NORTHWEST PIPELINE LLC
For the period ended Mar 31, 2026. Filed May 4, 2026.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Mar 31, 2026 · Filed May 4, 2026
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Company Outlook
Williams’ strategy is to provide a large-scale, reliable, and clean energy infrastructure designed to maximize the opportunities created by the vast supply of natural gas and natural gas products that exists in the United States. Williams accomplishes this by connecting the growing demand for cleaner fuels and feedstocks with our major positions in the premier natural gas and natural gas products supply basins. Williams continues to maintain a strong commitment to safety, environmental stewardship including seeking opportunities for renewable energy ventures, operational excellence, and customer satisfaction. Williams believes that accomplishing these goals will position it to deliver safe, reliable, clean energy services to its customers and an attractive return to shareholders. Williams’ business plan for 2026 includes a continued focus on earnings and cash flow growth.
In 2026, Williams’ operating results are expected to benefit from the continued growth in the Transmission, Power & Gulf segment, primarily reflecting the impacts of the Socrates Power Innovation project, as well as numerous expansion projects at Transco and the Gulf of America. Growth in 2026 will benefit from a full year of the Louisiana Energy Gateway expansion project as well as expected increases in Haynesville Shale volumes.
Additionally, Williams expects higher gathering and processing results in the Northeast. These increases are partially offset by the divestiture of the South Mansfield upstream joint venture, and lower expected Eagle Ford results in our West segment which relate to contractual step-downs in minimum volume commitments.
Williams seeks to maintain a strong financial position and liquidity, as well as manage a diversified portfolio of safe, clean, and reliable energy infrastructure assets that continue to serve key growth markets and supply basins in the United States. Williams’ growth capital and investment expenditures in 2026 are expected to range from $7.0 billion to $7.6 billion, excluding acquisitions and certain long-lead time equipment for power innovation projects which are backed by reimbursement from the customer if the equipment order is cancelled. Growth capital spending in 2026 primarily includes the Power Innovation projects, Transco expansions, all of which are fully contracted with firm transportation agreements, projects supporting growth in the Haynesville Shale basin, and projects supporting the Northeast G&P business. Williams is investing capital in the Louisiana LNG and Driftwood Pipeline projects, as well as the development of its Wamsutter upstream oil and gas properties. In addition to growth capital and investment expenditures, Williams also remains committed to projects that maintain its assets for safe and reliable operations, as well as projects that reduce emissions, and meet legal, regulatory, and/or contractual commitments.
Potential risks and obstacles that could impact the execution of Williams’ plan include:
A global recession, which could result in downturns in financial markets and commodity prices, as well as impact demand for natural gas and related products;
Opposition to, and regulations affecting, our infrastructure projects, including the risk of delay or denial in permits and approvals needed for our projects;
Counterparty credit and performance risk;
Unexpected significant increases in capital expenditures or delays in capital project execution, including increases from inflation or delays caused by supply chain disruptions;
Unexpected changes in customer drilling and production activities, which could negatively impact gathering and processing volumes;
Lower than anticipated demand for natural gas and natural gas products which could result in lower-than-expected volumes, energy commodity prices, and margins;
General economic, financial markets, or industry downturns, including increased inflation, interest rates, or tariffs;
Physical damages to facilities, including damage to offshore facilities by weather-related events;
Other risks set forth under Part I, Item 1A. Risk Factors in the Annual Report on Form 10-K for the year ended December 31, 2025, as filed with the SEC on February 24, 2026, as may be supplemented by disclosure in Part II, Item 1A. Risk Factors in subsequent Quarterly Reports on Form 10‑Q.
Expansion Projects
Williams’ ongoing major expansion projects include the following:
Gillis West
In April 2026, Transco filed a prior notice application with the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from receipt points in Louisiana to delivery points in Texas. Transco plans to place the project into service as early as the fourth quarter of 2026, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 115 Mdth/d.
Southeast Supply Enhancement
In January 2026, Transco received FERC approval for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from receipt points in Virginia to delivery points in Virginia, North Carolina, South Carolina, Georgia, and Alabama. Transco plans to place the project into service as early as the third quarter of 2027, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 1,597 Mdth/d.
Northeast Supply Enhancement
In August 2025, the FERC issued an order granting Transco’s petition for reissuance of the certificate authorization for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from Transco’s Compressor Station 195 in Pennsylvania to the Rockaway Delivery Lateral transfer point in New York. In October and November 2025, Transco’s applications for Clean Water Act and related permits with the states of Pennsylvania, New York and New Jersey were approved. In August 2025, Transco executed precedent agreements with customers subscribing to all of the capacity under the project. Transco plans to place the project into service as early as the fourth quarter of 2027, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 400 Mdth⁄d.
