Future Resource Needs

Avista Utilities has operational strategies to provide sufficient resources to meet our energy requirements under a range of operating conditions. These operational strategies consider the amount of energy needed, which varies because of the factors that influence demand over intra-hour, hourly, daily, monthly and annual durations. Our average hourly load was 1,115 aMW in 2023, 1,142 aMW in 2022 and 1,113 aMW in 2021.

The following graph shows our forecast of our average annual energy requirements and our available resources for 2024 through 2027:

(1)

The combined maximum capacity of Boulder Park GS, Kettle Falls CT, Northeast CT and Rathdrum CT is 278 MW, with estimated available energy production as indicated for each year.

(2)

Other contracts for power purchases includes power purchase agreements for solar and wind energy.

(3)

The forecast assumes near normal hydroelectric generation.

(4)

Includes the Lancaster Plant PPA. Excludes Boulder Park GS, Kettle Falls CT, Northeast CT and Rathdrum CT, as these are considered peaking facilities and are generally not used to meet our base load requirements.

We are required to file an Integrated Resource Plan (IRP) or Washington Progress Report with the WUTC and IPUC every two years. The WUTC and IPUC review the IRP and give the public the opportunity to comment. The WUTC and IPUC do not approve or disapprove of the content in the IRP; rather, they acknowledge that the IRP was prepared in accordance with applicable standards if that is the case. The IRP details projected growth in demand for energy and the new resources needed to serve customers over the next 20 years. We regard the IRP as a tool for resource evaluation, rather than an acquisition plan for a particular project.

In June 2023, we filed our 2023 Electric IRP with the WUTC and the IPUC. We anticipate our next IRP to be filed in 2025.

Highlights of the 2023 Electric IRP include the following expectations and/or assumptions:

The forecast for growth in energy requirements increased to 0.9 percent per year, from 0.2 percent in the 2021 IRP. Higher growth largely reflects higher residential and commercial electric vehicle forecasts and new building electrification.

We have entered into PPAs for several renewable resources, and an expected divestiture (Colstrip at the end of 2025) since our 2021 IRP.

The resource strategy selected in the IRP is designed to achieve an 80 percent reduction in GHG emissions by 2045.

We need long-duration storage to serve customers in peak hours after 2035.

We created a Named Community Investment Fund to increase energy-related investments in disadvantaged communities. The fund will increase distributed energy resources such as energy efficiency, small-scale renewables, and energy storage.

We are subject to the Washington State Energy Independence Act, which requires us to obtain a portion of our electricity from qualifying renewable resources or through purchase of RECs and acquiring all cost effective conservation measures. Future generation resource decisions will be affected by legislation for restrictions on greenhouse gas emissions and renewable energy requirements.

See “Item 7. Management’s Discussion and Analysis of Financial Condition – Environmental Issues and Contingencies” and “Colstrip” for information related to existing and proposed laws and regulations, and issues relating to Colstrip.

Additional generating resources required will either be owned by us or be owned by other parties who will sell us the capacity and energy under PPAs. The decision as to ownership will be made as to each project at the appropriate time and will depend on, among other things, the type of project and the related economics, including tax and ratemaking treatment.

Electric Clean Energy Goals

We have an aspirational goal to serve our customers with 100 percent clean electricity by 2045. To help achieve this goal and add to our clean electricity portfolio, we have implemented renewable energy projects, including entering into various PPAs for solar, wind and hydroelectric resources. These resources are in addition to our existing clean hydroelectric generation, biomass generation, and additional wind and solar projects.

To achieve our clean energy goals, we expect energy storage and other technologies, which are either not currently available or are not cost-effective under the lowest reasonable cost regulatory standard, will advance to allow us to meet our goals while maintaining reliability and affordability for our customers. If the required technology is not available or not affordable in the future, we may not meet our goals in the desired timeframe. Meeting our clean energy goals may also require accommodation from regulatory agencies. See the discussion under “Electric Resources” for more information on our existing clean electricity sources and efforts to achieve these goals. See “Item 7. Management’s Discussion and Analysis of Financial Condition – Environmental Issues and Contingencies” for further discussion on clean energy, including applicable regulations.

Wildfire Resiliency Plan

We are implementing additional measures to enhance our ability to mitigate the potential for, and impact of, wildfires within our service territories. Building on prevention and response strategies in place for many years, in 2020 we created a comprehensive 10-year Wildfire Resiliency Plan that includes improved defense strategies and operating practices for a more resilient system. This plan is periodically updated and informed by observed experience as well as changes in observed landscape and climatic conditions.

We developed the Wildfire Resiliency Plan through a series of internal workshops, industry research and engagement with state and local fire agencies. Improvements to infrastructure and operational practices were identified as key components to the plan.

These key components are categorized into the following categories: grid hardening, vegetation management, situational awareness, operations and emergency response, and worker and public safety.

We expect to spend $437 million ($124 million of which was spent through 2023) implementing the plan components over the life of the 10-year plan that began in 2020. The IPUC and WUTC approved deferral of certain costs of the wildfire resiliency plan, and we will continue to seek recovery of costs in future rate filings.

See “Note 22 of the Notes to Consolidated Financial Statements” for further discussion on wildfires.