- ACQUISITIONS AND DISPOSITIONS
On September 30, 2025, Alabama Power completed its acquisition of Tenaska Alabama Partners, L.P., which owned and operated the Lindsay Hill Generating Station, an approximately 879.7-MW combined cycle generation facility in Autauga County, Alabama. The transaction was accounted for as a business combination. The total purchase price was $635 million, of which $622 million was related to net assets recorded within property, plant, and equipment and the remainder was included in inventory, current receivables, and accounts payable on the balance sheet. The transaction was recorded as a business acquisition within the investing section of the statement of cash flows. Alabama Power assumed an existing power sales agreement under which the full output of the generating facility remains committed to a non-affiliated third party through April 2027. See Note 2 under "Alabama Power – Rate CNP New Plant" for additional information.
On July 30, 2025, Mississippi Power completed the acquisition of FP&L's 50% ownership interest in Plant Daniel Units 1 and 2 and, as part of the acquisition, received approximately $36 million from FP&L. See Note 2 under "Mississippi Power – Plant Daniel" for additional information.
Southern Power's acquisition-related costs for the projects discussed under "Asset Acquisitions" and "Construction Projects" were not material for any of the years presented.
II-245
Asset Acquisitions
During 2023, Southern Power acquired the Millers Branch and South Cheyenne projects, as discussed further under "Construction Projects" below, with an aggregate purchase price of $193 million. There were no asset acquisitions during 2024 and 2025.
Construction Projects
During 2024, Southern Power completed construction of and placed in service the 150-MW South Cheyenne solar facility. During 2025, Southern Power continued construction of the three phases of the 512-MW Millers Branch solar facility. At December 31, 2025, the total cost of construction incurred for the Millers Branch project was $694 million, which is primarily included in CWIP. The ultimate outcome of these matters cannot be determined at this time.
| ProjectFacility | Resource | Approximate Nameplate Capacity (MW) | Location | Actual/Projected COD | PPA Contract Period |
|---|---|---|---|---|---|
| Projects Under Construction at December 31, 2025 | |||||
| Millers Branch | |||||
| Phase I | Solar | 200 | Haskell County, TX | February 2026(*) | 20 years |
| Phase II | Solar | 180 | Haskell County, TX | Second quarter 2026 | 15 years |
| Phase III | Solar | 132 | Haskell County, TX | Fourth quarter 2026 | 15 years |
| Projects Completed During 2024 | |||||
| South Cheyenne | Solar | 150 | Laramie County, WY | April 2024 | 20 years |
(*)Subsequent to December 31, 2025, Southern Power completed construction of the 200-MW first phase of the Millers Branch solar facility.
Wind Repowering Projects
During 2025, Southern Power continued the development project to repower the Kay wind facility and began development projects to repower the Grant Plains, Grant, Wake, and Bethel wind facilities. At December 31, 2025, the total cost of construction incurred related to the projects was $358 million and is included in CWIP. The repowered output of the facilities is contracted under new and amended PPAs. The ultimate outcome of these matters cannot be determined at this time.
| Project Facility | Resource | Approximate Nameplate Capacity(MW) | Location | Projected COD |
|---|---|---|---|---|
| Projects Under Construction at December 31, 2025 | ||||
| Kay(*) | Wind | 200 | Kay County, OK | Third quarter 2026 |
| Grant Plains | Wind | 147 | Grant County, OK | Fourth quarter 2026 |
| Grant | Wind | 152 | Grant County, OK | Fourth quarter 2026 |
| Wake | Wind | 257 | Crosby & Floyd Counties, TX | Second quarter 2027 |
| Bethel | Wind | 276 | Castro County, TX | Third quarter 2027 |
(*)The facility has a total capacity of 299 MWs, of which 200 MWs is projected to be repowered and is contracted under a PPA.
Purchase of Renewable Facility Interests
On December 31, 2025, Southern Power completed the purchase of 100% of the noncontrolling Class A membership interests in SP Wind from thethree financial investors for approximately $282 million. Since Southern Power retains control of SP Wind, the purchase was accounted for as an equity transaction, and Southern Power will continue to consolidate SP Wind in its financial statements. On the date of the transaction, noncontrolling interest was reduced by $242 million. The difference in the purchase price and the carrying value of the noncontrolling interest resulted in a $36 million non-cash decrease to Southern Power's common stockholders' equity, net of deferred tax remeasurement. See Note 7 under "Southern Power – Variable Interest Entities – SP Wind" for additional information.