Capital Investment Plan
Major Transmission Projects
A summary of SCE's most significant transmission and substation construction projects during the next two years is presented below. The timing of the projects below is subject to timely receipt of permitting, licensing and regulatory approvals.
| · · · · · · · · · · · | |||||||
|---|---|---|---|---|---|---|---|
| | | | Direct | | | | |
| · · Project · · Expenditures · · Inception to Date · · Scheduled In- · | |||||||
| Project Name · Lifecycle Phase · (in millions)1 · (in millions)1 · Service Date | |||||||
| Riverside Transmission Reliability2 | Licensing | | 584 | | 34 | 2028 | |
| Alberhill System3 | Licensing | | 472 | | 47 | 2029 | |
| Eldorado-Lugo-Mohave Upgrade | Construction | | 383 | | 247 | 2024 | |
| 1 | Direct expenditures include direct labor, land and contract costs incurred for the respective projects and exclude overhead costs that are included in the capital expenditures forecast discussed in "Management Overview—Capital Program." |
| 2 | Expenditures and in-service date are based on CPUC approved plans and will likely be impacted by the timing of CPUC determination of the City of Norco’s petition for modification ("PFM") and any changes to those plans required by Riverside City Council ("RCC"). |
| 3 | In June 2023, SCE filed an amended application for a certificate of public convenience and necessity ("CPCN") with technical design modifications and engineering refinements to the proposed project that decreases project costs and reduces GHG emissions. Accordingly, the direct expenditures of the project are estimated to be reduced from $486 million to $472 million. SCE is unable to predict the timing of a final CPUC decision and the final project costs for the Alberhill System Project. |
Riverside Transmission Reliability Project
The Riverside Transmission Reliability Project is a joint project between SCE and Riverside Public Utilities ("RPU"), the municipal utility department of the City of Riverside. While RPU will be responsible for constructing some of the project's facilities within Riverside, SCE's portion of the project consists of constructing upgrades to its system, including a new 230 kV substation; certain interconnection and telecommunication facilities and overhead transmission
lines in the cities of Riverside, Jurupa Valley and Norco and in portions of unincorporated Riverside County. In May 2022, the RCC voted to investigate alternatives to the CPUC approved project. Consequently, SCE suspended all major activities on the project. In January 2023, the RCC voted to establish a working group to pursue funding for additional undergrounding. On October 2, 2023, the Cityof Norco filed a PFM to modify the CPUC decision approving the project and reopen the record to reconsider full undergrounding. In November 2023, SCE filed a response opposing the PFM.
Alberhill System Project
The Alberhill System Project consists of constructing a new 500 kV substation, two 500 kV transmission lines to connect the proposed substation to the existing Serrano-Valley 500 kV transmission line, telecommunication equipment and subtransmission lines in western Riverside County. The project was designed to meet long-term forecasted electrical demand in the proposed Alberhill System Project area and to increase electrical system reliability and resiliency. In April 2018 and July 2018, the CPUC issued a proposed decision and an alternate proposed decision, both denying SCE's ability to construct the Alberhill System Project based on a perceived lack of need. SCE filed comments on both proposed decisions requesting that the CPUC grant the CPCN for the Alberhill System Project. In August 2018, the CPUC issued a decision that did not deny or approve the Alberhill System Project but directed SCE to submit supplemental information on the Alberhill System Project including but not limited to a load forecast and cost benefit analysis of several alternatives to the proposed project. Ongoing capital spending has been deferred as a result of the CPUC request for additional information. In January 2020, SCE submitted a supplemental analysis to the CPUC for the Alberhill System Project including several alternatives to the proposed project as well as an update to the original project cost. A final decision on the Alberhill System Project remains pending. In June 2023, SCE filed an amended CPCN with technical design modifications and engineering refinements to the proposed project that decrease project costs and reduce GHG emissions. Given the uncertainty associated with the resolution of the permitting process, potential revisions to the project have not been reflected in total direct expenditures. SCE continues to believe a system solution is needed for the project area but is unable to predict the timing of a final CPUC decision in connection with the Alberhill System Project proceeding.
Approximately 48% of the Alberhill System Project costs spent to date would be subject to recovery through CPUC revenue and 52% through FERC revenue. In October 2017, SCE obtained approval from the FERC for abandoned plant treatment for the Alberhill System Project, which allows SCE to seek recovery of 100% of all prudently incurred costs after the approval date and 50% of prudently incurred costs prior to the approval date. Excluding land costs, which may be recovered through sale to a third party, SCE has incurred approximately $62 million of capital expenditures, including overhead costs, of which approximately $44 million may not be recoverable if the project is cancelled as of December 31, 2023.
