Skip to main content

NORTHWEST PIPELINE LLC

For the period ended Jun 30, 2025. Filed Aug 4, 2025.

View on SEC.gov

About this filing

A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Jun 30, 2025 · Filed Aug 4, 2025

WMB$67.46+1.5%Stored close · as of Nov 10, 2026

Extracted filing text, with the paragraph anchors used by the comparison.

See the whole filing, with its images and exhibits
Contents

Company Outlook

Williams’ strategy is to provide a large-scale, reliable, and clean energy infrastructure designed to maximize the opportunities created by the vast supply of natural gas and natural gas products that exists in the United States. Williams accomplishes this by connecting the growing demand for cleaner fuels and feedstocks with our major positions in the premier natural gas and natural gas products supply basins. Williams continues to maintain a strong commitment to safety, environmental stewardship including seeking opportunities for renewable energy ventures, operational excellence, and customer satisfaction. Williams believes that accomplishing these goals will position it to deliver safe, reliable, clean energy services to its customers and an attractive return to shareholders. Williams’ business plan for 2025 includes a continued focus on earnings and cash flow growth.

In 2025, Williams’ operating results are expected to benefit from the continued growth in the Transmission & Gulf of America segment, primarily reflecting the impacts of numerous expansion projects at Transco and the Gulf of America. Additionally, growth in 2025 includes the impact of the Transco rate case and higher gathering and processing results associated with growth in the DJ Basin and the Northeast. Williams also expects increases in Haynesville Shale volumes, including partial year impact of the Louisiana Energy Gateway expansion project and higher expected results from its upstream operations, including the full year impact of the Crowheart Acquisition. Williams also expects to benefit from the recent equity investment in Cogentrix. These increases are partially offset by a modest increase in expenses, lower gas marketing results, and lower expected Eagle Ford results in our West segment related to minimum volume commitment reductions.

Williams seeks to maintain a strong financial position and liquidity, as well as manage a diversified portfolio of safe, clean, and reliable energy infrastructure assets that continue to serve key growth markets and supply basins in the United States. Williams’ growth capital and investment expenditures in 2025 are expected to range from $2.575 billion to $2.875 billion, excluding acquisitions. Growth capital spending in 2025 primarily includes the Socrates Power Innovation project, projects supporting growth in the Haynesville Shale basin (including the Louisiana Energy Gateway expansion project), Transco expansions, all of which are fully contracted with firm transportation agreements, and projects supporting the Northeast G&P business. Williams also expects to invest capital in the development of its upstream oil and gas properties. In addition to growth capital and investment expenditures, Williams also remains committed to projects that maintain its assets for safe and reliable operations, as well as projects that reduce emissions, and meet legal, regulatory, and/or contractual commitments.

Potential risks and obstacles that could impact the execution of Williams’ plan include:

A global recession, which could result in downturns in financial markets and commodity prices, as well as impact demand for natural gas and related products;

Opposition to, and regulations affecting, our infrastructure projects, including the risk of delay or denial in permits and approvals needed for our projects;

Counterparty credit and performance risk;

Unexpected significant increases in capital expenditures or delays in capital project execution, including increases from inflation or delays caused by supply chain disruptions;

Unexpected changes in customer drilling and production activities, which could negatively impact gathering and processing volumes;

Lower than anticipated demand for natural gas and natural gas products which could result in lower-than-expected volumes, energy commodity prices, and margins;

General economic, financial markets, or industry downturns, including increased inflation, interest rates, or tariffs;

Physical damages to facilities, including damage to offshore facilities by weather-related events;

Other risks set forth under Part I, Item 1A. Risk Factors. Risk Factors in the Annual Report on Form 10-K for the year ended December 31, 2024, as filed with the SEC on February 25, 2025, as may be supplemented by disclosure in Part II, Item 1A. Risk Factors in subsequent Quarterly Reports on Form 10‑Q.

Expansion Projects

Williams’ ongoing major expansion projects include the following:

Overthrust Westbound Compression Expansion

In October 2024, MountainWest received approval from the FERC for the project, which involves an expansion of MountainWest’s existing natural gas transmission system to provide incremental firm transportation capacity from multiple receipt points in Wamsutter, Wyoming to a delivery point in Opal, Wyoming. MountainWest plans to place the project into service as early as the fourth quarter of 2025, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 325 Mdth/d.

Commonwealth Energy Connector

In November 2023, Transco received approval from the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity in Virginia. Transco plans to place the project into service as early as the fourth quarter of 2025, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 105 Mdth/d.

Alabama Georgia Connector

In March 2024, Transco received approval from the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from Transco’s Station 85 pooling point in Alabama to customers in Georgia. Transco plans to place the project into service as early as the fourth quarter of 2025, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 64 Mdth/d.

