Accounting Policies
Application of Critical Accounting Policies and Estimates
The Registrants prepare their financial statements in accordance with GAAP, which requires the use of estimates, judgments, and assumptions. Significant accounting policies are described in the notes to the financial statements. Detailed further herein are certain estimates made in the application of these policies that may have a material impact on the results of operations, financial condition, and related disclosures of the applicable Registrants (as indicated in the section descriptions herein). Different assumptions and measurements could produce estimates that are significantly different from those recorded in the financial statements. Senior management has reviewed and discussed these critical accounting policies and estimates with the Audit Committee of Southern Company's Board of Directors.
Utility Regulation (Southern Company, Alabama Power, Georgia Power, Mississippi Power, and Southern Company Gas)
The traditional electric operating companies and the natural gas distribution utilities are subject to retail regulation by their respective state PSCs or other applicable state regulatory agencies and wholesale regulation by the FERC. These regulatory agencies set the rates the traditional electric operating companies and the natural gas distribution utilities are permitted to charge customers based on allowable costs, including a reasonable ROE. As a result, the traditional electric operating companies and the natural gas distribution utilities apply accounting standards which require the financial statements to reflect the effects of rate regulation. Through the ratemaking process, the regulators may require the inclusion of costs or revenues in periods different than when they would be recognized by a non-regulated company. This treatment may result in the deferral of expenses and the recording of related regulatory assets based on anticipated future recovery through rates or the deferral of gains or creation of liabilities and the recording of related regulatory liabilities. The application of the accounting standards for rate regulated entities also impacts their financial statements as a result of the estimates of allowable costs used in the ratemaking process. These estimates may differ from those actually incurred by the traditional electric operating companies and the natural gas distribution utilities; therefore, the accounting estimates inherent in specific costs such as depreciation, AROs, and pension and other postretirement benefits have less of a direct impact on the results of operations and financial condition of the applicable Registrants than they would on a non-regulated company. Additionally, a regulatory agency may disallow recovery of all or a portion of certain assets. See Note 2 to the financial statements under "Southern Company Gas – Infrastructure Replacement Programs and Capital Projects – Nicor Gas" for information regarding the disallowance of certain capital investments at Nicor Gas and "Estimated Cost, Schedule, and Rate Recovery for the Construction of Plant Vogtle Units 3 and 4" herein for information regarding the Prudency Stipulation related to Georgia Power's construction of Plant Vogtle Units 3 and 4.
Revenues related to regulated utility operations as a percentage of total operating revenues in 2023 for the applicable Registrants were as follows: 89% for Southern Company, 98% for Alabama Power, 96% for Georgia Power, 99% for Mississippi Power, and 87% for Southern Company Gas.
As reflected in Note 2 to the financial statements, significant regulatory assets and liabilities have been recorded. Management reviews the ultimate recoverability of these regulatory assets and any requirement to refund these regulatory liabilities based on applicable regulatory guidelines and GAAP. However, adverse legislative, judicial, or regulatory actions could materially impact
II-48 the amounts of such regulatory assets and liabilities and could adversely impact the financial statements of the applicable Registrants.
Estimated Cost, Schedule, and Rate Recovery for the Construction of Plant Vogtle Units 3 and 4
(Southern Company and Georgia Power)
In 2016, the Georgia PSC approved a settlement agreement (Vogtle Cost Settlement Agreement) resolving certain prudency matters in connection with Georgia Power's fifteenth VCM report. In January 2018, the Georgia PSC issued an order approving Georgia Power's seventeenth VCM report, which included a modification of the Vogtle Cost Settlement Agreement. The January 2018 order and the modified Vogtle Cost Settlement Agreement resolved certain regulatory matters related to Plant Vogtle Units 3 and 4 including, but not limited to: (i) Georgia Power's total project capital cost forecast of $7.3 billion (net of $1.7 billion received under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds) was found reasonable and (ii) a prudence proceeding on cost recovery would occur subsequent to achieving fuel load for Unit 4. On December 19, 2023, the Georgia PSC voted to approve Georgia Power's Application as modified by the Prudency Stipulation. Under the terms of the approved Prudency Stipulation, Georgia Power will recover $7.562 billion in total construction and capital costs and associated retail rate base items of $1.02 billion, which includes AFUDC financing costs above $4.418 billion (the Georgia PSC-certified amount) up to $7.562 billion. The approval of the Application and the Prudency Stipulation resolves all issues for determination by the Georgia PSC regarding the reasonableness, prudence, and cost recovery for the remaining Plant Vogtle Units 3 and 4 construction and capital costs not already in retail base rates.
