General

Williams is an energy company committed to being the leader in providing infrastructure that safely delivers natural gas products to reliably fuel the clean energy economy. Its operations are located in the United States.

Williams’ interstate natural gas pipeline strategy is to create value by maximizing the utilization of its pipeline capacity by providing high-quality, low-cost transportation of natural gas to large and growing markets. Williams’ gas pipeline businesses’ interstate transmission and storage activities are subject to regulation by the FERC. As such, Williams’ rates and charges for the transportation of natural gas in interstate commerce; the extension, expansion, or abandonment of jurisdictional facilities; and accounting, among other things, are subject to regulation. The rates are established primarily through the FERC’s ratemaking process, but Williams may also negotiate rates with its customers pursuant to the terms of its tariffs and FERC policy. Changes in commodity prices and volumes transported have limited near-term impact on these revenues because the majority of the cost of service is recovered through firm capacity reservation charges in transportation rates.

The ongoing strategy of Williams’ midstream operations is to safely and reliably operate large-scale midstream infrastructure where its assets can be fully utilized and drive low per-unit costs. Williams focuses on consistently attracting new business by providing highly reliable service to its customers. These services include natural gas gathering and processing, treating, compression and storage; NGL fractionation, transportation and storage; and crude oil production handling and transportation, as well as marketing services for NGL, crude oil, and natural gas.

Consistent with the manner in which Williams’ CODM evaluates performance and allocates resources, Williams’ operations are conducted, managed, and presented within the following reportable segments: Transmission, Power & Gulf; Northeast G&P; West; and Gas & NGL Marketing Services (See Note 1 – Description of Business and Basis of Presentation). All remaining business activities, including upstream operations and corporate activities, are included in Other.

Unless indicated otherwise, the following discussion and analysis of results of operations and financial condition and liquidity relates to Williams’ current continuing operations and should be read in conjunction with the financial statements and combined notes thereto of this Form 10-Q and the Annual Report on Form 10-K for the year ended December 31, 2025, as filed with the SEC on February 24, 2026.

Dividends

In September 2026, Williams paid a regular quarterly dividend of $0.525 per share.

Overview of Nine Months Ended September 30, 2026

Net income (loss) attributable to The Williams Companies, Inc. for the nine months ended September 30, 2026, increased $508 million compared to the nine months ended September 30, 2025. Further discussion of the results is found in this report in the Results of Operations.

Recent Developments

Momentum Acquisition

On September 3, 2026, Williams closed on the acquisition of Momentum for total consideration of approximately $5.1 billion. Momentum’s assets in the Haynesville Shale region include 6 Bcf/d of gathering capacity and 4 Bcf/d of pipeline capacity. See Note 3 – Acquisitions and Divestitures.

Sale of Partial Interest in Pantheon

In July 2026, Williams sold a noncontrolling interest in five power projects, Socrates, Apollo, Aquila, Socrates the Younger, and Neo, to an investor in exchange for $5.34 billion of committed capital. The initial contribution of $3.74 billion was received in July 2026 and the remaining committed capital is expected to be received through first quarter of 2027, including $1 billion received in October 2026. See Note 1 – Description of Business and Basis of Presentation.

Sale of Permian Interests

Consolidated Permian Gathering Assets

In August 2026, Williams completed the sale of certain gas gathering assets in the Permian basin within its West segment for total consideration of $139 million, resulting in the recognition of an $83 million gain in the third quarter of 2026. See Note 3 – Acquisitions and Divestitures.

Brazos Permian II Equity-Method Investment

In June 2026, Williams completed the sale of an equity-method investment in Brazos Permian II, LLC within its West segment for total consideration of $143 million, resulting in the recognition of a $127 million gain reflected in the second quarter of 2026. See Note 3 – Acquisitions and Divestitures.

Transco FERC Rate Case Filing

On August 30, 2024, Transco filed a general rate case with the FERC for an overall increase in rates and to comply with the terms of the settlement of its prior rate case. On September 30, 2024, the FERC issued an order accepting and suspending Transco’s general rate filing to be effective March 1, 2025, subject to refund and the outcome of hearing procedures established by the FERC. The order also accepted rate decreases for certain services to be effective as of October 1, 2024. During the third quarter of 2025, Transco reached an agreement in principle with its customers and the other participants to settle all aspects of the rate case and accrued a related liability for rate refunds. Transco filed with the FERC in October 2025 for approval of the settlement. On December 30, 2025, the FERC approved the settlement which became effective March 1, 2026. The refunds were paid in April 2026.

Sale of Mid-Continent Gathering Assets

In February 2026, Williams closed on the sale of certain gas gathering assets in the Mid-Continent region. These operations were designated as held for sale at December 31, 2025 and an impairment, within the West segment, was recognized. See Note 8 – Fair Value Measurements and Guarantees.

Sale of South Mansfield Upstream Interests

In January 2026, Williams closed on the sale of its interests in certain upstream ventures in the South Mansfield area of the Haynesville Shale region, included in Other, for consideration of $398 million with additional contingent consideration to possibly be received through 2029. Upon closing, Williams recognized a gain of $182 million in the first quarter of 2026 and an additional gain of $12 million in the second quarter of 2026. See Note 3 – Acquisitions and Divestitures.

Expansion Project Updates

Expansion projects placed into service for the current year are described below. Ongoing major expansion projects are discussed later in Company Outlook.

Gillis West

This project involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from receipt points in Louisiana to delivery points in Texas. Transco placed the project into service in late October 2026. The project is expected to increase capacity by 115 Mdth/d.

Ryckman Creek Lateral

This project involves an expansion of NWP’s existing natural gas transmission system to provide incremental firm transportation capacity from a receipt point in northeast Oregon to multiple delivery points in southwest Wyoming. NWP placed the project into service in late October 2026. The project is expected to increase contracted capacity by 50 Mdth/d.

Huntingdon Connector

This project involves an expansion of NWP’s existing natural gas transmission system that will provide year-round transportation capacity from the Sumas receipt point to various delivery points in Washington. NWP placed the project into service in late October 2026. The project is expected to increase capacity by 78 Mdth/d.

Power - Socrates

The project consists of the Socrates North and South power generation facilities and associated gas pipeline infrastructure in New Albany, Ohio, which together have an expected 556 MW of capacity. Socrates South was placed into service in late July 2026. Socrates North remains under construction and is expected to be placed into service later in the fourth quarter of 2026. The project is supported by a 10‑year, primarily fixed‑price power purchase agreement, with an option for the customer to extend the term of the agreement. Williams has received necessary approvals from the Ohio Power Siting Board.

Naughton Coal-to-Gas Conversion

The project involves an expansion of NWP’s existing natural gas transmission system to provide year-round transportation capacity to a power plant in southwest Wyoming. NWP placed the project into service in April 2026, increasing NWP’s contracted capacity by 98 Mdth/d.