readily available on hand to be able to complete the final integration and testing of the required number of Block 2 BB satellites closer to the planned launch timelines. As of the date of this Annual Report, we have completed production of various components and sub systems and have completed assembly of microns for multiple Block 2 BB satellites. We plan on continuing with the production of various components and sub systems and assembly of microns based on our current capacity and supply of materials. We plan to integrate these microns with control sat and test the fully integrated Block 2 BB satellites closer to the planned launch timeline. Once we complete the integration and testing of the first Block 2 BB satellite and complete our planned investments to increase assembly, integration, and testing capacity to six Block 2 BB satellites per month, we plan to accelerate the manufacturing, assembly, integration and testing of the Block 2 BB satellites to meet our planned launches in 2025 and 2026.
We have entered into launch agreements with multiple launch service providers which will enable us to commence a planned launch campaign during 2025 and 2026 to launch approximately 60 Block 2 BB satellites to enable Continuous SpaceMobile Service coverage across key markets such as the United States, Europe, Japan and other strategic markets as well as to facilitate U.S. government applications. We expect to ship the first next-generation Block 2 BB satellite to the launch provider by the end of April 2025 for a launch estimated to occur shortly thereafter, which will commence our launch campaign of approximately 60 Block 2 BB satellites in 2025 through 2026. The timing of shipment of the first Block 2 BB satellite is contingent upon a number of factors including satisfactory completion of the testing of the Block 2 BB satellite, receipt of necessary regulatory approvals for the launch, readiness of the launch vehicle, logistics and other factors, many of which are beyond our control. The timing of the planned launches in 2025 and 2026 is contingent on satisfactory and timely completion of the assembly and testing of the Block 2 BB satellites in accordance with our plan, timely receipt of necessary regulatory approvals, readiness of the launch vehicles and availability of launch windows by the launch providers, logistics, our ability to raise capital for manufacturing of satellites and launch payments, and other factors, many of which are beyond our control.
Government Regulations
We are required to comply with the laws and regulations of, and often obtain approvals from, national and local authorities in connection with our services. As we initiate service in additional countries and regions, we will become subject to additional governmental approvals and regulations. We will provide several services that rely on the use of radio-frequency spectrum, and the provision of such services is highly regulated. Satellites must be operated in a manner consistent with the regulations and procedures of the International Telecommunication Union (“ITU”), a specialized agency of the United Nations, which require the coordination of the operation of satellite systems in certain circumstances, and more generally are intended to avoid the occurrence of harmful interference among different authorized uses of the radio spectrum.
Our business is subject to extensive rules, regulations, statutes, orders and policies imposed by the government in the United States and in foreign jurisdictions. For example, in the U.S. commercial use of radio-frequency spectrum is subject to the jurisdiction of the Federal Communications Commission (“FCC”) under the Communications Act of 1934, as amended. The FCC is responsible for authorizing the operation of U.S. registered commercial spacecraft, and also authorizes non-U.S. licensed spacecraft to serve the United States. The FCC also licenses the operation of earth stations in U.S. states, territories and protectorates, and regulates the technical and other aspects of the operation of these facilities.
We will submit a modification to our commercial license with the FCC. This modification application (“Modification Application”) will be filed in the coming weeks, and will request authority to add additional satellites and frequencies for use with the SpaceMobile Service in the United States, including the incorporation of Verizon frequencies. This additional authority will support the growth and commercialization of our company in the United States, including the start of full commercial operations of the Non-Geostationary Orbit (“NGSO”) satellite system employing low-band (below 1 GHz) commercial cellular frequencies for service links, S- and UHF-band frequencies to support off-nominal telemetry, tracking, and control (“TT&C”) communications, and V-band frequencies for routine feeder link operations.
We expect that, if approved, the FCC will apply routine conditions to a license grant authorizing further satellite launches for the revised NGSO satellite system that we must comply with. If we further change the operational parameters of our satellites, we will need to file a supplemental application to modify our license with the FCC and obtain affirmative consent before undertaking such changes. If we do not meet the launch and operation milestones set out in our August 2024 grant of authority, we risk losing all or a portion of our surety bond for failure to meet such milestones.
