Item 1. Business
MGE Energy operates in the following business segments:
Regulated electric utility operations – generating, purchasing, and distributing electricity through MGE.
Regulated gas utility operations – purchasing and distributing natural gas through MGE.
Nonregulated energy operations – owning and leasing electric generating capacity that assists MGE through MGE Energy's wholly owned subsidiaries MGE Power Elm Road and MGE Power West Campus.
Transmission investments – representing our investment in American Transmission Company LLC, a company engaged in the business of providing electric transmission services primarily in Wisconsin, and our investment in ATC Holdco LLC, a company created to facilitate out-of-state electric transmission development and investments.
All other – investing in companies and property that relate to the regulated operations and financing the regulated operations, through its wholly owned subsidiaries CWDC, MAGAEL, North Mendota, and Corporate functions.
MGE's utility operations represent a majority of the assets, liabilities, revenues, expenses, and operations of MGE Energy. MGE Energy's nonregulated energy operations currently include an undivided interest in two coal-fired generating units located in Oak Creek, Wisconsin, which we refer to as the Elm Road Units, and an undivided interest in a cogeneration facility located on the Madison campus of the University of Wisconsin, which we refer to as the West Campus Cogeneration Facility or WCCF.
As a public utility, MGE is subject to regulation by the PSCW and the FERC. The PSCW has authority to regulate most aspects of MGE's business including rates, accounts, issuance of securities, and plant siting. The PSCW also has authority over certain aspects of MGE Energy as a holding company of a public utility. FERC has jurisdiction, under the Federal Power Act, over certain accounting practices and certain other aspects of MGE's business.
MGE Energy's subsidiaries are also subject to regulation under local, state, and federal laws regarding air and water quality and solid waste disposal. See "Environmental" below.
MGE Energy was organized as a Wisconsin corporation in 2001. MGE was organized as a Wisconsin corporation in 1896. Our principal offices are located at 133 South Blair Street, Madison, Wisconsin 53788, and our telephone number is (608) 252-7000.
Electric Utility Operations
MGE distributes electricity in a service area covering a 264 square-mile area of Dane County, Wisconsin. The service area includes the city of Madison, Wisconsin. It owns or leases ownership interests in electric generation facilities located in Wisconsin and Iowa.
As of December 31, 2023, MGE supplied electric service to approximately 163,000 customers, with approximately 90% located in the cities of Fitchburg, Madison, Middleton, and Monona and 10% in adjacent areas.
Electric sales, customers, and revenues for 2023 were comprised of the following:
Electric operations accounted for approximately 71%, 65%, and 69% of MGE's total 2023, 2022, and 2021 regulated revenues, respectively.
See Item 2. Properties for a description of MGE's electric utility plant.
MGE is registered with North American Electric Reliability Corporation (NERC) and one regional entity, the Midwest Reliability Organization. The essential purposes of these entities are to develop and implement regional and NERC reliability standards and determine compliance with those standards, including enforcement mechanisms.
Transmission
American Transmission Company LLC (ATC) was formed by Wisconsin-based utilities who were required by Wisconsin law to contribute their transmission facilities to it in 2001 and is owned by those utilities and their affiliates. ATC's purpose is to provide reliable, economic transmission service to all customers in a fair and equitable manner. ATC plans, constructs, operates, maintains, and expands transmission facilities that it owns to provide adequate and reliable transmission of power. ATC is regulated by FERC for all rate terms and conditions of service. ATC is also regulated by the PSCW for some aspects of its governance and is a transmission-owning member of the MISO.
Regional Transmission Organizations (RTO)
MISO
MGE is a nontransmission owning member of MISO. MISO, a FERC-approved RTO, is responsible for monitoring the electric transmission system that delivers power from generating plants to wholesale power customers. MISO's role is to ensure equal access to the transmission system and to maintain or improve electric system reliability across 15 U.S. states and the Canadian province of Manitoba.
MISO operates a bid-based energy market. MGE offers substantially all of its generation to the MISO market and purchases its electric supply, or load requirement from the MISO market in accordance with the MISO tariff. MGE also participates in the ancillary services market operated by MISO, which is an extension of the existing energy market. Through the operation of the ancillary services market, MISO provides the reserves for MGE's load, and MGE may offer to sell reserves from its generating units.
