Capital Requirements

We expect that all of our capital requirements over the next three years will come from a combination of internally generated funds and external debt financing. Projected capital construction and investment expenditures, excluding nuclear fuel purchases, for the next three years are presented in the following table. These projections include Allowance for Funds Used During Construction for PSE&G and Interest Capitalized During Construction for PSEG’s other subsidiaries. These amounts are subject to change, based on various factors. Amounts shown below for PSE&G include currently approved programs. We intend to continue to invest in infrastructure modernization and will seek to extend these and related programs as appropriate.

2025 · 2026 · 2027
Millions
PSE&G:
Transmission$735$890$920
Electric Distribution1,1901,2351,325
Gas Distribution1,0501,0251,050
Clean Energy745840935
Total PSE&G$3,720$3,990$4,230
Competitively Bid, FERC Regulated Transmission30265115
PSEG Power & Other280305290
Total PSEG$4,030$4,560$4,635

PSE&G

PSE&G’s projections for future capital expenditures include material additions and replacements to its T&D systems to meet expected growth and to manage reliability. As project scope and cost estimates develop, PSE&G will modify its current projections to include these required investments. PSE&G’s projected expenditures for the various items reported above are primarily comprised of the following:

Transmission—investments focused on growing demand, reliability improvements and replacement of aging infrastructure.

Electric and Gas Distribution—investments for new business and demand, reliability improvements and modernization and replacement of equipment that has reached the end of its useful life.

Clean Energy—investments associated with customer EE programs, infrastructure supporting EVs and grid-connected solar.

In 2024, PSE&G made $2,921 million of capital expenditures, primarily for T&D system reliability. In addition, PSE&G had cost of removal, net of salvage, of $170 million associated with capital replacements, and expenditures for EE programs of approximately $544 million, which are included in operating cash flows.

Competitively Bid, FERC Regulated Transmission

In December 2023, PJM awarded us an approximately $424 million project to address increasing load and reliability issues in Maryland and northern Virginia as part of its 2022 Window 3 competitive solicitation. PJM has directed that the project be placed in service in 2027.

PSEG’s other projected expenditures are primarily comprised of investments to maintain and enhance current nuclear operations and opportunities to increase nuclear generation at PSEG Power and to purchase hardware, software and office equipment at Services.

In 2024, PSEG Power & Other made capital expenditures of $251 million, excluding $208 million for nuclear fuel, primarily related to various nuclear projects at PSEG Power and various IT projects at Services.

Other Material Cash Requirements

The following table reflects our other material cash requirements which include debt maturities and interest payments, operating lease payments and energy related purchase commitments in the respective periods in which they are due. For additional information, see Item 8. Note 14. Debt and Credit Facilities, Note 7. Leases and Note 13. Commitments and Contingent Liabilities.

The table below does not reflect any anticipated cash payments for pension and OPEB or AROs due to uncertain timing of payments. See Item 8. Note 12. Pension, Other Postretirement Benefits (OPEB) and Savings Plans and Note 11. Asset Retirement Obligations (AROs) for additional information.

TotalAmountCommitted · LessThan1 Year · 2 - 3Years · 4 - 5Years · Over5 Years
Millions
Long-Term Recourse Debt Maturities
PSEG$4,896$550$700$1,350$2,296
PSE&G15,1153501,3001,07512,390
PSEG Power1,2501,250———
Interest on Recourse Debt
PSEG1,158207405268278
PSE&G9,6835901,1471,0786,868
PSEG Power (A)3232———
Operating Leases
PSE&G11619292147
PSEG Power & Other9416333213
Energy-Related Purchase Commitments
PSEG Power2,853904996532421
Total$35,197$3,918$4,610$4,356$22,313

(A)

Based on a blended rate including effects of floating to fixed rate hedging transacted at the Parent level.