Because the SpaceMobile Service will communicate with end users employing personal/portable cellular devices serving as mobile earth stations transmitting on spectrum traditionally licensed to MNOs, in the U.S. we also will need the approval of the FCC’s Wireless Telecommunications Bureau, which handles terrestrial wireless licensing. We have a lease agreement with AT&T pending before the FCC to authorize service links to end users in low-band spectrum that will be revised to align with the Modification Application. Similarly, we intend to file a new lease agreement with Verizon to enable use of its low-band spectrum that will be processed in parallel with the Modification Application.
We have experimental licenses with the FCC that permit the testing of the BW3 test satellite and the Block 1 BB satellites in LTE frequencies in multiple locations in the United States and permits the testing of V-band ground stations with the BW3 in Texas and Hawaii in connection therewith. We are required to comply with operational and coordination requirements set forth as conditions to the experimental license grant. Material changes to the experimental license testing parameters would require prior approval by the FCC.
We also will need to secure FCC authority in the future for the ground segment of the SpaceMobile Service, consisting of five fixed earth stations located in the United States. Earth station licenses generally are granted for 15-year terms, and typically are renewed in the ordinary course. Special temporary authority (“STA”) has been applied for each of these earth station sites as bridging authority, and the FCC approved such operations for Midland, Texas and Brewster, Washington in February 2025. Material changes in earth station operations would require prior approval by the FCC. The operation of our earth stations is subject to various license conditions, as well as the technical and operational requirements of the FCC’s rules and regulations.
We are also seeking regulatory approval for fixed earth stations in other jurisdictions around the world to operate satellite earth stations in connection with our service, including in connection with evaluation of the Block 1 BB satellites. Also, we are seeking regulatory approval to permit the commercial operation of our satellites using V-band and cellular frequencies in foreign jurisdictions where we intend to operate. If we are unable to obtain such regulatory approvals, we would not be able to operate in those jurisdictions. With respect to the BW3 test satellite, we have contracted with third parties to permit the usage of UHF and S-band frequencies for orbit raising maneuvers and off-nominal TT&C communications in jurisdictions outside of the United States. We intend to contract with third parties for the usage of UHF and S-band frequencies in jurisdictions outside of the United States in connection with the commercial operation of the SpaceMobile Service.
The SpaceMobile Service will also operate under filings made by the United States with the ITU to enable us to operate our satellite system. The orbital location and frequencies for our satellites are subject to the ITU’s regulations, including its frequency registration and coordination procedures, and its various provisions on spectrum usage. Those procedures are specified in the ITU Radio Regulations and seek to facilitate shared international use of limited spectrum and orbital resources in a manner that avoids harmful interference. Among other things, the ITU regulations set forth procedures for establishing international priority with respect to the use of such resources, deadlines for bringing satellite networks into use in order to maintain such priority, and coordination rights and obligations with respect to other networks, which vary depending on whether such networks have higher or lower ITU priority. Further licensing by the United States may be required if material changes to the SpaceMobile Service are made. We expect to register each of our satellites after launch with the United Nations Register of Objects Launched Into Outer Space.
Government regulators, including the FCC, have adopted expansive views of the scope of their regulatory authority over common carriers providing Cellular Broadband and are increasingly focused on the quality of service, customer disclosures, customer privacy, and the customer support that wireless carriers provide. These include, but are not limited to, common carrier obligations; universal service obligations; rules governing billing and the pass through of third party charges, regulations governing subscriber privacy and customer proprietary network information; access to E911 and location accuracy requirements; roaming obligations; rules that require wireless service providers to configure their networks to facilitate electronic surveillance by law enforcement officials; emergency warning requirements; rules governing spam, telemarketing and truth-in-billing; outage reporting; open Internet and Net neutrality requirements; cybersecurity and rules requiring the offering of equipment and services that are accessible to and usable by persons with disabilities, among others. Although we do not currently expect that SpaceMobile will be subject to common carrier obligations and regulations, SpaceMobile’s MNO partners may be subject to the conditions described above.
On March 14, 2024, the FCC adopted a First Report & Order to implement a regulatory framework for SCS, which allows satellite operators to collaborate with terrestrial service providers to expand coverage to terrestrial licensee subscribers. We view the initial SCS rules as creating a favorable regulatory framework for the satellite-to-device services industry.
