A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Sep 30, 2025 · Filed Nov 3, 2025

WMB$66.45+3.7%Stored close · as of Nov 9, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

General

Williams is an energy company committed to being the leader in providing infrastructure that safely delivers natural gas products to reliably fuel the clean energy economy. Its operations are located in the United States.

Williams’ interstate natural gas pipeline strategy is to create value by maximizing the utilization of its pipeline capacity by providing high-quality, low-cost transportation of natural gas to large and growing markets. Williams’ gas pipeline businesses’ interstate transmission and storage activities are subject to regulation by the FERC. As such, Williams’ rates and charges for the transportation of natural gas in interstate commerce, and the extension, expansion, or abandonment of jurisdictional facilities and accounting, among other things, are subject to regulation. The rates are established primarily through the FERC’s ratemaking process, but Williams may also negotiate rates with its customers pursuant to the terms of its tariffs and FERC policy. Changes in commodity prices and volumes transported have limited near-term impact on these revenues because the majority of the cost of service is recovered through firm capacity reservation charges in transportation rates.

The ongoing strategy of Williams’ midstream operations is to safely and reliably operate large-scale midstream infrastructure where its assets can be fully utilized and drive low per-unit costs. Williams focuses on consistently attracting new business by providing highly reliable service to its customers. These services include natural gas gathering, processing, treating, compression and storage; NGL fractionation, transportation and storage; and crude oil production handling and transportation, as well as marketing services for NGL, crude oil, and natural gas.

Consistent with the manner in which Williams’ CODM evaluates performance and allocates resources, Williams’ operations are conducted, managed, and presented within the following reportable segments: Transmission, Power & Gulf, Northeast G&P, West, and Gas & NGL Marketing Services. All remaining business activities, including upstream operations, certain new energy ventures, and corporate activities, are included in Other. Williams’ reportable segments are comprised of the following business activities:

Transmission, Power & Gulf is comprised of interstate natural gas pipelines and their related natural gas storage facilities including Transco, NWP, and MountainWestand a 50 percent equity-method investment in Gulfstream; natural gas gathering and processing and crude oil production handling and transportation assets in the Gulf Coast region, including Discovery, a former 60 percent equity-method investment in which Williams acquired the remaining ownership interest in August 2024 (see Note 3 – Acquisitions and Divestitures) and a 51 percent interest in Gulfstar One; and natural gas storage facilities and pipelines providing services in north Texas, and also in Louisiana and Mississippi related to the January 2024 Gulf Coast Storage Acquisition (see Note 3 – Acquisitions and Divestitures). Transmission, Power & Gulf also includes power innovation projects under development that will deliver speed-to-market solutions in grid-constrained markets. This segment was formerly referred to as Transmission & Gulf of America.

Northeast G&P is comprised of midstream gathering, processing, and fractionation businesses in the Marcellus Shale region primarily in Pennsylvania and New York, and the Utica Shale region of eastern

Ohio, as well as a 65 percent interest in Northeast JV which operates in West Virginia, Ohio, and Pennsylvania, a 66 percent interest in Cardinal which operates in Ohio, a 50 percent equity-method investment in Blue Racer, and Appalachia Midstream Investments.

West is comprised of gas gathering, processing, and treating operations in the Rocky Mountain region of Colorado and Wyoming, the Barnett Shale region of north-central Texas, the Eagle Ford Shale region of south Texas, the Haynesville Shale region of east Texas and northwest Louisiana, the Mid-Continent region which includes the Anadarko and Permian basins, and the DJ Basin of Colorado. This segment also includes NGL storage facilities, an undivided 50 percent interest in an NGL fractionator near Conway, Kansas, and a 50 percent equity-method investment in OPPL.

Gas & NGL Marketing Services is comprised of NGL and natural gas marketing and trading operations, which include risk management and transactions related to the storage and transportation of natural gas and NGLs on strategically positioned assets.

Unless indicated otherwise, the following discussion and analysis of results of operations and financial condition and liquidity relates to Williams’ current continuing operations and should be read in conjunction with the financial statements and combined notes thereto of this Form 10-Q and the Annual Report on Form 10-K for the year ended December 31, 2024, dated February 25, 2025.

Dividends

In September 2025, Williams paid a regular quarterly dividend of $0.50 per share.

Overview of Nine Months Ended September 30, 2025

Net income (loss) attributable to The Williams Companies, Inc. for the nine months ended September 30, 2025, increased $145 million compared to the nine months ended September 30, 2024. Further discussion of the results is found in this report in the Results of Operations.

Recent Developments

Transco FERC Rate Case Filing

On August 30, 2024, Transco filed a general rate case with the FERC for an overall increase in rates and to comply with the terms of the settlement of its prior rate case. On September 30, 2024, the FERC issued an order accepting and suspending Transco’s general rate filing to be effective March 1, 2025, subject to refund and the outcome of hearing procedures established by the FERC. The order also accepted rate decreases for certain services to be effective as of October 1, 2024. During the third quarter of 2025, Transco reached an agreement in principle with its customers and the other participants to settle all aspects of the rate case and has accrued a related reserve. Transco filed with the FERC in October 2025 for approval of the settlement.

Data Center Power Innovation Projects

Williams continues to pursue projects to support the power demands created by new data center development, including agreements with an unnamed large, investment-grade company to provide onsite natural gas and power generation infrastructure. See Expansion Projects for further discussion.