MGE participates in the MISO capacity auction, which provides a forum for buyers and sellers of planning resource credits to interact. Load serving entities such as MGE may participate in the capacity auction to obtain the necessary aggregate planning resource credits needed to meet their planning reserve margin requirement established by the PSCW. Generator owners may participate to sell any excess aggregate planning resource credits.
Fuel supply and generation
MGE satisfies its customers' electric demand with internal generation and purchased power. MGE's current fuel mix for generation fluctuates from year-to-year due to fuel pricing in the market, generating unit availability, weather, and customer demand. MGE has a responsibility to its customers to dispatch the lowest cost generation available pursuant to regulatory requirements.
MGE's electric energy delivery requirements were satisfied from the following fuel sources:
| (in MWh) | 2023 | 2022 | 2021 |
|---|---|---|---|
| Coal(a) | 1,359,691 | 1,219,793 | 1,797,017 |
| Natural gas | 566,972 | 539,265 | 405,696 |
| Renewable sources(b) | 715,369 | 759,194 | 581,374 |
| Fuel oil | 544 | 475 | 884 |
| Purchased power - other(c)(d) | 744,120 | 919,052 | 726,008 |
| Total fuel sources | 3,386,696 | 3,437,779 | 3,510,979 |
| Adjusted total fuel sources(d) | 3,643,267 | 3,741,207 | 3,743,743 |
(a)
In 2023, MGE used more coal generation for electric supply, compared with 2022. Generation sources change based on lowest cost generation available. MGE continues to drive its commitment to achieve our emission reduction goals through the continuing addition of renewable generation and its transition plan to eliminate coal as a fuel source.
(b)
Includes both internal generation and purchased power.
(c)
Includes third-party purchased power and MISO market activity. A significant percentage of MGE's electric supply comes from internal generation sources. MGE supplements this internal generation with long-term purchase power agreements and spot purchases in the MISO market.
(d)
The MISO market consists of two energy markets, the Day-ahead market and the Real-time market. The table above nets purchases and sales within the same hour in the two MISO markets. For the years ended December 31, 2023, 2022, and 2021, the amount netted between Day-ahead and the Real-time MISO markets was 256,571 MWh, 303,428 MWh, and 232,764 MWh, respectively. These amounts are reflected in "Adjusted total fuel sources."
MGE is working toward a more sustainable future for the benefit of its investors, employees, customers and the broader community. MGE is targeting net-zero carbon electricity by 2050 and MGE has committed to achieving carbon reductions of at least 80% by 2030 (from 2005 levels).
MGE's carbon reduction goals are aligned with those of the scientific community, specifically the Intergovernmental Panel on Climate Change (IPCC) and its recommendation of limiting global temperature increases to 1.5 degrees Celsius above pre-industrial levels. In 2020, the University of Wisconsin-Madison's Nelson Institute for Environmental Studies released its analysis of MGE's goal of reaching net-zero carbon electricity by 2050. The IPCC modeling available suggested that by 2050, emissions from electricity generation in industrialized countries should be 87% to 99% lower than the 2005 baseline. The analysis determined that our 2050 goal is in line with model benchmarks to limit global warming to 1.5 degrees Celsius above pre-industrial levels.
MGE is working to achieve a more sustainable energy future using the best, most cost-effective technologies as they become available. MGE's future path to achieve its target of 80% carbon reduction by 2030 (from 2005 levels) is based on the transition away from coal and the addition of new renewable generation to reach our ultimate target of net-zero carbon by 2050. MGE already has taken action toward its goals:
Transition away from coal - MGE and the other co-owners of Columbia, a two-unit coal-fired generation facility, intend to retire Unit 1 and Unit 2 by June 2026. MGE currently owns 19% of the facility. Final timing and retirement dates are subject to change depending on operational, regulatory, and other factors. By 2027, with the planned retirement of both units at Columbia, MGE will have eliminated approximately two-thirds of the company’s current coal-fired generation capacity. MGE's remaining use of coal is expected to be further reduced as the Elm Road Units transition to natural gas. MGE is a minority owner of the coal-fired Elm Road Generating Station. Transition plans and costs will be subject to PSCW approval. By the end of 2030, MGE expects coal to be used only as a backup fuel at the Elm Road Units. This transition will help MGE meet its 2030 carbon reduction goal. By the end of 2032, MGE expects that the Elm Road Units will be fully transitioned away from coal, which will eliminate coal as an owned generation source for MGE.