On August 2, 2024, the FCC authorized the launch of the first five Block 1 BB satellites under Call Sign S3065. This call sign will serve as underlying FCC designator for the full 248 satellite constellation planned by AST SpaceMobile. The FCC also approved operation of ancillary communications to the AST SpaceMobile fleet in UHF, S-band and V-band frequencies for telemetry, tracking and command functions, as well as feeder link connectivity for aggregated voice and data traffic.
In January 2025, we obtained STAs for service link operations from the FCC, under which we have begun testing in the United States employing low-band spectrum from AT&T and Verizon in the United States. We have also obtained the Special Temporary Authority in Turkey and the United Kingdom with Vodafone.
Intellectual Property
Our IP portfolio is expansive and technologically diverse, containing numerous and various innovations of the direct-to-cell satellite ecosystem from space to Earth. As of December 31, 2024, our IP portfolio consists of more than 3,500 patent and patent pending claims worldwide, of which approximately 1,550 have been officially granted or allowed. We have 36 patent families worldwide and to date, we have 45 granted United States patents (44 of which we own and one of which is exclusively licensed to us) and at least five United States patent applications that have been indicated as allowable and ready for issue pending completion of patent office formalities. We also have approximately 26 currently pending United States patent applications. Moreover, we have 19 granted international patents providing protection in 17 different countries, including Europe, Australia, Canada, India, Japan, and South Korea, and 6 that have been indicated as allowable and ready for issue pending completion of patent office formalities. We have approximately 61 pending international patent applications in the countries noted above as well as under the Patent Cooperation Treaty.
We seek to establish and maintain our proprietary rights in our technology and products through a combination of patents, copyrights, trademarks, trade secrets and contractual rights. We also seek to maintain our trade secrets and confidential information through nondisclosure policies, the use of appropriate confidentiality agreements and other security measures. We maintain IP infringement enforcement and defense insurance and plan to vigorously defend any infringement of our IP. We have filed or registered a number of patents and trademarks in the United States and in other countries and have a number of patent filings pending. There can be no assurance, however, that these rights can be successfully enforced against competitors or competitive products in any particular jurisdiction. Although we believe the protection afforded by our patents, copyrights, trademarks, trade secrets and contracts has incredible value, the rapidly changing technology in the satellite and wireless communications industries and uncertainties in the legal process make our future success dependent on the innovative skills, technological expertise and management abilities of our employees.
Certain of our products include software or other intellectual property licensed from third parties. While it may be necessary in the future to seek or renew licenses relating to various aspects of our products, we believe, based upon past experience and standard industry practice, that such licenses generally could be obtained on commercially reasonable terms. Nonetheless, there can be no assurance that the necessary licenses would be available on acceptable terms, if at all.
The industry in which we compete is characterized by rapidly changing technology, a large number of patents, and related litigation regarding patent and other intellectual property rights. We cannot assure you that our patents and other proprietary rights will not be challenged, invalidated or circumvented, that others will not assert intellectual property rights to technologies that are relevant, or that our rights will give us a competitive advantage. In addition, the laws of some foreign countries may not protect our proprietary rights to the same extent as the laws of the United States.
Competition
The mobile satellite services industry at-large is highly competitive but has significant barriers to entry, including the cost and difficulty associated with successfully developing, building and launching a satellite network and obtaining various governmental and regulatory approvals. In addition to cost, there is a significant amount of lead time associated with obtaining the required licenses, building and launching the satellite constellation, and developing and deploying the ground network technology. We currently face competition from other service providers that offer a range of mobile and fixed communications options. There are also a number of competitors who have developed or are working to develop innovative solutions to compete in this industry, many of which are more established providers or have significantly greater resources than we do.
We face competition from existing and new companies including SpaceX’s Starlink and Globalstar, which are developing satellite communications technology using LEO constellations to provide competitive services in the direct-to-device segment of the mobile satellite services industry. In 2023, Apple introduced a new service supported by Globalstar which provides SOS Emergency Service capabilities to its latest generation iPhones. In February 2025, SpaceX and T-Mobile US offered a beta test of Starlink that included text messaging. In addition, we face competition from existing service providers such as Inmarsat, Globalstar, ORBCOMM, Thuraya Telecommunications Co. and Iridium Communications that offer a range of mobile and fixed communications options. We believe the planned SpaceMobile Service will compete with the direct-to-device segment of the mobile satellite service sector by providing the ability to support Cellular Broadband data rates, utilize existing unmodified handsets and operate in virtually all of the low to mid-band spectrums used by MNOs today. In comparison, the mobile satellite service LEOs offered by our existing competitors are designed to support low data rate applications such as SOS.