As of December 31, 2023, Georgia Power revised its total project capital cost forecast to $10.8 billion (net of $1.7 billion received under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds). This forecast includes construction contingency of $36 million and is based on the actual in-service date of July 2023 for Unit 3 and a projected in-service date during the second quarter 2024 for Unit 4. Since 2018, established construction contingency and additional costs totaling $2.7 billion have been assigned to the base capital cost forecast. Georgia Power did not seek rate recovery for the $0.7 billion increase to the base capital cost forecast included in the nineteenth VCM report and charged to income by Georgia Power in the second quarter 2018 and, until the prudency proceeding described above, did not seek rate recovery for subsequent construction and additional contingency costs assigned to the base capital cost forecast. After considering the significant level of uncertainty that existed regarding the future recoverability of these costs since the ultimate outcome of these matters was subject to the outcome of assessments by management, as well as Georgia PSC decisions in the related regulatory proceedings, Georgia Power recorded total pre-tax charges to income of $1.1 billion ($0.8 billion after tax) in 2018; $149 million ($111 million after tax) and $176 million ($131 million after tax) in the second quarter and the fourth quarter 2020, respectively; $48 million ($36 million after tax), $460 million ($343 million after tax), $264 million ($197 million after tax), and $480 million ($358 million after tax) in the first quarter 2021, the second quarter 2021, the third quarter 2021, and the fourth quarter 2021, respectively; and $36 million ($27 million after tax), $32 million ($24 million after tax), and $148 million ($110 million after tax) in the second quarter 2022, the third quarter 2022, and the fourth quarter 2022, respectively. As a result of the Georgia PSC's approval of the Prudency Stipulation, Georgia Power recorded a pre-tax credit to income of approximately $228 million ($170 million after tax) in the fourth quarter 2023 to recognize CWIP costs previously charged to income, which are now recoverable through retail rates. Associated AFUDC on these costs was also recognized.
In September 2022, Georgia Power and MEAG Power reached an agreement to resolve a dispute regarding the cost-sharing and tender provisions of the Global Amendments (as defined in Note 2 to the financial statements under "Georgia Power – Nuclear Construction – Joint Owner Contracts"). Under the terms of the agreement, among other items, (i) MEAG Power will not exercise its tender option and will retain its full ownership interest in Plant Vogtle Units 3 and 4; (ii) Georgia Power will reimburse a portion of MEAG Power's costs of construction for Plant Vogtle Units 3 and 4 as such costs are incurred and with no further adjustment for force majeure costs, which payments will total approximately $92 million based on the current project capital cost forecast; and (iii) Georgia Power will reimburse 20% of MEAG Power's costs of construction with respect to any amounts over the current project capital cost forecast, with no further adjustment for force majeure costs.