Eldorado-Lugo-Mohave Upgrade Project
The Eldorado-Lugo-Mohave Upgrade Project will increase capacity on existing transmission lines to allow additional renewable energy to flow from Nevada to southern California. The project would modify SCE's existing Eldorado, Lugo, and Mohave electrical substations to accommodate the increased power flows from Nevada to southern California; increase the power flow through the existing 500 kV transmission lines by constructing two new capacitors along the lines; raise transmission tower heights to meet ground clearance requirements; and install fiber optics on the transmission lines to provide communications between existing SCE substations. In August 2020, the CPUC approved the CPCN for the project.
Construction for the project began in November 2020. The total costs for the Eldorado-Lugo-Mohave Upgrade Project are expected to exceed amounts currently approved in the CPCN granted by the CPUC due to delays in regulatory approvals, contractor performance issues, supply chain constraints, COVID-19 impacts and the availability of CAISO outage windows. In May 2023, SCE filed a Petition for Modification of the decision that approved the project to increase the maximum reasonable and prudent cost for the project, which increased the direct expenditures from $247 million to
$319 million. SCE expects the project to be in service in 2024. Additional work after the in-service date is also required to mitigate the impact of the project on nearby natural gas transmission lines. Current estimation of the additional work is approximately $64 million. A further Petition for Modification is expected to be filed before the authorized spending is exceeded.
Utility Owned Storage Projects
In October 2021, SCE contracted with Ameresco, Inc. ("Ameresco") for the construction of utility owned energy storage projects at three sites in SCE's service territory with an aggregate capacity of 537.5 MW, consisting of a 225 MW project, a 200 MW project and a 112.5 MW project, and an in-service date of August 1, 2022. Ameresco has advised SCE that it currently expects all three projects to be in-service prior to June 2024.
In April 2022, SCE received aforce majeure event notice from Ameresco in which Ameresco asserted that both manufacturing delays related to COVID-19 shut-downs in China and new shipping restrictions imposed by Chinese governmental authorities were then impacting the supply of batteries from China necessary for timely completion of the projects. Ameresco subsequently supplemented itsforce majeure notice noting additional supply chain issues related to COVID-19. Permitting delays and engineering issues and certain changes requested by SCE also impacted the projects in 2022. SCE expects to receive in aggregate approximately $270 million of tax credits available under the IRA for all three projects, which will accrue to the benefit of its customers. In January 2023, SCE received aforce majeure event notice from Ameresco in which Ameresco asserted that severe winter storms in Southern California had impacted the timely completion of the projects.
In April 2023, Ameresco discovered damage to some of the equipment at the 225 MW project. Ameresco has sent SCE a notice of potentialforce majeure event and has concluded that the damage was caused by soil heave and that the soil heave was caused by extreme rainstorms at the project site in the winter of 2022 – 2023. Ameresco is performing corrective action in response to the damage discovered in 2023.
SCE is continuing to evaluate theforce majeure event notices and is awaiting additional information from Ameresco on the underlying events. If there is a validforce majeureevent under the contracts with Ameresco, subject to certain conditions, the project schedules and any related triggers of liquidated damages may be extended, and the contract prices may be increased to account for the impact of theforce majeure event. Because Ameresco did not achieve an in-service date of August 1, 2022, SCE is entitled to liquidated damages under the terms of the contracts subject to any relief Ameresco may be entitled to under the contracts, including any relief for any validforce majeure events. Once triggered, liquidated damages accrue daily for up to 60 days up to a maximum of $89 million in aggregate for all three projects.
Subject to reductions for any liquidated damages SCE is paid, SCE currently expects these storage projects to result in $1.0 billion of capital expenditures. In December 2021, the CPUC approved recovery of these expenditures and establishment of a balancing account for the associated revenue requirement, which have been reflected in rates beginning in the first quarter of 2022. Authorized revenue requirements will be included in the annual ERRA review proceeding and can only be disallowed upon a finding that SCE failed to prudently administer the contracts.
Ameresco has obtained surety bonds to secure its obligations to complete the construction of the projects, and is also required to obtain surety bonds or letters of credit after completion of the projects to secure its performance obligations, including its warranty obligations. If Ameresco is unable to fulfill its obligations and the amounts available under any surety bonds or letters of credit are insufficient or the issuer of any such surety bonds or letters of credit disputes coverage or otherwise does not perform or pay for the performance of Ameresco’s obligations, SCE will incur additional costs beyond its contractual obligations.
Other Capital Investment Projects and Programs