We also compete with regional mobile satellite communications services in several geographic markets. In these cases, the majority of our competitors’ customers require regional, not global, mobile voice and data services, so competitors may present a viable alternative to the SpaceMobile Service. These regional competitors operate or plan to operate geostationary satellites. In some markets, we compete directly or indirectly with very small aperture terminal operators that offer communications services through private networks using very small aperture terminals or hybrid systems to target business users. We also compete indirectly with terrestrial wireline and wireless communications networks and to the extent that terrestrial communications companies invest in underdeveloped areas, we may face increased competition in those areas.
Environmental, Health and Safety
We are subject to various laws and regulations relating to the protection of the environment and human health and safety, including those governing the management, storage and disposal of hazardous materials, such as fuels and batteries, which may contain hazardous materials. Certain environmental laws, such as the U.S. Comprehensive Environmental Response, Compensation and Liability Act of 1980, as amended (“CERCLA”), impose joint and several liability, without regard to fault, for cleanup costs on persons who disposed of or released hazardous substances into the environment, including at third-party sites or offsite disposal locations, or those who currently own or operate (or formerly owned or operated) sites where such a release occurred. In addition to clean-up actions brought by federal, state, local and foreign governmental entities, private parties could raise personal injury or other claims against us due to the presence of, or exposure to, hazardous materials on, from or otherwise relating to such a property.
Also, our operation of satellites will be regulated by various jurisdictions over which our satellites will travel, as well as those jurisdictions in which we enter or return to the earth’s atmosphere and land (including through unintentional landings), though complete destructive atmosphere reentry of each satellite is anticipated. We could incur significant costs, including cleanup costs, fines, sanctions and third-party claims, as a result of violations of or in connection with liabilities under environmental laws and regulations.
Human Capital Management
As of December 31, 2024, we had approximately 578 employees and consultants worldwide, which included approximately 312 employees and consultants in the U.S. and approximately 266 in other jurisdictions, primarily Scotland, Spain, India and Israel. We view the strength of our leadership team and our talented colleagues around the world as a critical component of our future success. In certain countries in which we operate, we are subject to, and comply with, local labor law requirements, which may automatically make our employees subject to industry-wide collective bargaining agreements. None of our U.S. employees are subject to any collective bargaining agreement. Generally, each employee is required to sign a confidentiality, non-disclosure and non-use agreement with us. We have not experienced any work stoppages and consider our relations with our employees to be good.
We consider our talent to be very important to our operations and execution of our business strategy as well as the overall success of our business. Our key human capital objectives in managing our business include attracting, developing and retaining top talent. As such, we invest significant management attention, time and resources to attract, engage, develop and retain our talent. Our talent strategy focuses on our employee training and development and the overall well-being and safety of our talent.
We have ongoing training and development programs to enable employees to further refine and develop their skills. We provide access and make training and development programs available to our employees which include technical programs, regulatory and compliance, business communications and leadership development.
We seek to attract employees by using a wide variety of recruiting platforms, such as online job portals, recruiters, in-person job fairs, local university training and recruitment programs, and employee referrals. We encourage training and development of our employees and provide on-the-job training and online platforms.
Our success depends, in part, on our continuing ability to identify, hire, attract, train, develop, and maintain our employees’ well-being. Our ability to hire, attract and retain employees depends on our ability to provide competitive total compensation. Our compensation and benefit packages are designed to attract and retain employees and align the employees’ interests with our long-term success. We seek to align the interests of our employees and stockholders by providing long-term incentive programs such as awards of stock-based compensation to most of our employees. We generally make available the following benefits for our employees, including, but not limited to, a 401(k) retirement savings plan for our U.S. based employees, health insurance, flexible spending accounts, life insurance, long- and short-term disability, paid vacation, paid time off for holidays, sick time, and parental leave.
