A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Jun 30, 2025 · Filed Aug 4, 2025

WMB$66.45+3.7%Stored close · as of Nov 9, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

General

Williams is an energy company committed to being the leader in providing infrastructure that safely delivers natural gas products to reliably fuel the clean energy economy. Its operations are located in the United States.

Williams’ interstate natural gas pipeline strategy is to create value by maximizing the utilization of its pipeline capacity by providing high-quality, low-cost transportation of natural gas to large and growing markets. Williams’ gas pipeline businesses’ interstate transmission and storage activities are subject to regulation by the FERC. As such, Williams’ rates and charges for the transportation of natural gas in interstate commerce, and the extension, expansion, or abandonment of jurisdictional facilities and accounting, among other things, are subject to regulation. The rates are established primarily through the FERC’s ratemaking process, but Williams may also negotiate rates with its customers pursuant to the terms of its tariffs and FERC policy. Changes in commodity prices and volumes transported have limited near-term impact on these revenues because the majority of the cost of service is recovered through firm capacity reservation charges in transportation rates.

The ongoing strategy of Williams’ midstream operations is to safely and reliably operate large-scale midstream infrastructure where its assets can be fully utilized and drive low per-unit costs. Williams focuses on consistently attracting new business by providing highly reliable service to its customers. These services include natural gas gathering, processing, treating, compression and storage; NGL fractionation, transportation and storage; and crude oil production handling and transportation, as well as marketing services for NGL, crude oil, and natural gas.

Consistent with the manner in which Williams’ CODM evaluates performance and allocates resources, Williams’ operations are conducted, managed, and presented within the following reportable segments: Transmission & Gulf of America, Northeast G&P, West, and Gas & NGL Marketing Services. All remaining business activities, including upstream operations, certain new energy ventures, and corporate activities, are included in Other. Williams’ reportable segments are comprised of the following business activities:

Transmission & Gulf of America is comprised of the Transco, NWP, and MountainWest interstate natural gas pipelines, and their related natural gas storage facilities, as well as natural gas gathering and processing and crude oil production handling and transportation assets in the Gulf Coast region, including Discovery, a former 60 percent equity-method investment in which Williams acquired the remaining ownership interest in August 2024 (see Note 3 – Acquisitions and Divestitures), a 51 percent interest in Gulfstar One, and a 50 percent equity-method investment in Gulfstream. Transmission & Gulf of America also includes natural gas storage facilities and pipelines providing services in north Texas, and also in Louisiana and Mississippi related to the January 2024 Gulf Coast Storage Acquisition (see Note 3 – Acquisitions and Divestitures).

Northeast G&P is comprised of midstream gathering, processing, and fractionation businesses in the Marcellus Shale region primarily in Pennsylvania and New York, and the Utica Shale region of eastern Ohio, as well as a 65 percent interest in Northeast JV which operates in West Virginia, Ohio, and

Pennsylvania, a 66 percent interest in Cardinal which operates in Ohio, a 50 percent equity-method investment in Blue Racer, and Appalachia Midstream Investments.

West is comprised of gas gathering, processing, and treating operations in the Rocky Mountain region of Colorado and Wyoming, the Barnett Shale region of north-central Texas, the Eagle Ford Shale region of south Texas, the Haynesville Shale region of east Texas and northwest Louisiana, the Mid-Continent region which includes the Anadarko and Permian basins, and the DJ Basin of Colorado. This segment also includes NGL storage facilities, an undivided 50 percent interest in an NGL fractionator near Conway, Kansas, and a 50 percent equity-method investment in OPPL.

Gas & NGL Marketing Services is comprised of NGL and natural gas marketing and trading operations, which include risk management and transactions related to the storage and transportation of natural gas and NGLs on strategically positioned assets.

Unless indicated otherwise, the following discussion and analysis of results of operations and financial condition and liquidity relates to Williams’ current continuing operations and should be read in conjunction with the financial statements and combined notes thereto of this Form 10-Q and the Annual Report on Form 10-K for the year ended December 31, 2024, dated February 25, 2025.

Dividends

In June 2025, Williams paid a regular quarterly dividend of $0.50 per share.