On October 5, 2023 and October 17, 2023, Georgia Power reached agreements with OPC and Dalton, respectively, to resolve its respective dispute with each of OPC and Dalton regarding the cost-sharing and tender provisions of the Global Amendments. Under the terms of the agreements with OPC and Dalton, among other items, (i) each of OPC and Dalton retracted its exercise of the tender option and will retain its full ownership interest in Plant Vogtle Units 3 and 4, (ii) Georgia Power made payments immediately after execution of the agreements of $308 million and $17 million to OPC and Dalton, respectively, representing payment for a portion of each of OPC's and Dalton's costs of construction for Plant Vogtle Units 3 and 4 previously incurred, (iii) Georgia Power will pay a portion of each of OPC's and Dalton's further costs of construction for Plant Vogtle Units 3 and 4 as such costs are incurred and with no further adjustment for force majeure costs, which payments will be in an aggregate amount of approximately $105 million and $6 million for OPC and Dalton, respectively, based on the current project capital cost forecast,
II-49 and (iv) Georgia Power will pay 66% of each of OPC's and Dalton's costs of construction with respect to any amounts above the current project capital cost forecast, with no further adjustment for force majeure costs.
Georgia Power recorded pre-tax charges to income through the fourth quarter 2022 of $407 million ($304 million after tax) associated with the cost-sharing provisions of the Global Amendments, including the settlement with MEAG Power. Based on the current project capital cost forecast and the settlements with OPC and Dalton described above, Georgia Power recorded a pre-tax charge to income of approximately $160 million ($120 million after tax) in the third quarter 2023. These charges are included in the total project capital cost forecast and will not be recovered from retail customers.
As part of its ongoing processes, Southern Nuclear continues to evaluate cost and schedule forecasts for Unit 4 on a regular basis to incorporate current information available, particularly in the areas of start-up testing and related test results and engineering support.
The projected schedule for Unit 4 significantly depends on the progression of start-up and pre-operational testing, which may be impacted by equipment or other operational failures. Any further delays could result in a later in-service date and cost increases.
Various design and other licensing-based compliance matters may result in additional license amendment requests or require other resolution. If any license amendment requests or other licensing-based compliance issues are not resolved in a timely manner, there may be delays in the Unit 4 project schedule that could result in increased costs.
The ultimate outcome of these matters cannot be determined at this time. However, any extension of the in-service date beyond June 2024 for Unit 4, including the current level of cost sharing described in Note 2, is estimated to result in additional base capital costs for Georgia Power of up to $25 million per month as well as any additional related construction, support resources, or testing costs. Pursuant to the Prudency Stipulation, any further changes to the capital cost forecast will not be recoverable through regulated rates and will be required to be charged to income, and such charges could be material.
Given the significant complexity involved in estimating the future costs to complete construction and start-up of Plant Vogtle Unit 4, as well as the potential impact on results of operations and cash flows, Southern Company and Georgia Power consider these items to be critical accounting estimates. See Note 2 to the financial statements under "Georgia Power – Nuclear Construction" for additional information.
Accounting for Income Taxes (Southern Company, Georgia Power, Mississippi Power, Southern Power, and Southern Company Gas)
The consolidated income tax provision and deferred income tax assets and liabilities, as well as any unrecognized tax benefits and valuation allowances, require significant judgment and estimates. These estimates are supported by historical tax return data, reasonable projections of taxable income, the ability and intent to implement tax planning strategies if necessary, and interpretations of applicable tax laws and regulations across multiple taxing jurisdictions. The effective tax rate reflects the statutory tax rates and calculated apportionments for the various states in which the Southern Company system operates.
Southern Company files a consolidated federal income tax return and the Registrants file various state income tax returns, some of which are combined or unitary. Under a joint consolidated income tax allocation agreement, each Southern Company subsidiary's current and deferred tax expense is computed on a stand-alone basis and each subsidiary is allocated an amount of tax similar to that which would be paid if it filed a separate income tax return. In accordance with IRS regulations, each company is jointly and severally liable for the federal tax liability. Certain deductions and credits can be limited or utilized at the consolidated or combined level resulting in tax credit and/or state NOL carryforwards that would not otherwise result on a stand-alone basis. Utilization of these carryforwards and the assessment of valuation allowances are based on significant judgment and extensive analysis of Southern Company's and its subsidiaries' current financial position and results of operations, including currently available information about future years, to estimate when future taxable income will be realized. See Note 10 to the financial statements under "Deferred Tax Assets and Liabilities – Tax Credit Carryforwards" and " – Net Operating Loss Carryforwards" for additional information.
