ALABAMA POWER CO
For the period ended Sep 30, 2025. Filed Oct 30, 2025.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Sep 30, 2025 · Filed Oct 30, 2025
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Acquisitions and Dispositions
(K)ACQUISITIONS AND DISPOSITIONS
See Note 15 to the financial statements in Item 8 of the Form 10-K for additional information.
On September 30, 2025, Alabama Power completed its acquisition of Tenaska Alabama Partners, L.P., which owned and operated the Lindsay Hill Generating Station. The transaction was accounted for as a business combination. The total purchase price was $635 million, of which $622 million was related to net assets recorded within property, plant, and equipment and the remainder was included in inventory, current receivables, and accounts payable on the balance sheet. The transaction was recorded as a business acquisition within the investing section of the statement of cash flows. Alabama Power assumed an existing power sales agreement under which the full output of the generating facility remains committed to a non-affiliated third party through April 2027. See Note (B) under "Alabama Power – Petition for Certificate of Convenience and Necessity" for additional information.
On July 30, 2025, Mississippi Power completed the acquisition of FP&L's 50% interest in Plant Daniel Units 1 and 2 and, as part of the acquisition, received approximately $36 million from FP&L. See Note (B) under "Mississippi Power – Plant Daniel" for additional information.
Construction Projects
During the nine months ended September 30, 2025, Southern Power continued construction of the three phases of the 512-MW Millers Branch solar facility. At September 30, 2025, the total cost of construction incurred for the Millers Branch project was $661 million, which is primarily included in CWIP. The ultimate outcome of these matters cannot be determined at this time.
| Project Facility | Resource | Approximate Nameplate Capacity(MW) | Location | Projected COD | PPA Contract Period |
|---|---|---|---|---|---|
| Projects Under Construction at September 30, 2025 | |||||
| Millers Branch | |||||
| Phase I | Solar | 200 | Haskell County, TX | Fourth quarter 2025 | 20 years |
| Phase II | Solar | 180 | Haskell County, TX | Second quarter 2026 | 15 years |
| Phase III | Solar | 132 | Haskell County, TX | Fourth quarter 2026 | 15 years |
Wind Repowering Projects
During the nine months ended September 30, 2025, Southern Power continued the development project to repower the Kay Wind facility and began development projects to repower the Grant Plains, Grant Wind, and Wake Wind facilities. At September 30, 2025, the total cost of construction incurred related to the projects was $165 million and is included in CWIP. The repowered output of the facilities is contracted under new and amended PPAs. The ultimate outcome of these matters cannot be determined at this time.
| Project Facility | Resource | Approximate Nameplate Capacity(MW) | Location | Projected COD |
|---|---|---|---|---|
| Projects Under Construction at September 30, 2025 | ||||
| Kay Wind(*) | Wind | 200 | Kay County, OK | Third quarter 2026 |
| Grant Plains | Wind | 147 | Grant County, OK | Fourth quarter 2026 |
| Grant Wind | Wind | 152 | Grant County, OK | Fourth quarter 2026 |
| Wake Wind | Wind | 257 | Crosby & Floyd Counties, TX | Second quarter 2027 |
(*)The facility has a total capacity of 299 MWs, of which 200 MWs is projected to be repowered and is contracted under a PPA.