Overview of Six Months Ended June 30, 2025

Net income (loss) attributable to The Williams Companies, Inc. for the six months ended June 30, 2025, increased $204 million compared to the six months ended June 30, 2024. Further discussion of the results is found in this report in the Results of Operations.

Recent Developments

Transco FERC Rate Case Filing

On August 30, 2024, Transco filed a general rate case with the FERC for an overall increase in rates and to comply with the terms of the settlement of its prior rate case. On September 30, 2024, the FERC issued an order accepting and suspending Transco’s general rate filing to be effective March 1, 2025, subject to refund and the outcome of hearing procedures established by the FERC. The order also accepted rate decreases for certain services to be effective as of October 1, 2024. Transco has provided a reserve for rate refunds, which it believes is adequate for any refunds that may be required.

Data Center Power Projects

Williams continues to pursue projects to support the power demands created by new data center development, including an agreement with an unnamed large, investment-grade company to provide onsite natural gas and power generation infrastructure. See Expansion Projects for further discussion of Socrates.

Saber Asset Purchase

In June 2025, Williams acquired 100 percent of Saber Midstream, LLC (Saber). The acquisition, which was accounted for as an asset purchase, included cash consideration of $47 million and the retention of $113 million of Saber’s debt, which was separately repaid in full within the same month. Saber operates a gas gathering system in the Haynesville Shale region in the West segment.

Cogentrix Investment

In March 2025, Williams purchased a minority interest in Cogentrix Co-Investment Fund, LP (Cogentrix) for $153 million, which is accounted for as an equity-method investment within the Gas & NGL Marketing Services segment. Cogentrix owns interests in 11 natural gas power plants.

Rimrock Asset Purchase

On January 31, 2025, Williams purchased a group of natural gas gathering and processing assets from Rimrock Energy Partners, LLC for approximately $325 million, to expand Williams’ gathering and processing footprint and create operational synergies in the DJ Basin in the West segment.

Expansion Project Updates

Expansion projects placed into service for the current year are described below. Ongoing major expansion projects are discussed later in Company Outlook.

Deepwater Shenandoah Project

In June 2021, Williams reached an agreement with two third parties to provide offshore natural gas gathering and transportation services as well as onshore natural gas processing services. The project expands the existing Gulf of America offshore infrastructure connecting to a third-party offshore lateral pipeline from the Shenandoah platform to Discovery’s existing Keathley Canyon Connector pipeline, adds onshore processing facilities at Larose, Louisiana to handle the expected rich Shenandoah production, and the natural gas liquids are now fractionated and marketed at Discovery’s Paradis plant in Louisiana. This project was placed into service in July 2025.

Texas to Louisiana Energy Pathway

In January 2024, Transco received approval from the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide firm transportation capacity from receipt points in south Texas to delivery points in Texas and Louisiana. Transco placed the project into service in April 2025. Under the project, Transco provides 364 Mdth/d of new firm transportation service through a combination of increasing capacity, converting interruptible capacity to firm, and utilizing existing capacity.

Southeast Energy Connector

In November 2023, Transco received approval from the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from receipt points in Mississippi and Alabama to a delivery point in Alabama. Transco placed the project into service in April 2025. The project increases Transco’s capacity by 150 Mdth/d.

Deepwater Whale Project

In August 2021, Williams reached an agreement with two third-parties to provide offshore natural gas gathering and crude oil transportation services as well as onshore natural gas processing services. The project expands its existing Western Gulf of America offshore infrastructure via a 26-mile gas lateral pipeline from the Whale platform to the existing Perdido gas pipeline and adds a new 124-mile oil pipeline from the Whale platform to Williams’ existing junction platform. This project was placed into service in January 2025.

West

Louisiana Energy Gateway

In August 2024, Williams began construction activities on new natural gas gathering assets in the Haynesville Shale basin to increase delivery of natural gas to premium markets, including Transco, industrial markets, and growing LNG export demand along the Gulf Coast. This project was placed into service in third-quarter 2025, increasing natural gas gathering capacity by 1.8 Bcf/d.