Southeast Supply Enhancement

In October 2024, Transco filed a certificate application with the FERC for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from receipt points in Virginia to delivery points in Virginia, North Carolina, South Carolina, Georgia, and Alabama. Transco plans to place the project into service as early as the third quarter of 2027, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 1,597 Mdth/d.

Gillis West

Transco plans to file a prior notice application for the project with the FERC in 2026, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from receipt points in Louisiana to delivery points in Texas. Transco plans to place the project into service as early as the second quarter of 2026, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 115 Mdth/d.

Northeast Supply Enhancement

In May 2025, Transco filed a petition with the FERC for reissuance of the certificate authorization for the project, which involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from Transco’s Compressor Station 195 in Pennsylvania to the Rockaway Delivery Lateral transfer point in New York. Also in May 2025, Transco filed applications with the states of New York, New Jersey, and Pennsylvania for Clean Water Act and related permits for the project. In August 2025, Transco executed precedent agreements with customers subscribing to all of the capacity under the project. Transco plans to place the project into service as early as the fourth quarter of 2027, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 400 Mdth⁄d.

Dalton Lateral II

Transco plans to file a certificate application for the project with the FERC in 2026. The project involves an expansion of Transco’s existing natural gas transmission system to provide incremental firm transportation capacity from Transco’s main line near existing Station 115 to an existing power plant in Georgia. Transco plans to place the project into service as early as the fourth quarter of 2029, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity up to 460 Mdth/d.

Ryckman Creek Loop

NWP plans to file a prior notice application for the project with the FERC in 2025. The project involves an expansion of NWP’s existing natural gas transmission system to provide incremental firm transportation capacity from a receipt point in northeast Oregon (Stanfield) to multiple delivery points in southwest Wyoming. NWP plans to place the project into service as early as the fourth quarter of 2026, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 50 Mdth/d.

Stanfield South

The project involves an expansion of NWP’s existing natural gas transmission system to provide year-round transportation capacity from the Stanfield receipt point in Oregon to multiple delivery points in Idaho. NWP plans to place the project into service as early as the fourth quarter of 2025, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 80 Mdth/d.

Naughton Coal-to-Gas Conversion

The project involves an expansion of NWP’s existing natural gas transmission system to provide year-round transportation capacity to a power plant in southwest Wyoming. NWP plans to place the project into service as early as the second quarter of 2026, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 98 Mdth/d.

Kelso-Beaver Reliability

NWP filed a certificate application for the project with the FERC in February 2025. The Kelso-Beaver Reliability project on NWP’s existing natural gas transmission system will provide year-round transportation capacity to various receipt and delivery points in Oregon. NWP plans to place the project into service during the fourth quarter of 2028, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 183 Mdth/d.

Huntingdon Connector

NWP plans to file a prior notice application for the project with the FERC in 2026. The project involves an expansion of NWP’s existing natural gas transmission system that will provide year-round transportation capacity from the Sumas receipt point to various delivery points in Washington. NWP plans to place the project into service during the fourth quarter of 2026, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 78 Mdth/d.

Wild Trail

In May 2025, NWP filed a certificate application with the FERC for the project, which involves an expansion of NWP’s existing natural gas transmission system that will provide year-round transportation capacity from the White River Hub receipt point in western Colorado to various delivery points in southwest Wyoming and southern Colorado. This Wild Trail project is fully subscribed by an affiliate within Williams’ Gas & NGL Marketing Services segment. NWP plans to place the project into service during the fourth quarter of 2027, assuming timely receipt of all necessary regulatory approvals. The project is expected to increase capacity by 83 Mdth/d.

Socrates

Williams has received partial approval and is waiting for full approval from the Ohio Power Siting Board for this Power Innovation project, which involves the construction of the Socrates North and South power generation facilities in New Albany, Ohio. Williams has agreed to invest approximately $1.6 billion to provide committed power generation and associated gas pipeline infrastructure for the project, which is expected to provide a combined 400 megawatts of committed onsite power generation capacity to the customer. The project is backed by a ten-year, primarily fixed-price power purchase agreement, with an option for the customer to extend. Williams plans to place the project into service in the second half of 2026, assuming timely receipt of permits.

West

Haynesville Gathering Expansion

In February 2023, Williams announced its agreement with a third party to facilitate natural gas production growth in the Haynesville Shale basin. Williams is constructing a greenfield gathering system in support of a 26,000-acre dedication. In April 2025, the third party sold a majority of their ownership interest to another party. The system, once completed, will provide natural gas gathering services to both parties who have also agreed to long-term capacity commitments on Williams’ Louisiana Energy Gateway expansion project. This project is expected to go into service in third-quarter 2025.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.