A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2024 · Filed Feb 27, 2025

EIX$59.37-2.5%Stored close · as of Nov 6, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

Rate Regulated Enterprises

Nature of Estimate Required. SCE follows the accounting principles for rate-regulated enterprises which are required for entities whose rates are set by regulators at levels intended to recover the estimated costs of providing service, plus a return on net investment, or rate base. Regulators may also impose penalties or grant incentives. Due to timing and other differences in the collection of revenue, these accounting principles allow a cost that would otherwise be charged as an expense by an unregulated entity to be capitalized as a regulatory asset if it is probable that such cost is recoverable through future rates; conversely the accounting principles require creation of a regulatory liability for amounts collected in rates to recover costs expected to be incurred in the future or amounts collected in excess of costs incurred and refundable to customers. In addition, SCE recognizes revenue and regulatory assets from alternative revenue programs, which enables the utility to adjust future rates in response to past activities or completed events, if certain criteria are met.

Accounting principles for rate-regulated enterprises also require recognition of an impairment loss if it becomes probable that the regulated utility will abandon a plant investment or the cost of a recently completed plant will be disallowed for ratemaking purposes, and a reasonable estimate of the amount of the disallowance can be made.

Key Assumptions and Approach Used. SCE's management assesses at the end of each reporting period whether regulatory assets are probable of future recovery by considering factors such as the current regulatory environment, the issuance of rate orders on recovery of the specific or a similar incurred cost to SCE or other rate-regulated entities, and other factors that would indicate that the regulator will treat an incurred cost as allowable for ratemaking purposes. Using these factors, management has determined that existing regulatory assets are probable of future recovery or settlement, and regulatory liabilities are properly identified. This determination reflects the current regulatory climate and is subject to change in the future. SCE also considers whether any plant investments are probable of abandonment or disallowance.

Effect if Different Assumptions Used. Significant management judgment is required to evaluate the anticipated recovery of regulatory assets and plant investments, the recognition of incentives and revenue subject to refund, as well as the anticipated cost of regulatory liabilities or penalties. If future recovery of costs ceases to be probable, all or part of the regulatory assets and/or plant investments would have to be written off against current period earnings, and additional regulatory liabilities would have to be recognized. At December 31, 2024, the consolidated balance sheets included regulatory assets of $11.6 billion and regulatory liabilities of $11.5 billion. If different judgments were reached on recovery of costs and timing of income recognition, SCE's earnings may vary from the amounts reported.

Application to Southern California Wildfires

Application to pre-AB 1054 fires

Regulatory recovery of SCE's losses realized in connection with the 2017/2018 Wildfire/Mudslide Events in excess of available insurance is subject to approval by regulators. Under accounting standards for rate-regulated enterprises, SCE defers costs as regulatory assets in the period it concludes that such costs are probable of future recovery in electric rates.

SCE utilizes objectively determinable evidence to form its view on probability of future recovery. The only directly comparable precedent, in which a California investor-owned utility sought recovery for uninsured wildfire claims related costs and the CPUC made a prudency determination, is SDG&E's requests for cost recovery related to 2007 wildfire activity. The FERC allowed recovery of all FERC-jurisdictional wildfire claims related costs, while the CPUC rejected recovery of all CPUC-jurisdictional wildfire claims related costs based on a determination that SDG&E did not meet the CPUC's prudency standard.

In January 2025, the CPUC approved the TKM Settlement Agreement and closed the proceeding. However, the CPUC did not make a determination regarding SCE's prudency when it approved the TKM Settlement Agreement. Therefore, notwithstanding CPUC approval of the TKM Settlement Agreement, SCE believes that the CPUC's interpretation and application of the prudency standard to SDG&E continues to create substantial uncertainty regarding how that standard will be applied to an investor-owned utility in wildfire cost-recovery proceedings for fires ignited prior to July 12, 2019. Consequently, SCE is unable to estimate the uninsured CPUC-jurisdictional claims related costs related to the Woolsey Fire or Creek Fire, both pre-AB 1054 events, that are probable of future recovery, and will not record a regulatory asset for recoveries related to the Woolsey Fire or Creek Fire in connection with the approval of the TKM Settlement Agreement. SCE will continue to evaluate the facts and circumstances of the pre-AB 1054 cost recovery proceeding to determine if and when a regulatory asset for pre-AB 1054 events may be recorded.

Through the operation of its FERC Formula Rate, and based upon the precedent established in SDG&E's recovery of FERC-jurisdictional wildfire-related costs, SCE believes it is probable it will recover its FERC-jurisdictional wildfire and mudslide related costs and has recorded total expected recoveries within the FERC balancing account.

Application to post-AB-1054 Other Wildfire Events

Management judgment is required to assess the probability of recovery of SCE's losses realized, in excess of available insurance, in connection with wildfires ignited after the adoption of AB 1054 in July 2019.

The CPUC and FERC may not allow SCE to recover uninsured losses through electric rates if it is determined that such losses were not reasonably or prudently incurred. On July 12, 2019, AB 1054 clarified that the CPUC must allow recovery of costs and expenses arising from a covered wildfire if the utility's conduct related to the ignition was consistent with actions that a reasonable utility would have undertaken in good faith under similar circumstances, at the relevant point in time, and based on the information available at that time. Further, utilities with a valid safety certification at the time of the relevant wildfire will be presumed to have acted prudently related to a wildfire ignition unless a party in the cost recovery proceeding creates "serious doubt" as to the reasonableness of the utility's conduct, at which time, the burden shifts back to the utility to dispel that doubt and prove its conduct was prudent. The serious doubt standard in AB 1054 is modeled after the FERC cost recovery standard. SCE evaluates the probability of recovery of costs related to the Other Wildfire Events that ignited after the adoption of AB 1054 in the context of the prudency standard laid out by AB 1054 above, including how the FERC applies the serious doubt standard. SCE’s evaluation also relies on its status as a holder of a valid safety certification, facts and other evidence known to date related to the ignition, and any regulatory decisions illustrating the interpretation and/or application of the prudency framework under AB 1054, which as of December 31, 2024, has not been applied by the CPUC to an actual cost recovery application filed by any California investor-owned utility. SCE also considers which costs are eligible for recovery based on precedent from other CPUC cost recovery proceedings. Management's assessment of the probability of recovery may change, related to changes in any of these factors in the future.

See "Notes to Consolidated Financial Statements—Note 12. Commitments and Contingencies—Contingencies—Southern California Wildfires and Mudslides" for further discussion of regulatory assets recorded for wildfire as of December 31, 2024.