Current and deferred state income tax liabilities and assets are estimated based on laws of multiple states that determine the income to be apportioned to their jurisdictions. States have various filing methodologies and utilize specific formulas to calculate the apportionment of taxable income. The calculation of deferred state taxes considers apportionment factors and filing methodologies that are expected to apply in future years. Any apportionments and/or filing methodologies ultimately finalized in a manner inconsistent with expectations could have a material effect on the financial statements of the applicable Registrants.
Asset Retirement Obligations (Southern Company, Alabama Power, Georgia Power, Mississippi Power, and Southern Company Gas)
Estimating AROs requires significant judgment. AROs are computed as the present value of the estimated costs for an asset's future retirement and are recorded in the period in which the liability is incurred. The estimated costs are capitalized as part of the
II-50 related long-lived asset and depreciated over the asset's useful life. In the absence of quoted market prices, AROs are estimated using present value techniques in which estimates of future cash outlays associated with the asset retirements are discounted using a credit-adjusted risk-free rate. Estimates of the timing and amounts of future cash outlays are based on projections of when and how the assets will be retired and the cost of future removal activities.
The ARO liabilities for the traditional electric operating companies primarily relate to facilities that are subject to the CCR Rule and the related state rules, principally ash ponds. In addition, Alabama Power and Georgia Power have retirement obligations related to the decommissioning of nuclear facilities (Alabama Power's Plant Farley and Georgia Power's ownership interests in Plant Hatch and Plant Vogtle Units 1 through 3). Other significant AROs include various landfill sites and asbestos removal for Alabama Power, Georgia Power, and Mississippi Power and gypsum cells and mine reclamation for Mississippi Power.
The traditional electric operating companies and Southern Company Gas also have identified other retirement obligations, such as obligations related to certain electric transmission and distribution facilities, certain asbestos-containing material within long-term assets not subject to ongoing repair and maintenance activities, certain wireless communication towers, the disposal of polychlorinated biphenyls in certain transformers, leasehold improvements, equipment on customer property, and property associated with the Southern Company system's rail lines and natural gas pipelines. However, liabilities for the removal of these assets have not been recorded because the settlement timing for certain retirement obligations related to these assets is indeterminable and, therefore, the fair value of the retirement obligations cannot be reasonably estimated. A liability for these retirement obligations will be recognized when sufficient information becomes available to support a reasonable estimation of the ARO.
The cost estimates for AROs related to the disposal of CCR are based on information using various assumptions related to closure and post-closure costs, timing of future cash outlays, inflation and discount rates, and the potential methods for complying with the CCR Rule and the related state rules. The traditional electric operating companies have periodically updated, and expect to continue periodically updating, their related cost estimates and ARO liabilities for each CCR unit as additional information related to these assumptions becomes available. Some of these updates have been, and future updates may be, material. The cost estimates for Alabama Power are based on closure-in-place for all ash ponds. The cost estimates for Georgia Power and Mississippi Power are based on a combination of closure-in-place for some ash ponds and closure by removal for others. Additionally, the closure designs and plans in the States of Alabama and Georgia are subject to approval by environmental regulatory agencies. See Note 6 to the financial statements and FUTURE EARNINGS POTENTIAL – "Environmental Matters – Environmental Laws and Regulations – Coal Combustion Residuals" herein for additional information, including updates to AROs related to ash ponds recorded during 2023 by certain Registrants.
