Acquisitions and Dispositions

(K)ACQUISITIONS AND DISPOSITIONS

See Note 15 to the financial statements in Item 8 of the Form 10-K for additional information.

Construction Projects

During the six months ended June 30, 2024, Southern Power completed construction of and placed in service the 150-MW South Cheyenne solar facility. In addition, Southern Power continued construction of the 200-MW first phase and the 180-MW second phase of the Millers Branch solar facility. Southern Power also committed to expand construction by an additional 90 MWs through a third phase of the Millers Branch solar project. At June 30, 2024, the total cost of construction incurred for the Millers Branch project was $117 million, which is primarily included in CWIP.

Project FacilityResourceApproximate Nameplate Capacity (MW)LocationProjected/Actual CODPPA Contract Period
Projects Completed During the Six Months Ended June 30, 2024
South CheyenneSolar150Laramie County, WYSecond quarter 202420 years
Projects Under Construction at June 30, 2024
Millers Branch(*)
Phase ISolar200Haskell County, TXFourth quarter 202520 years
Phase IISolar180Haskell County, TXSecond quarter 202615 years
Phase IIISolar90Haskell County, TXFourth quarter 202615 years

(*)The Millers Branch project includes an option to expand capacity up to a total of approximately 500 MWs.