Renewable generation - Our solar, wind, and battery storage projects are a major step toward deep decarbonization and greater use of clean energy sources in pursuit of our net-zero carbon goal. Additionally, MGE seeks to reduce its use of fossil fuels and work to help customers with energy efficiency and electrification, including the electrification of transportation.
Since 2015, MGE has added 196 MW of solar and 93 MW of wind generation facilities to its electric renewable generation portfolio. See Item 2. Properties below for further information on these facilities. MGE offers cost-effective renewable energy solutions to customers, including the Renewable Energy Rider (RER) and Shared Solar Program, using a portion of this renewable capacity. These programs are described further below. The following includes renewable energy projects expected to be completed or proposed to be completed, and MGE's share of capacity.
| Year of Commercial Operation | Project | Ownership Interest | Source | Share of Generation/Battery Storage |
|---|---|---|---|---|
| 2024 | Tyto Solar(a) - Online February 2024 | 100% | Solar | 6 MW |
| Paris | 10% | Solar | 20 MW | |
| Darien(b) | 10% | Solar | 25 MW | |
| Strix Solar(a) | 100% | Solar | 6 MW | |
| 2025 | Paris | 10% | Battery | 11 MW |
| 2026 | Koshkonong(b) | 10% | Solar | 30 MW |
| High Noon – proposed(c) | 10% | Solar | 30 MW |
(a)
Project located within MGE service territory.
(b)
24 MW of battery storage has been approved by the PSCW as part of these projects, but is not included in the forecasted capital expenditures for 2024 through 2028. MGE will continue to evaluate timing, cost, and feasibility of the installation of battery storage.
(c)
A filed application is pending approval by the PSCW. 16.5 MW of battery storage has been proposed as part of this project, but is not included in the forecasted capital expenditures for 2024 through 2028. MGE will continue to evaluate timing, cost, and feasibility of the installation of battery storage.
MGE is partnering with the co-owners of Columbia to construct a compressed carbon dioxide long-duration energy storage system, known as the Columbia Energy Storage project. The 20 MW project was selected for a grant from the U.S Department of Energy. If the Columbia Energy Storage project is approved by the PSCW, the project would be the first of its kind in the United States.
MGE is working to achieve a more sustainable energy future by investing in cost-effective renewable generation and innovative new technologies and services for customers. MGE has emphasized this innovation by developing customer programs to address climate change and encourage our customers to use clean energy. Our RER and Shared Solar programs reduce MGE's carbon emissions while providing customers the ability to purchase renewable energy to meet their energy needs, and we have been working on many fronts in the community to further the electrification of transportation.
Renewable Energy Rider (RER) – Under this program, MGE partners with large energy users, primarily governmental entities, on customized renewable energy solutions. MGE owns the generation assets and RER customers are billed a contractual renewable resource rate (as approved by the PSCW) for all costs associated with the construction and ongoing operations of the renewable generation facility. MGE has developed approximately 42 MW of solar generation under the RER program.
Shared Solar Program – This program provides an option for residential and small business customers to power their household or business with locally generated solar energy for up to half of their annual energy use. The first solar array associated with this program, owned by MGE, became operational in 2017 for 500 KW capacity. MGE expanded the program by completing construction of a second solar facility (Morey Field), which added 3.5 MW of capacity to the program.
Electrifying transportation - The electrification of transportation is a key strategy for reducing carbon emissions. MGE has established a network of more than 50 charging stations, powered by renewable energy, serving the growing number of electric vehicles (EV) in our service area. An EV fast charging hub features some of the most powerful EV chargers in the Midwest. Charge@Home, MGE's home EV charging program, makes it easy for EV drivers to charge efficiently and conveniently. We have continued to add EVs to our fleet and are targeting 100% all-electric or plug-in hybrid light-duty vehicles by 2030. Additionally, we are working with the City of Madison to further the electrification of its vehicles and buses. The City of Madison currently has a goal of 100% electric buses used for its' new Bus Rapid Transit system located in the downtown region.
