Acquisitions and Dispositions

(K)ACQUISITIONS AND DISPOSITIONS

See Note 15 to the financial statements in Item 8 of the Form 10-K for additional information.

On June 6, 2025, the FERC approved Alabama Power's acquisition of Tenaska Alabama Partners, L.P., which owns and operates the Lindsay Hill Generating Station. The ultimate outcome of this matter cannot be determined at this time. See Note (B) under "Alabama Power – Petition for Certificate of Convenience and Necessity" for additional information.

On June 19, 2025, the Florida PSC issued a final order approving the transfer of FP&L's 50% ownership interest in Plant Daniel Units 1 and 2 to Mississippi Power. On July 30, 2025, Mississippi Power completed the acquisition of FP&L's 50% interest in Plant Daniel Units 1 and 2 and, as part of the acquisition, received approximately $36 million from FP&L. See Note 2 to the financial statements under "Mississippi Power – Plant Daniel" in Item 8 of the Form 10-K for additional information.

Construction Projects

During the six months ended June 30, 2025, Southern Power continued construction of the three phases of the 512-MW Millers Branch solar facility. At June 30, 2025, the total cost of construction incurred for the Millers Branch project was $537 million, which is primarily included in CWIP. The ultimate outcome of these matters cannot be determined at this time.

Project FacilityResourceApproximate Nameplate Capacity(MW)LocationProjected CODPPA Contract Period
Projects Under Construction at June 30, 2025
Millers Branch
Phase ISolar200Haskell County, TXFourth quarter 202520 years
Phase IISolar180Haskell County, TXSecond quarter 202615 years
Phase IIISolar132Haskell County, TXFourth quarter 202615 years

Wind Repowering Projects

During the six months ended June 30, 2025, Southern Power continued the development project to repower the Kay Wind facility. In addition, Southern Power committed to development projects to repower the Grant Plains, Grant Wind, and Wake Wind facilities. At June 30, 2025, the total cost of construction incurred related to the projects was

$89 million and is included in CWIP. The repowered output of the facilities is contracted under new and amended PPAs. The ultimate outcome of these matters cannot be determined at this time.

Project FacilityResourceApproximate Nameplate Capacity(MW)LocationProjected COD
Projects Under Construction at June 30, 2025
Kay Wind(*)Wind200Kay County, OKThird quarter 2026
Grant PlainsWind147Grant County, OKFourth quarter 2026
Grant WindWind152Grant County, OKFourth quarter 2026
Wake WindWind257Crosby & Floyd Counties, TXSecond quarter 2027

(*)The facility has a total capacity of 299 MWs, of which 200 MWs is projected to be repowered and is contracted under an amended PPA.