Financial and Operational Developments
(PPL)
RIE Transition Services Agreement Completion
In connection with the acquisition of RIE in 2022, National Grid USA Service Company, Inc., National Grid U.S. and Narragansett Electric entered into a transition services agreement (TSA), pursuant to which the National Grid entities agreed to provide certain transition services to Narragansett Electric to facilitate the transition of the operation of Narragansett Electric to PPL following the acquisition. The TSA was for an initial two-year term and was completed in the third quarter of 2024. TSA costs of $137 million, $228 million, and $123 million were incurred for the years ended December 31, 2024, 2023, and 2022.
Transfer of Certain Credits under the Inflation Reduction Act
The IRS released the final Internal Revenue Code Section 6418 regulations related to the transfer of certain credits under the Inflation Reduction Act. The regulations became effective on July 1, 2024 and did not and are not expected to have a material impact on the financial statements regarding prior or future credit transfers.
Regulatory Requirements
The Registrants cannot predict the impact that future regulatory requirements may have on their financial condition or results of operations.
Environmental Considerations for Coal-Fired Generation
The businesses of LG&E and KU are subject to extensive federal, state and local environmental laws, rules and regulations, including those pertaining to CCRs, GHG, and ELGs. See Notes 7,12 and 18 to the Financial Statements for a discussion of these significant environmental matters. These and other environmental requirements led PPL, LG&E and KU to retire approximately 1,500 MW of coal-fired generating plants in Kentucky since 2010. As part of the long-term generation planning process, LG&E and KU evaluate a range of factors including the impact of potential stricter environmental regulations, fuel price scenarios, the cost of replacement generation, continued operations and major maintenance costs and the risk of major equipment failures in determining when to retire generation assets.
As a result of environmental requirements and aging infrastructure, LG&E has sought and obtained approval to retire two older coal-fired units at the Mill Creek Plant. Mill Creek Unit 1, with 300 MW of capacity, was retired in 2024. Mill Creek Unit 2, with 297 MW of capacity, is expected to be retired in 2027, subject to certain conditions.
On October 4, 2024, LG&E submitted an application related to the retirement of Mill Creek Unit 1, which occurred on December 31, 2024, requesting recovery of associated costs under the RAR rider. On October 28, 2024, the KPSC issued an order to establish a procedural schedule regarding its investigation of the reasonableness of the proposed tariff. The KPSC intends to rule on the matter by February 28, 2025. See Note 7 to the Financial Statements for additional information on the Mill Creek Unit 1 RAR rider application.
FERC Transmission Rate Filing
In 2018, LG&E and KU applied to the FERC requesting elimination of certain on-going waivers and credits to a sub-set of transmission customers relating to the 1998 merger of LG&E's and KU's parent entities and the 2006 withdrawal of LG&E and KU from the Midcontinent Independent System Operator, Inc. (MISO), a regional transmission operator and energy market. The application sought termination of LG&E's and KU's commitment to provide certain Kentucky municipalities mitigation for certain horizontal market power concerns arising out of the 1998 LG&E and KU merger and 2006 MISO withdrawal. The amounts at issue are generally waivers or credits granted to a limited number of Kentucky municipalities for either certain LG&E and KU or MISO transmission charges incurred for transmission service received. In 2019, the FERC granted LG&E's and KU's request to remove the ongoing credits, conditioned upon the implementation by LG&E and KU of a transition mechanism for certain existing power supply arrangements, which was subsequently filed, modified, and approved by the FERC in 2020 and 2021. In 2020, LG&E and KU and other parties filed appeals with the U.S. Court of Appeals - D.C. Circuit (D.C. Circuit Court of Appeals) regarding the FERC's orders on the elimination of the mitigation and required transition mechanism. In August 2022, the D.C. Circuit Court of Appeals issued an order remanding the proceedings back to the FERC. On May 18, 2023, the FERC issued an order on remand reversing its 2019 decision and requiring LG&E and KU to refund credits previously withheld, including under such transition mechanism. LG&E and KU filed a petition for review of the FERC's May 18, 2023 order with the D.C. Circuit Court of Appeals and provided refunds in accordance with the FERC order on December 1, 2023. The FERC issued an order on LG&E's and KU's compliance filing on November 16, 2023, and LG&E and KU filed a petition for review of this November 16, 2023 order on February 14, 2024. The FERC issued the substantive order on rehearing on March 21, 2024, reaffirming its prior decision. Oral argument before the D.C. Circuit Court of Appeals occurred on January 21, 2025. LG&E and KU cannot predict the ultimate outcome of the proceedings or any other post decision process but do not expect the annual impact to have a material effect on their operations or financial condition. LG&E and KU currently receive recovery of certain waivers and credits primarily through base rates increases, provided, however, that increases associated with the FERC's May 18, 2023 order are expected to be subject to future rate proceedings.
(PPL)
FY 2026 Gas ISR Plan
On December 31, 2024, RIE filed its FY 2026 Gas ISR Plan with the RIPUC with a budget that includes $187 million of capital investment spend and up to $15 million of additional contingency plan spend in connection with the PHMSA's potential enactment of regulations during FY 2026 that, if enacted, would significantly alter RIE's leak detection and repair obligations under federal regulations. The Plan also includes proposed spending on curb-to-curb paving of $22 million. A decision from the RIPUC on the Plan is expected by March 31, 2025. RIE cannot predict the outcome of this matter.
