Future Earnings Potential

Each Registrant's results of operations are not necessarily indicative of its future earnings potential. The level of the Registrants' future earnings depends on numerous factors that affect the opportunities, challenges, and risks of the Registrants' primary businesses of selling electricity and/or distributing natural gas, as described further herein. The Registrants are unable to predict changes in law, regulations, regulatory guidance, legal interpretations, policy positions, and implementation actions that may result from the new presidential administration.

For the traditional electric operating companies, these factors include the ability to maintain constructive regulatory environments that allow for the timely recovery of prudently-incurred costs during a time of increasing costs, including those related to projected long-term demand growth, stringent environmental standards, including CCR rules, safety, system reliability and resiliency, fuel, restoration following major storms, and capital expenditures, including constructing new electric generating plants, extending the retirement dates of certain fossil fuel plants, and expanding and improving the transmission and distribution systems; continued customer growth; and the trends of an uncertain inflationary environment and reduced electricity usage per customer, especially in residential and commercial markets.

Earnings in the electricity business will also depend upon maintaining and growing sales and pricing of large customers such that incremental costs are met with adequate incremental revenues, considering, among other things, recent trends driving projected growth in electricity consumption including the increasing digitization of the economy and growth in data centers, an increase in industrial activity in the Southern Company system's electric service territory, and continued electrification of transportation. These growth opportunities could be offset by energy efficiency trends in each market.

Economic uncertainty and policy uncertainty have increased the volatility of future economic outlooks above historical norms. Significant changes in fiscal, monetary, or trade policies could disrupt anticipated economic outlooks. This uncertainty in economic growth, interest rates, tariffs, and inflation could impact customer demand for energy, access to capital markets, and the cost of doing business. The shifting economic policy variables and weakening of historic relationships among economic activity, prices, and employment have increased the uncertainty of future levels of economic activity, which will directly impact future energy demand and operating costs. Weakening economic activity increases the risk of slowing or declining energy sales. See RESULTS OF OPERATIONS herein for information on energy sales in the Southern Company system's service territory during the first three months of 2025.

The level of future earnings for Southern Power's competitive wholesale electric business depends on numerous factors including the parameters of the wholesale market and the efficient operation of its wholesale generating assets; Southern Power's ability to execute its growth strategy through the development, construction, or acquisition of renewable facilities and other energy projects while containing costs; regulatory matters; customer creditworthiness; total electric generating capacity available in Southern Power's market areas; Southern Power's ability to successfully remarket capacity as current contracts expire; renewable portfolio standards; continued availability of federal and state ITCs and PTCs, which could be impacted by future tax legislation; transmission constraints; cost of generation from units within the Southern Company power pool; and operational limitations. See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Income Tax Matters" in Item 7 of the Form 10-K for information regarding the Inflation Reduction Act's expansion of the availability of federal ITCs and PTCs and Note (K) to the Condensed Financial Statements under "Southern Power" herein for information regarding construction projects.

The level of future earnings for Southern Company Gas' primary business of distributing natural gas and its complementary businesses in the gas pipeline investments and gas marketing services sectors depends on numerous factors. These factors include the natural gas distribution utilities' ability to maintain constructive regulatory environments that allow for the timely recovery of prudently-incurred costs, including those related to projected long-term demand growth, safety, system reliability and resiliency, natural gas, and capital expenditures, including expanding and improving the natural gas distribution systems; the completion and subsequent operation of ongoing infrastructure and other construction projects; customer creditworthiness; and certain policies to limit the use of natural gas, such as the potential in Illinois and across certain other parts of the United States for state or municipal bans on the use of natural gas or policies designed to promote electrification. The volatility of natural gas prices has an impact on Southern Company Gas' customer rates, its long-term competitive position against other energy sources, and the ability of Southern Company Gas' gas marketing services business to capture value from locational and seasonal spreads. Additionally, changes in commodity prices, primarily driven by tight gas supplies, geopolitical events, and diminished gas production, subject a portion of Southern Company Gas' operations to earnings variability and may result in higher natural gas prices. Additional economic factors may contribute to this environment. The demand for natural gas may increase, which may cause natural gas prices to rise and drive higher volatility in the natural gas markets on a longer-term basis. Alternatively, a significant drop in oil and natural gas prices could lead to a consolidation of natural gas producers or reduced levels of natural gas production.

Earnings for both the electricity and natural gas businesses are subject to a variety of other factors. These factors include weather; competition; developing new and maintaining existing energy contracts and associated load requirements with wholesale customers; demand growth in data centers; customer energy conservation practices; the use of alternative energy sources by customers; government incentives to reduce overall energy usage; fuel, labor, and material prices in an environment of heightened inflation and material and labor supply chain disruptions; and the price elasticity of demand. Demand for electricity and natural gas in the Registrants' service territories is primarily driven by the pace of economic growth or decline that may be affected by changes in regional and global economic conditions, which may impact future earnings.

