Skip to main content

SOUTHERN CALIFORNIA EDISON Co

For the period ended Dec 31, 2023. Filed Feb 22, 2024.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2023 · Filed Feb 22, 2024

EIX$60.20+0.1%Stored close · as of Nov 10, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

Decommissioning of San Onofre

The decommissioning of a nuclear plant requires the management of three related activities: radiological decommissioning, non-radiological decommissioning and the management of spent nuclear fuel. SCE is the operating agent of San Onofre and has engaged the DGC to undertake a significant scope of decommissioning activities for Units 1, 2 and 3 at San Onofre. The decommissioning of San Onofre is expected to take many years. SCE funds decommissioning costs, including costs associated with storing spent nuclear fuel, with assets that are currently held in nuclear decommissioning trusts.

Under federal law, the U.S. Department of Energy ("DOE") is responsible for the selection and construction of a facility for the permanent disposal of spent nuclear fuel and high-level radioactive waste. The DOE has not met its contractual obligation to accept spent nuclear fuel. Extended delays by the DOE have led to the construction of costly alternatives and associated siting and environmental issues. Two Independent Spent Fuel Storage Installations ("ISFSI") store nuclear fuel onsite at San Onofre. The first primarily stores nuclear fuel from Unit 1 ("ISFSI 1") and the second stores nuclear fuel from Units 2 and 3 ("ISFSI 2").

SCE's Coastal Development Permits, the principal discretionary permits required for major decommissioning activities, extend through 2035.

Decommissioning of San Onofre Unit 1 began in 1999 and the transfer of spent nuclear fuel from Unit 1 to dry cask storage in ISFSI 1 was completed in 2005. Major decommissioning work for Unit 1 has been completed except for certain underground work.

Decommissioning of San Onofre Units 2 and 3 began in June 2013 and the transfer of spent nuclear fuel from San Onofre Units 2 and 3 to dry cask storage in the two ISFSIs was completed in August 2020. In August 2020, SCE commenced, and is currently conducting, major decommissioning activities in accordance with the terms of the Coastal Developmental Permit for San Onofre Units 2 and 3.

In 2021, SCE updated its decommissioning cost estimate for decommissioning activities to be completed at San Onofre Units 2 and 3 to $3.4 billion (SCE share is $2.6 billion) in 2021 dollars. The decommissioning cost estimate included costs through the expected decommissioning completion date, currently estimated to be in 2053 for San Onofre Units 2 and 3. SCE requested approval of its updated decommissioning cost estimate from the CPUC in February 2022 as part of its 2021 NDCTP filing. Decommissioning cost estimates are subject to a number of uncertainties including the cost and timing of nuclear waste disposal, the time it will take to obtain required permits, cost of removal of property, site remediation costs, as well as a number of other assumptions and estimates, including when the federal government will provide for either interim or permanent off-site storage of spent nuclear fuel enabling the removal and transport of spent fuel canisters from the San Onofre site, as to which there can be no assurance. Cost estimates are subject to change as decommissioning proceeds and such changes may be material.

SCE's share of the San Onofre Units 2 and 3 decommissioning costs recorded during 2023 and 2022 were $226 million (in 2023 dollars) and $187 million (in 2022 dollars), respectively. The CPUC conducts a reasonableness review of recorded decommissioning costs in NDCTPs.

In the 2021 NDCTP, filed in February 2022, SCE requested reasonableness review of approximately $570 million (SCE share in 2022 dollars) of recorded San Onofre Units 2 and 3 decommissioning costs incurred during the period 2018 to

  1. In May 2023, SCE entered into a settlement with the relevant intervenors under which, subject to CPUC approval, SCE agreed to a disallowance in the 2021 NDCTP of approximately $30 million. SCE has accrued for this disallowance.

SCE had nuclear decommissioning trust funds for San Onofre Units 2 and 3 of $2.2 billion at both December 31, 2023 and 2022. Based upon the resolution of a number of uncertainties, including the uncertainties of decommissioning discussed above, the financial performance of the nuclear decommissioning trust fund investments, as well as the resolution of a number of other assumptions and estimates, additional contributions to the nuclear decommissioning trust's funds may be required. If additional contributions to the nuclear decommissioning trust funds become necessary, SCE will seek recovery of additional contributions to the decommissioning trust through electric rates and any such recovery will be subject to a reasonableness review by the CPUC. Cost increases resulting from contractual disputes, delays in performance by the contractor, elevated levels of inflation, or permitting delays, among other things, could cause SCE to materially overrun the decommissioning cost estimate and could materially impact the sufficiency of trust funds.

In December 2023, the CPUC approved disbursements from SCE's nuclear decommissioning trusts to cover forecasted 2024 decommissioning costs for San Onofre Units 2 and 3, of which SCE's share is approximately $300 million in 2024 dollars.