Sale of South Mansfield Upstream Interests

In October 2025, Williams entered into an agreement to sell its interests in certain upstream ventures in the South Mansfield area of the Haynesville Shale region, included in Other, for consideration of approximately $398 million with additional contingent consideration to possibly be received through 2029. Upon closing, Williams expects to record a gain in the fourth quarter of 2025.

Louisiana LNG and Driftwood Pipeline

In October 2025, Williams closed on various agreements with the same counterparty to acquire a 10 percent equity-method interest in Louisiana LNG LLC, which is developing a fully permitted LNG export facility, and an 80 percent interest in Driftwood Pipeline LLC, which is constructing a fully permitted greenfield pipeline connecting to multiple other pipelines, including Transco and Louisiana Energy Gateway, to supply the LNG facility. Williams will be the operator of the pipeline. The total initial purchase price was $378 million, and both investments will require additional capital to fund further construction. The Louisiana LNG LLC and Driftwood Pipeline LLC purchases were funded with available liquidity. Williams will also manage the gas supply for the LNG facility and purchase a portion of the LNG produced.

Saber Asset Purchase

In June 2025, Williams acquired 100 percent of Saber Midstream, LLC (Saber). The acquisition, which was accounted for as an asset purchase, included cash consideration of $47 million and the retention of $113 million of Saber’s debt, which was separately repaid in full within the same month. Saber operates a gas gathering system in the Haynesville Shale region in the West segment.

Cogentrix Investment

In March 2025, Williams purchased a minority interest in Cogentrix Co-Investment Fund, LP (Cogentrix) for $153 million, which is accounted for as an equity-method investment within the Gas & NGL Marketing Services segment. Cogentrix owns interests in 11 natural gas power plants.

Rimrock Asset Purchase

On January 31, 2025, Williams purchased a group of natural gas gathering and processing assets from Rimrock Energy Partners, LLC (Rimrock) for approximately $325 million, to expand Williams’ gathering and processing footprint and create operational synergies in the DJ Basin in the West segment.

Expansion Project Updates

Expansion projects placed into service for the current year are described below. Ongoing major expansion projects are discussed later in Company Outlook.

Stanfield South

The project on NWP’s existing natural gas transmission system provides year-round transportation capacity from the Stanfield receipt point in Oregon to multiple delivery points in Idaho and a new delivery meter in Wyoming. NWP placed the project into service in November 2025, increasing NWP’s contracted capacity by 80 Mdth/d.

Commonwealth Energy Connector

In November 2023, Transco received approval from the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity in Virginia. Transco placed the project into service in November 2025, increasing Transco’s capacity by 105 Mdth/d.

Alabama Georgia Connector

In March 2024, Transco received approval from the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from Transco’s Station 85 pooling point in Alabama to customers in Georgia. Transco placed the project into service in October 2025, increasing Transco’s capacity by 64 Mdth/d.

Deepwater Shenandoah Project

In June 2021, Williams reached an agreement with two third parties to provide offshore natural gas gathering and transportation services as well as onshore natural gas processing services. The project expands the existing Gulf of America offshore infrastructure connecting to a third-party offshore lateral pipeline from the Shenandoah platform to Discovery’s existing Keathley Canyon Connector pipeline, adds onshore processing facilities at Larose, Louisiana to handle the expected rich Shenandoah production, and the natural gas liquids are now fractionated and marketed at Discovery’s Paradis plant in Louisiana. This project was placed into service in July 2025.

Texas to Louisiana Energy Pathway

In January 2024, Transco received approval from the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide firm transportation capacity from receipt points in south Texas to delivery points in Texas and Louisiana. Transco placed the project into service in April 2025. Under the project, Transco provides 364 Mdth/d of new firm transportation service through a combination of increasing capacity, converting interruptible capacity to firm, and utilizing existing capacity.

Southeast Energy Connector

In November 2023, Transco received approval from the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from receipt points in Mississippi and Alabama to a delivery point in Alabama. Transco placed the project into service in April 2025, increasing Transco’s capacity by 150 Mdth/d.

Deepwater Whale Project

In August 2021, Williams reached an agreement with two third parties to provide offshore natural gas gathering and crude oil transportation services as well as onshore natural gas processing services. The project expands its existing Western Gulf of America offshore infrastructure via a 26-mile gas lateral pipeline from the Whale platform to the existing Perdido gas pipeline and adds a new 124-mile oil pipeline from the Whale platform to Williams’ existing junction platform. This project was placed into service in January 2025.

West

Haynesville Gathering Expansion

In February 2023, Williams announced its agreement with a third party to facilitate natural gas production growth in the Haynesville Shale basin for the construction of a greenfield gathering system in support of a 26,000-acre dedication. In April 2025, the third party sold a majority of their ownership interest to another party, with both third parties agreeing to long-term capacity commitments on Williams’ Louisiana Energy Gateway expansion project. This project was placed into service in September 2025, providing natural gas gathering services to both parties.

Louisiana Energy Gateway

In August 2024, Williams began construction activities on new natural gas gathering assets in the Haynesville Shale basin to increase delivery of natural gas to premium markets, including Transco, industrial markets, and growing LNG export demand along the Gulf Coast. This project was placed into service in July and August 2025, increasing natural gas gathering capacity by 1.8 Bcf/d.

ContentsView on SEC.gov