Natural gas as a fuel source - As part of MGE's continued energy transition plan, MGE plans to invest in additional natural gas plants and storage facilities. These power sources are vital to the success of our carbon reduction goals as they will provide reliable energy to dependably serve demand, while MGE continues to build out its renewable generation infrastructure and complete its full transition away from coal. In early 2023, MGE purchased 25 MW in the West Riverside Energy Center, a highly efficient, state-of-the-art natural gas-fired plant in Beloit, Wisconsin. In fall 2023, MGE requested approval from the PSCW to purchase an additional 25 MW of capacity in West Riverside. The closing and actual transfer of ownership is expected to occur in June 2024. Natural gas has lower carbon emission rates compared to coal-fired generation. The reliable energy supply provided by West Riverside plant will help MGE to retire the Columbia coal-fired facility. MGE has additional investments in natural gas generators planned for the future to ensure adequate dispatchable capacity requirements are met.
Generation sources
MGE receives electric generation supply from coal-fired, gas-fired, and renewable energy sources. These sources include owned facilities as well as facilities leased from affiliates and accounted for under our nonregulated energy operations. See Item 2. Properties for more information regarding these generation sources, including location, capacity, ownership or lease arrangement, and fuel source. See "Nonregulated Energy Operations" below for more information regarding generating capacity leased to MGE by MGE Energy's nonregulated subsidiaries.
Purchased power
MGE enters into short- and long-term purchase power commitments with third parties to meet a portion of its anticipated electric energy supply needs. As of December 31, 2023, MGE has 30 MW of a renewable purchase power commitment for each of the next four years.
Gas Utility Operations
MGE transports and distributes natural gas in a service area covering 1,684 square miles in seven south-central Wisconsin counties. The service area includes the city of Madison, Wisconsin and surrounding areas.
As of December 31, 2023, MGE supplied natural gas service to approximately 176,000 customers in the cities of Elroy, Fitchburg, Lodi, Madison, Middleton, Monona, Prairie du Chien, Verona, and Viroqua; 25 villages; and all or parts of 50 townships. Gas sales, customers, and revenues for 2023 were comprised of the following:
Gas operations accounted for approximately 29%, 35%, and 31% of MGE's total 2023, 2022, and 2021 regulated revenues, respectively.
MGE can curtail gas deliveries to interruptible customers. These are customers who agree to reduce their load in the case of an emergency interruption. Approximately 3% of retail gas deliveries in 2023, 2022 and 2021 were to interruptible customers.
Environmental Initiatives - Natural gas distribution
Building upon our long-standing commitment to providing affordable, sustainable energy, MGE has set a goal to achieve net-zero methane emissions from its natural gas distribution system by 2035. If MGE can accelerate plans to achieve net-zero methane emissions from its natural gas system—through the evolution of new technologies, such as renewable natural gas—it will. MGE is working to reduce overall emissions from its natural gas distribution system cost-effectively as quickly as possible.
Gas supply
MGE has physical interconnections with ANR Pipeline Company (ANR) and Northern Natural Gas Company (NNG). MGE's primary service territory, which includes Madison and the surrounding area, receives deliveries at one NNG and four ANR gate stations. MGE's outlying territory receives deliveries at NNG gate stations located in Elroy, Prairie du Chien, Viroqua, and Crawford County. Interconnections with two major pipelines provide competition in interstate pipeline service and a more reliable and economical gas supply mix, which includes gas from Canada and the mid-continent and Gulf Coast regions of the United States.
During the winter months, when customer demand is high, MGE is primarily concerned with meeting its obligation to customers. MGE meets customer demand by using firm supplies under contracts finalized before the heating season, supplies in storage (injected during the summer), and other firm supplies purchased during the winter period.
By contract, a total of approximately 6.5 million Dth of gas can be injected into ANR's storage fields in Michigan from April 1 through October 31. These gas supplies are then available for withdrawal during the subsequent heating season, November 1 through March 31. Using storage allows MGE to buy gas supplies during the summer season, when prices are normally lower, and withdraw these supplies during the winter season, when prices are typically higher. Storage also gives MGE more flexibility in meeting daily load fluctuations.
MGE's contracts for firm transportation service of gas include winter maximum daily quantities of:
185,650 Dth (including 116,078 Dth of storage withdrawals) on ANR.
81,453 Dth on NNG.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.