Executive Overview
Overall Results
Net income for the three and nine months ended September 30, 2024 increased compared to the three and nine months ended September 30, 2023, primarily due to the effects of general rate cases and tax customer credits. These increases in earnings were partially offset by expected increases in operating expenses, depreciation and amortization expense, taxes other than income tax and interest expense.
More detailed explanations of the fluctuations in revenues and expenses are provided in the results of operations and business segment discussions (Avista Utilities, AEL&P, and the other businesses) that follow this summary.
Resource Adequacy
Peak Load Requirements
Extreme weather events, both in summer and winter, have recently occurred in the Pacific Northwest. These events have resulted in system load peaks that were higher than anticipated. Historically, we have had excess capacity as compared to peak load, but during some extreme events we have had to purchase short-term energy from the wholesale market to meet demand when our energy resources were not operating at full capacity or were otherwise unavailable. These weather events have highlighted the growing need for additional generating capacity both on our system and in the Pacific Northwest region. Accordingly, we are taking the increased peaks in demand into account as we consider our resource adequacy and generation requirements.
Annual Energy Requirements
The transition to clean energy (including the replacement of emitting facilities with non-emitting facilities, which are impacted by conditions outside of our control), and electrification, combined with expected load growth, factor into the analysis of the need for additional generation. As a result, we expect additional generating capacity will be needed earlier than reflected in our 2023 integrated resource plan (IRP).
2025 IRP
A draft IRP, reflecting the accelerated addition of generating resources, was submitted to the WUTC and IPUC in October 2024, and we plan to file the final IRP in January 2025. While the draft 2025 IRP is, and even the final 2025 IRP will be, subject to change from time to time due to changing circumstances, assumptions and projections, given the exit of Colstrip (222 MW) from our system by December 31, 2025 and the expected retirement of the Northeast combustion turbine (64.8 MW) in 2030, we see the need for the addition of approximately 490 MW of generating capacity by 2030 and a total of approximately 950 MW through 2035. We believe the additional capacity would likely consist of primarily of wind resources and a natural gas combustion turbine. The new capacity would likely be a combination of resources owned by the Company and resources committed under PPAs, to be determined on a case-by-case basis depending upon financial, tax and regulatory considerations.
We also expect expanded transmission infrastructure will provide access to additional resources and improve reliability in our region. We have signed a non-binding memorandum of understanding to join the North Plains Connector transmission line project, constructing a transmission line from Bismarck, North Dakota to Colstrip, Montana.
2024 Hydroelectric Generation and Snowpack Conditions
During 2024, our region experienced low precipitation, resulting in low snowpack levels and streamflows when compared to historical averages. This had a negative impact on our hydroelectric generation resources. Lower hydroelectric generation increased net power supply costs and resulted in us absorbing additional costs under the ERM in Washington. In the nine months ended September 30, 2024, we had a $7.8 million pre-tax expense under the ERM in Washington.
Washington Climate Commitment Act (CCA)
Effective January 1, 2023, the CCA went into effect in the State of Washington, requiring us to secure carbon allowances to cover our carbon emissions over a certain amount each year. Costs associated with the CCA are being deferred and are included in Washington natural gas customer rates starting in April 2024. The resulting aggregate increase to customer bills was approximately 3.7 percent over a one year period, and impacts customers differently based on revenue class, income level, and meter connection date. We have proposed an additional customer bill increase to recover costs associated with the CCA of 9.1 percent to become effective in November 2024, subject to WUTC approval.
Costs associated with the CCA related to our electric operations are deferred and included in the ERM for Washington customers. Amounts allocated to Idaho are not approved for recovery from customers. See "Note 15 of the Notes to Condensed Consolidated Financial Statements" for further discussion of the CCA costs associated with our electric operations and impacts on our financial results.
Regulatory Lag
Regulatory “lag” is inherent in utility ratemaking; a result of the delay between the investment in utility plant and/or the increase in costs and the receipt of an order of a public utility commission authorizing an increase in rates sufficient to recover such investment or costs. Regulatory lag can be mitigated to some extent by the incorporation of reasonably expected forward-looking information into an authorization of increased rates. However, there is no protection against unexpected inflation and increased interest rates, as experienced in 2022 and 2023. While we believe our recent general rate settlements are helpful, some increases in our costs will have to be addressed in future rate cases, including our 2024 Washington general rate cases. See “Regulatory Matters” for additional discussion of the general rate cases.