As part of its ongoing effort to adapt to changing market conditions, Southern Company continues to evaluate and consider a wide array of potential business strategies. These strategies may include business combinations, partnerships, and acquisitions involving other utility or non-utility businesses or properties, disposition of, or the sale of interests in, certain assets or businesses, internal restructuring, or some combination thereof. Furthermore, Southern Company may engage in new business ventures that arise from competitive and regulatory changes in the utility industry. Pursuit of any of the above strategies, or any combination thereof, may significantly affect the business operations, risks, and financial condition of Southern Company. In addition, Southern Power and Southern Company Gas regularly consider and evaluate joint development arrangements as well as acquisitions and/or dispositions of businesses and assets as part of their business strategies. See Note 15 to the financial statements in Item 8 of the Form 10-K, Note (K) to the Condensed Financial Statements herein, and "Construction Programs" herein for additional information.

For additional information relating to these issues, see RISK FACTORS in Item 1A and MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL in Item 7 of the Form 10-K.

Environmental Matters

See MANAGEMENT'S DISCUSSION AND ANALYSIS– FUTURE EARNINGS POTENTIAL– "Environmental Matters" and – FINANCIAL CONDITION AND LIQUIDITY– "Cash Requirements" in Item 7 and Note 3 to the financial statements under "Environmental Remediation" and Note 6 to the financial statements in Item 8 of the Form 10-K, as well as Note (C) to the Condensed Financial Statements under "General Litigation Matters" and "Environmental Remediation" herein, for additional information.

Environmental Laws and Regulations

Air Quality

On April 14, 2025, the U.S. Court of Appeals for the D.C. Circuit granted the EPA's motion to hold in abeyance the litigation regarding the 2015 Ozone National Ambient Air Quality Standards (NAAQS) Good Neighbor federal implementation plan (FIP).

On March 25, 2025, the U.S. Court of Appeals for the Fifth Circuit vacated and remanded the EPA's disapproval of the Mississippi state implementation plan (SIP) addressing interstate transport provisions of the Clean Air Act for the 2015 NAAQS. The decision protects the State of Mississippi from the requirements of the federal Good Neighbor plan unless or until the EPA properly disapproves Mississippi's SIP.

The ultimate impact of the FIP and associated legal matters cannot be determined at this time; however, implementation of the stayed FIP would likely result in increased compliance costs for the traditional electric operating companies.

Water Quality

On February 28, 2025, the U.S. Court of Appeals for the Eighth Circuit granted the EPA's motion to hold the 2024 ELG Rule litigation in abeyance for 60 days. On March 12, 2025, the EPA announced its intent to reconsider the standards finalized in the 2024 ELG Rule, including the new technology-based ELGs for leachate. On April 29, 2025, the EPA filed a motion with the U.S. Court of Appeals for the Eighth Circuit requesting an additional 60-day abeyance of the 2024 ELG Rule litigation. The ultimate impact of the 2024 ELG Rule and associated legal matters cannot be determined at this time; however, it may result in significant compliance costs.

Coal Combustion Residuals

On March 12, 2025, the EPA announced its intent to undertake several regulatory actions related to the CCR Rule, including reviewing the legacy rule and evaluating whether to grant short- and long-term relief, such as extending compliance deadlines.

On January 16, 2025, the EPA simultaneously published a direct final rule and companion proposed rule that included identical revisions to certain definitions in the 2024 final legacy CCR surface impoundment rule. On March 20, 2025, the EPA published a notice withdrawing its direct final rule and stating the EPA's intent to respond to comments received on the companion proposed rule. The ultimate impact of any final rule and associated legal matters cannot be determined at this time; however, it may result in significant compliance costs.

Based on compliance requirements for closure and monitoring of CCR units pursuant to state and federal CCR rules, the traditional electric operating companies have periodically updated, and expect to continue periodically updating, their related cost estimates and ARO liabilities for each CCR unit as additional information related to compliance monitoring, closure methodologies and strategies, schedules, and/or costs becomes available. Some of these updates have been, and future updates may be, material. The cost estimates for Alabama Power are based on closure-in-place for all surface impoundments. The cost estimates for Georgia Power and Mississippi Power are based on a combination of closure-in-place for some surface impoundments and closure by removal for others. Additionally, the closure designs and plans in the States of Alabama and Georgia are subject to approval by environmental regulatory agencies. Absent continued recovery of ARO costs through regulated rates, results of operations, cash flows, and financial condition for Southern Company and the traditional electric operating companies could be materially impacted.

Greenhouse Gases

On February 19, 2025, the U.S. Court of Appeals for the D.C. Circuit granted the EPA's motion to hold the litigation over the 2024 GHG Rules in abeyance for 60 days. On April 25, 2025, the U.S. Court of Appeals for the D.C. Circuit granted the EPA's motion requesting a continuing abeyance of the litigation over the 2024 GHG Rules. The EPA states in its motion that the agency will issue a proposed reconsideration rule in spring 2025 and a final reconsideration rule by December 2025. The ultimate impact of the final rules and associated legal matters cannot be determined at this time; however, it may result in significant compliance costs.