Line 200
In April 2023, Driftwood received FERC approval for Line 200, which will connect multiple pipelines to the Louisiana LNG facility. Williams will be the operator of the pipeline and plans to place the project into service as early as the second quarter of 2028. The pipeline has an expected capacity of 3,100 Mdth/d.
Pine Prairie Phase IV Expansion
In August 2025, Williams filed a certificate application with the FERC for the project, which will involve an expansion of storage capacity and the injection and withdrawal capabilities of one of its existing storage facilities in the Gulf Coast region. Williams plans to place the project into service during the fourth quarter of 2028, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase working gas storage capacity by 10 Bcf.
Dalton Lateral II
Transco plans to file a certificate application for the project with the FERC in 2027. The project involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from Transco’s main line near existing Station 115 to an existing power plant in Georgia. Transco plans to place the project into service as early as the fourth quarter of 2029, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity up to 460 Mdth/d.
Power Express
Transco plans to file an application with the FERC as early as the second quarter 2027 for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity in Virginia. Transco plans to place the project into service as early as the third quarter of 2030, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 750 Mdth/d.
Ryckman Creek Loop
In February 2026, NWP received FERC approval for the project, which involves an expansion of NWP’s existing natural gas transmission system to provide incremental firm transportation capacity from a receipt point in northeast Oregon to multiple delivery points in southwest Wyoming. NWP plans to place the project into service as early as the fourth quarter of 2026. The project is expected to increase capacity by 50 Mdth/d.
Huntingdon Connector
In February 2026, NWP filed a prior notice application with the FERC for the project, which involves an expansion of NWP’s existing natural gas transmission system that will provide year-round transportation capacity from the Sumas receipt point to various delivery points in Washington. NWP plans to place the project into service during the fourth quarter of 2026, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 78 Mdth/d.
Wild Trail
In March 2026, NWP received FERC approval for the project, which involves an expansion of NWP’s existing natural gas transmission system that will provide year-round transportation capacity from the White River Hub receipt point in western Colorado to various delivery points in southwest Wyoming and southern Colorado. The Wild Trail project is fully subscribed by an affiliate of NWP. NWP plans to place the project into service during the fourth quarter of 2027, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 83 Mdth/d.
Kelso-Beaver Reliability
In November 2025, NWP received FERC approval for the project, which will provide year-round transportation capacity to various receipt and delivery points in Oregon. NWP plans to place the project into service during the fourth quarter of 2028, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 183 Mdth/d. In May 2026, NWP purchased the 17-mile Kelso-Beaver pipeline, a key milestone for this project.
Silver Spur
NWP plans to file an application with the FERC as early as the second half of 2027 for the project, which will provide year-round transportation capacity from the Rockies Supply hub at Opal, Wyoming to various delivery points in Idaho. NWP plans to place the project into service as early as the first half of 2030, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 275 Mdth/d.
Power Innovation
Socrates
The Socrates project involves the construction of the Socrates North and South power generation facilities and associated gas pipeline infrastructure in New Albany, Ohio, which together have an expected 556 MW of capacity. The project is backed by a 10 year, primarily fixed-price power purchase agreement, with an option for the customer to extend the term of the agreement. Williams has received necessary approvals from the Ohio Power Siting Board. Williams plans to place the project into service in the third and fourth quarter of 2026.
Additional Projects
Williams has agreed to provide committed power generation and associated gas pipeline infrastructure for four additional Power Innovation projects, Apollo, Aquila, Socrates the Younger, and Neo. The projects are backed by primarily fixed-price power purchase agreements, with options for the customer to extend the term of the agreements. The Apollo project, in Ohio, has a term of 12.5 years, and Williams expects the project to be placed into service in the second half of 2027 and to provide 490 MW of capacity. The Aquila project, in Utah, also has a term of 12.5 years, and Williams expects the project to be placed into service in the second half of 2027 and the first half of 2028 and to provide 520 MW of capacity. The Socrates the Younger project, in Ohio, has a term of 10 years, and Williams expects the project to be placed into service the second half of 2028 and to provide 340 MW of capacity. The Neo project, in Ohio, has a term of 12.5 years, and Williams expects the project to be placed into service in the second half of 2028 and to provide 682 MW of capacity. All expected in-service dates assume timely receipt of permits.
West
Dorne
Williams will construct and operate a greenfield treating and dehydration facility with a capacity of 400 MMcf/d. This project is expected to be placed into service in the third quarter of 2027.
Other
Lakeland Solar Project
Williams is constructing and will operate a 75 MW alternating current solar power facility interconnecting with Lakeland Electric in Florida. This project is expected to be placed in service in the fourth quarter of 2026.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.