FY 2026 Electric ISR Plan
On December 23, 2024, RIE filed its FY 2026 Electric ISR Plan with the RIPUC with a budget that includes $160 million of capital investment spend, $14 million of vegetation operation and maintenance (O&M) expense spend and $1 million of Other O&M spend. In addition, the FY 2026 Electric ISR Plan includes $88 million of capital investment spend for Advanced Metering Functionality (AMF) which, together with the $160 million of capital investment spend, results in total capital investment spend of $248 million. A decision from the RIPUC is expected by March 31, 2025. RIE cannot predict the outcome of this matter.
Advanced Metering Functionality (AMF)
In 2021, RIE filed its Updated AMF Business Case and Grid Modernization Plan (GMP) with the RIPUC in accordance with the Amended Settlement Agreement (ASA) approved by the RIPUC in August 2018, and which among other things, sought approval to deploy smart meters throughout the service territory. After PPL completed the acquisition of RIE, RIE filed a new AMF Business Case with the RIPUC in 2022, consisting of a detailed proposal for full-scale deployment of AMF across its electric service territory.
On September 27, 2023, the RIPUC unanimously approved RIE to deploy an AMF-based metering system for the electric distribution business. RIE is authorized to seek recovery of the approved capital investment through the ISR process with an overall multi-year cap on recovery at approximately $153 million, subject to certain terms, conditions and limitations with respect to the potential offsets and recoverability of certain costs. RIE is required to continue spending even if above the recovery cap, until it achieves the functionalities outlined in the AMF Business Case. RIE filed with the RIPUC for approval of (i) an updated electric Service Quality Plan on December 27, 2023, (ii) additional compliance tariff provisions regarding recovery and updated cost schedules to reflect the RIPUC's decision on December 22, 2023, and (iii) electric and gas tariff advice filings for RIPUC Automatic Meter Reading/AMF meter opt-out tariff provision on September 19, 2024. The RIPUC approved RIE’s revised service quality metrics with certain modifications on August 1, 2024 and October 30, 2024. In addition, the RIPUC approved RIE’s AMR/AMF opt-out tariff provisions for electric and natural gas with modifications on December 19, 2024 for effect January 1, 2025, and approved the proposed updated fees to be assessed at the start of the AMF roll-out. On January 7, 2025, RIE filed compliance tariffs to reflect the RIPUC’s ruling, which they approved at their January 23, 2025 Open Meeting.
Rate Case Proceedings(KU)
On April 30, 2024, KU filed a request with the VSCC for an annual increase in Virginia base electricity rates of approximately $9 million. KU's request is based on an authorized 10.5% return on equity. Subject to regulatory review and approval, new rates would become effective February 1, 2025. On November 6, 2024, KU and VSCC Staff filed a stipulation to resolve the proceeding, with a proposed annual rate increase amount of $8 million and annual authorized returns on equity in a range from 9.5% to 10.5% for various tariff purposes, with no objection from the Office of the Attorney General. A public hearing on the matter was held on November 13, 2024. On December 10, 2024, the Hearing Examiner issued an alternative recommendation to approve the stipulation with a nonmaterial adjustment to the revenue requirement. All parties filed letters in support of the Hearing Examiner’s alternative recommendation. On January 28, 2025, the VSCC issued an order approving the stipulation, including the adjustment recommended by the Hearing Examiner, and the resulting new rates went into effect on February 1, 2025.
DSIC Petition(PPL and PPL Electric)
On April 26, 2024, PPL Electric filed a Petition with the PAPUC requesting that the PAPUC waive PPL Electric's DSIC cap of 5% of billed revenues and increase the maximum allowable DSIC to 9% for bills rendered on or after January 1, 2025. On November 21, 2024, the Administrative Law Judge in the proceeding issued a Recommended Decision recommending the denial of PPL Electric’s DSIC Cap Waiver Petition. PPL Electric filed exceptions to the Recommended Decision on December 11, 2024. Several of the other parties filed Reply Exceptions on December 23, 2024. The Administrative Law Judge's Recommended Decision and the Exceptions and Reply Exceptions are currently before the PAPUC for a final order. PPL Electric cannot predict the timing or outcome of that decision.
Long-Term Infrastructure Improvement Plan Petition (LTIIP)(PPL and PPL Electric)
On January 17, 2024, PPL Electric filed a petition with the PAPUC seeking to modify its LTIIP, which covers the period from 2023 through 2027, to increase the total projected capital spending for existing LTIIP programs and to add a new LTIIP program related to predictive failure technology. On July 11, 2024, the PAPUC approved the petition in part, allowing for an increase of $203 million for existing LTIIP programs. The proposed new LTIIP program was determined not to be eligible for recovery under the DSIC. However, investments in such programs are potentially recoverable through a base rate proceeding.
Artificial Intelligence (AI) Governance (All Registrants)
To leverage potential benefits of AI, PPL management has established an AI Governance committee, with oversight from the Chief Technology and Innovation Officer and the Chief Legal Officer, which assesses benefits and risks associated with AI. The governance committee is a cross-functional team with leadership representation from Technology, Security, Audit, Legal, Operations, Human Resources and Data and AI. The governance committee reviews potential AI solutions using an intake process which involves risk and benefit assessment, data security and privacy considerations, and ensures that all solutions are compliant with PPL technology and security standards.