Pension and Other Postretirement Benefits (Southern Company, Alabama Power, Georgia Power, Mississippi Power, and Southern Company Gas)
The applicable Registrants' calculations of pension and other postretirement benefits expense are dependent on a number of assumptions. These assumptions include discount rates, healthcare cost trend rates, expected long-term rate of return (LRR) on plan assets, mortality rates, expected salary and wage increases, and other factors. Components of pension and other postretirement benefits expense include interest and service cost on the pension and other postretirement benefit plans, expected return on plan assets, and amortization of certain unrecognized costs and obligations. Actual results that differ from the assumptions utilized are accumulated and amortized over future periods and, therefore, generally affect recognized expense and the recorded obligation in future periods. While the applicable Registrants believe the assumptions used are appropriate, differences in actual experience or significant changes in assumptions would affect their pension and other postretirement benefit costs and obligations.
Key elements in determining the applicable Registrants' pension and other postretirement benefit expense are the LRR and the discount rate used to measure the benefit plan obligations and the periodic benefit plan expense for future periods. For purposes of determining the applicable Registrants' liabilities related to the pension and other postretirement benefit plans, Southern Company discounts the future related cash flows using a single-point discount rate for each plan developed from the weighted average of market-observed yields for high quality fixed income securities with maturities that correspond to expected benefit payments. The discount rate assumption impacts both the service cost and non-service costs components of net periodic benefit costs as well as the projected benefit obligations.
The LRR on pension and other postretirement benefit plan assets is based on Southern Company's investment strategy, as described in Note 11 to the financial statements, historical experience, and expectations that consider external actuarial advice, and represents the average rate of earnings expected over the long term on the assets invested to provide for anticipated future benefit payments. Southern Company determines the amount of the expected return on plan assets component of non-service costs by applying the LRR of various asset classes to Southern Company's target asset allocation. The LRR only impacts the non-service costs component of net periodic benefit costs for the following year and is set annually at the beginning of the year.
II-51
The following table illustrates the sensitivity to changes in the applicable Registrants' long-term assumptions with respect to the discount rate, salary increases, and the long-term rate of return on plan assets:
| Increase/(Decrease) in | |||
| 25 Basis Point Change in: | Total Benefit Expense for 2024 | Projected Obligation for Pension Plan at December 31, 2023 | Projected Obligation forOther PostretirementBenefit Plans at December 31, 2023 |
|---|---|---|---|
| (in millions) | |||
| Discount rate: | |||
| Southern Company | $35/$(32) | $419/$(397) | $34/$(32) |
| Alabama Power | $9/$(9) | $101/$(96) | $9/$(8) |
| Georgia Power | $9/$(9) | $122/$(116) | $11/$(11) |
| Mississippi Power | $2/$(1) | $18/$(18) | $1/$(1) |
| Southern Company Gas | $2/$(2) | $27/$(25) | $4/$(4) |
| Salaries: | |||
| Southern Company | $18/$(17) | $87/$(84) | $–/$– |
| Alabama Power | $5/(5) | $24/$(23) | $–/$– |
| Georgia Power | $5/(5) | $23/$(23) | $–/$– |
| Mississippi Power | $1/$(1) | $4/$(4) | $–/$– |
| Southern Company Gas | $1/$(1) | $3/$(3) | $–/$– |
| Long-term return on plan assets: | |||
| Southern Company | $41/$(41) | N/A | N/A |
| Alabama Power | $10/$(10) | N/A | N/A |
| Georgia Power | $13/$(13) | N/A | N/A |
| Mississippi Power | $2/$(2) | N/A | N/A |
| Southern Company Gas | $3/$(3) | N/A | N/A |
See Note 11 to the financial statements for additional information regarding pension and other postretirement benefits.
Impairment (Southern Company, Southern Power, and Southern Company Gas)
Goodwill (Southern Company and Southern Company Gas)
The acquisition method of accounting for business combinations requires the assets acquired and liabilities assumed to be recorded at the date of acquisition at their respective estimated fair values. The applicable Registrants have recognized goodwill as of the date of their acquisitions, as a residual over the fair values of the identifiable net assets acquired. Goodwill is recorded at the reporting unit level, which is the operating segment or a business one level below the operating segment (a component), if discrete financial information is prepared and regularly reviewed by management. Components are aggregated if they have similar economic characteristics. Goodwill is tested for impairment at the reporting unit level on an annual basis in the fourth quarter of the year and on an interim basis if events and circumstances occur that indicate goodwill may be impaired.