In 2009, the EPA finalized its determination that concentration of certain GHGs in the atmosphere represent a danger to public health and welfare, and such endangerment finding is a prerequisite for regulation of GHG emissions from electric generating units. On March 21, 2025, the EPA announced its intent to ask for public comment on its reconsideration of this endangerment finding. The ultimate impact of this action cannot be determined at this time.

Regulatory Matters

See Note 2 to the financial statements in Item 8 of the Form 10-K, OVERVIEW – "Recent Developments" herein, and Note (B) to the Condensed Financial Statements herein for a discussion of regulatory matters related to Alabama Power, Georgia Power, Mississippi Power, and Southern Company Gas, including items that could impact the applicable Registrants' future earnings, cash flows, and/or financial condition.

Construction Programs

The Southern Company system strategy continues to include developing and constructing new electric generating facilities, expanding and improving the electric transmission and electric and natural gas distribution systems, and undertaking projects to comply with environmental laws and regulations.

The traditional electric operating companies are engaged in continuous construction programs to accommodate existing and estimated future loads on their respective systems. Major generation construction projects are subject to state PSC approval in order to be included in retail rates, through which the traditional electric operating companies recover their investment and a return. See Note 2 to the financial statements under "Georgia Power – Integrated

Resource Plans" in Item 8 of the Form 10-K and Note (B) to the Condensed Financial Statements under "Georgia Power – Other Construction" herein for information regarding Georgia Power's construction of three simple cycle combustion turbines at Plant Yates.

Alabama Power executed an agreement to build a battery energy storage facility at the former Plant Gorgas site in Walker County, Alabama. The new Gorgas battery facility will have the capacity to store up to 150 MWs of electricity generated by other Alabama Power resources. Construction is expected to begin in 2025, with estimated completion by 2027.

Southern Power's construction program includes the Millers Branch solar project and the Kay Wind repowering project. The Kay Wind repowering project results in accelerated depreciation related to the equipment being replaced that will continue until commercial operation of the project, which is projected to occur in the third quarter 2026. At March 31, 2025, the remaining pre-tax accelerated depreciation, net of noncontrolling interest impacts, is projected to total approximately $75 million in 2025 and $40 million in 2026. The ultimate outcome of this matter cannot be determined at this time. See Note (K) to the Condensed Financial Statements under "Southern Power" herein for information relating to Southern Power's construction of renewable energy facilities.

Southern Company Gas is engaged in various infrastructure improvement programs designed to update or expand the natural gas distribution systems of the natural gas distribution utilities to improve reliability and resiliency, reduce emissions, and meet operational flexibility and growth. The natural gas distribution utilities recover their investment and a return associated with these infrastructure programs through their regulated rates, as approved by their applicable state regulatory agency. See Note 2 to the financial statements in Item 8 of the Form 10-K for additional information on Southern Company Gas' construction program.

See FINANCIAL CONDITION AND LIQUIDITY – "Cash Requirements" herein for additional information regarding the Registrants' capital requirements for their construction programs.

Southern Power's Power Sales Agreements

See MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Southern Power's Power Sales Agreements" in Item 7 of the Form 10-K for additional information.

At March 31, 2025, Southern Power's average investment coverage ratio for its generating assets, including those owned with various partners, based on the ratio of investment under contract to total investment using the respective facilities' net book value (or expected in-service value for facilities under construction) as the investment amount was 96% through 2029 and 87% through 2034, with an average remaining contract duration of approximately 12 years.

Income Tax Matters

See Note (G) to the Condensed Financial Statements herein and MANAGEMENT'S DISCUSSION AND ANALYSIS – FUTURE EARNINGS POTENTIAL – "Income Tax Matters" in Item 7 of the Form 10-K for additional information.

Georgia State Tax Legislation

On April 15, 2025, the State of Georgia enacted tax legislation that reduced the corporate income tax rate from 5.39% to 5.19% effective for the 2025 tax year. This legislation will reduce the amount of Southern Company's and certain subsidiaries' income tax expense in the State of Georgia and existing state net accumulated deferred tax liabilities, increase regulatory liabilities at Georgia Power and Southern Company Gas, and reduce Georgia Power's ability to utilize certain state tax credits in the State of Georgia. The legislation is not expected to have a material impact on the net income of the applicable Registrants. The ultimate outcome of this matter cannot be determined at this time.

General Litigation and Other Matters

The Registrants are involved in various matters being litigated and/or regulatory and other matters that could affect future earnings, cash flows, and/or financial condition. The ultimate outcome of such pending or potential litigation against each Registrant and any subsidiaries or regulatory and other matters cannot be determined at this time; however, for current proceedings and/or matters not specifically reported herein or in Notes (B) and (C) to the Condensed Financial Statements herein, management does not anticipate that the ultimate liabilities, if any, arising from such current proceedings and/or matters would have a material effect on such Registrant's financial statements. See Notes (B) and (C) to the Condensed Financial Statements for a discussion of various contingencies, including matters being litigated, regulatory matters, and other matters which may affect future earnings potential.