We are committed to providing a safe working environment for our employees. Our engineering and manufacturing facilities have injury prevention programs, and our procedures emphasize the need for the cause of injuries to be investigated and for action plans to be implemented to mitigate potential recurrence.
Key Wireless Infrastructure Provider Relationships
We have relationships with various wireless infrastructure providers. A summary of certain commercial relationships with wireless infrastructure providers is below.
Vodafone
On December 9, 2024, AST LLC and Vodafone entered into a definitive long-term commercial agreement through 2034, subject to certain termination rights, which establishes the framework for Vodafone to offer space-based cellular broadband connectivity in its home markets, as well as to other operators via its Partner Markets program (the “Vodafone Commercial Agreement”). The Vodafone Commercial Agreement includes mutual exclusivity, conditioned upon AST meeting certain service commitments and applicable regulatory or governmental approvals for the services, within certain Vodafone home markets for five years; preferential commercial terms in Vodafone partner markets; a revenue share for the SpaceMobile Service; and the procurement, building and operating of mobile network ground stations at a mutually agreed cost by Vodafone. Vodafone submitted purchase orders for Block 1 BlueBird gateways and other network equipment from us to support planned commercial service. Vodafone has the right to designate one individual to our Board of Directors. Currently, Vodafone’s designee is Luke Ibbetson, Head of Group Research & Development, Vodafone.
American Tower
We and American Tower have entered into a side letter agreement that was subsequently amended and restated on December 15, 2020 to reflect the transactions and agreements contemplated by the Equity Purchase Agreement between us and New Providence Acquisition Corp. (“NPA”) (the “Amended and Restated Letter Agreement”). The Amended and Restated Letter Agreement contemplates that we and American Tower will enter into commercial agreements to allow us to use American Tower facilities for our terrestrial gateway facilities in certain markets. The term of the operational agreement between us and American Tower is for an anticipated five years after the initial launch of commercial mobile services by us.
On March 22, 2022, we and American Tower entered into a non-binding term sheet reflecting the terms and conditions for the deployment of our gateway satellite technology equipment on property owned and operated by American Tower. Under the agreement, American Tower will provide us leased space and managed services at its current and future tower sites and data centers under the global master lease agreements to be entered into by the parties.
The usage of any American Tower services in a Vodafone market will be memorialized in a commercial agreement among all three parties. In markets where Vodafone does not operate (“Carrier Neutral Markets”), we and American Tower may enter into an agreement for American Tower to manage the operation of our deployed gateway facility in such market. In Carrier Neutral Markets where we require a third party to provide a gateway facility or services, we agree to not accept any bid that is inferior to American Tower’s best and final proposal for such gateway facility or services. We also agree to use commercially reasonable efforts to utilize American Tower facilities in (i) Vodafone markets where Vodafone decides to not use its facilities, (ii) in Carrier Neutral Markets, and (iii) instances where we require a third-party vendor.
Additionally, we will work with American Tower to evaluate and plan gateway facility and radio access network data center deployments with preferred vendor status to offer carrier-neutral hosting facilities in certain equatorial markets. American Tower will serve as the preferred vendor for carrier neutral hosting facilities. We will pay American Tower a monthly connection fee for use of a carrier neutral hosting facility, which we expect will be charged back to each applicable MNO. If we and American Tower agree to construct a new carrier neutral hosting facility or improve an existing one and American Tower elects to fund all such capital expenditures, American Tower will provide us with a fair-market, long-term lease to such facility. No payments have been made to date between us and American Tower under the Amended and Restated Letter Agreement. American Tower has the right to designate one individual to our Board of Directors. Currently, American Tower’s designee is Ed Knapp, Chief Technology Officer, American Tower.
Rakuten
On February 4, 2020, we entered into a commercial agreement with Rakuten, for the development of exclusive network capabilities in Japan compatible with the mobile network of Rakuten and its affiliates, which agreement was amended and restated as of December 15, 2020 (the “Rakuten Agreement”). Under the terms of the Rakuten Agreement, we agreed to make investments in building network capabilities in Japan that are compatible with the mobile network of Rakuten and its affiliates. Furthermore, we will collaborate with Rakuten to ensure network capability with Rakuten’s licensed frequencies, including full coverage in Japan with 3GPP Band 3 frequencies with MIMO capability. Upon the launch of such coverage, Rakuten will receive unlimited, exclusive rights and usage capacity in Japan in exchange for a $0.5 million annual maintenance fee payable to us or our successors. Furthermore, we will make $5.0 million (or such lesser amount as mutually agreed upon the parties) in capital investments towards the design, assembly, acquisition and implementation of ground communication assets. We and Rakuten will receive unlimited rights and usage of the ground assets for their respective operations, including, but not limited to, satellite and other telecommunication communications. The term of the Rakuten Agreement shall remain in effect until we fulfill our obligations under the Rakuten Agreement. Rakuten Inc. has also submitted purchase orders for purchase of network equipment from AST LLC to support planned commercial service. Rakuten has the right to designate one individual to our Board of Directors and to appoint one observer to the Board. Currently, Rakuten has designated Hiroshi Mikitani, Founder, Chairman and Chief Executive Officer, Rakuten, Inc. as a director.
AT&T
We have achieved many significant milestones in our collaboration with AT&T over the years. We achieved our first two-way voice call in April 2023, first over-the-top video application call in June 2023 and first direct-to-cellular 5G call in September 2023 using our BW3 test satellite and our first video call in February 2025 using our Block 1 BB satellites. We have also collaborated with AT&T to test applications of a nationwide public safety network built with and for America’s first responders in January 2024.
On May 10, 2024, AST LLC and AT&T entered into a definitive commercial agreement (“AT&T Commercial Agreement”) through 2030, subject to auto-renewal for successive two-year periods unless either party terminates. Under the AT&T Commercial Agreement, AT&T will purchase access to and utilize our network and satellite services to provide service offerings to AT&T’s end users within the continental United States (excluding Alaska) and Hawaii. AT&T will pay to AST LLC a percentage of the gross monthly revenue AT&T bills to its end users for the services enabled by the satellite services. AT&T has also submitted purchase orders for purchase of network equipment from AST LLC to support planned commercial service. In addition, under the AT&T Commercial Agreement, AT&T has made a non-refundable $20.0 million commercial payment for prepaid service revenue, creditable against future service revenue of AST LLC, as first set forth in a letter agreement, dated January 16, 2024, between AT&T and us. AT&T has the right to designate one individual to our Board of Directors. Currently, AT&T’s designee is Keith Larson, a long-time Intel executive with deep expertise in corporate development and corporate governance.
AST LLC entered into a letter agreement on January 16, 2024 with Google, LLC (“Google”) whereby the parties will negotiate and execute a definitive agreement to provide, among other things, certain services to each other and have agreed to collaborate on product development, testing and implementation plans for SpaceMobile network connectivity on Android devices (such agreement, the “Services Agreement”). On October 18, 2024, the parties executed the Services Agreement for a term that is three years after continuous commercial service coverage for end users at certain satellite orbit inclinations, subject to auto-renewal for successive three-year periods unless either party terminates.
Verizon
On May 23, 2024, AST LLC and Verizon entered into a Memorandum of Understanding, pursuant to which Verizon has made a non-refundable $20.0 million commercial payment for prepaid service revenue, creditable against future service revenue of AST LLC and will make a second $45.0 million commercial payment for prepaid service revenue, creditable against future service revenue of AST LLC, subject to us receiving certain regulatory approvals for our SpaceMobile Service and entry into a definitive commercial agreement. Verizon has also submitted purchase orders for purchase of network equipment from AST LLC to support planned commercial service.
Available Information
Our Company's internet website address is www.ast-science.com. We file or furnish periodic reports and amendments thereto, including our Annual Reports on Form 10-K, our Quarterly Reports on Form 10-Q and Current Reports on Form 8-K, proxy statements and other information with the SEC. We also make available on that website, and in print, if any stockholder or other person so requests, our “Code of Business Conduct and Ethics” applicable to all employees and Directors. Any waiver granted by us to our principal executive officer, principal financial offer, principal accounting officer or controller or persons performing similar functions under the Code of Ethics and certain amendments to the Code of Ethics will be posted on that website. In addition, the SEC maintains a website (www.sec.gov) that contains reports, proxy and information statements, and other information regarding issuers that file electronically.