Goodwill is evaluated for impairment either under the qualitative assessment option or the quantitative option to determine the fair value of the reporting unit. If goodwill is determined to be impaired, an impairment loss measured at the amount by which the reporting unit's carrying amount exceeds its fair value, not to exceed the carrying amount of goodwill, is recorded.
Goodwill for Southern Company and Southern Company Gas was $5.2 billion and $5.0 billion, respectively, at December 31, 2023. During 2022, Southern Company recorded a $119 million impairment loss as a result of its annual goodwill impairment test for PowerSecure.
The judgments made in determining the estimated fair value assigned to each class of assets acquired and liabilities assumed, as well as asset lives, can significantly impact the applicable Registrant's results of operations. Fair values and useful lives are determined based on, among other factors, the expected future period of benefit of the asset, the various characteristics of the asset, and projected cash flows. As the determination of an asset's fair value and useful life involves management making certain estimates and because these estimates form the basis for the determination of whether or not an impairment charge should be recorded, the applicable Registrants consider these estimates to be critical accounting estimates.
II-52
See Note 1 to the financial statements under "Goodwill and Other Intangible Assets" for additional information regarding the applicable Registrants' goodwill.
Long-Lived Assets (Southern Company, Southern Power, and Southern Company Gas)
The applicable Registrants assess their other long-lived assets for impairment whenever events or changes in circumstances indicate that an asset's carrying amount may not be recoverable. If an impairment indicator exists, the asset is tested for recoverability by comparing the asset carrying amount to the sum of the undiscounted expected future cash flows directly attributable to the asset's use and eventual disposition. If the estimate of undiscounted future cash flows is less than the carrying amount of the asset, the fair value of the asset is determined and a loss is recorded equal to the difference between the carrying amount and the fair value of the asset. In addition, when assets are identified as held for sale, an impairment loss is recognized to the extent the carrying amount of the assets or asset group exceeds their fair value less cost to sell. A high degree of judgment is required in developing estimates related to these evaluations, which are based on projections of various factors, some of which have been quite volatile in recent years.
Southern Power's investments in long-lived assets are primarily generation assets. Excluding the natural gas distribution utilities, Southern Company Gas' investments in long-lived assets are primarily natural gas transportation assets.
For Southern Power, examples of impairment indicators could include, but are not limited to, significant changes in construction schedules, current period losses combined with a history of losses or a projection of continuing losses, a significant decrease in market prices, changes in tax legislation, the inability to remarket generating capacity for an extended period, the unplanned termination of a customer contract, or the inability of a customer to perform under the terms of the contract. For Southern Company Gas, examples of impairment indicators could include, but are not limited to, significant changes in the U.S. natural gas storage market, construction schedules, current period losses combined with a history of losses or a projection of continuing losses, a significant decrease in market prices, the inability to renew or extend customer contracts or the inability of a customer to perform under the terms of the contract, attrition rates, or the inability to deploy a development project.
As the determination of the expected future cash flows generated from an asset, an asset's fair value, and useful life involves management making certain estimates and because these estimates form the basis for the determination of whether or not an impairment charge should be recorded, the applicable Registrants consider these estimates to be critical accounting estimates.
During 2021, Southern Company recorded impairment charges totaling $7 million ($6 million after tax) related to its leveraged lease investments. During 2022, Southern Company Gas recorded pre-tax impairment charges totaling $131 million ($99 million after tax) related to natural gas storage facilities. During 2021, Southern Company Gas recorded total pre-tax impairment charges of $84 million ($67 million after tax) related to its equity method investment in the PennEast Pipeline project. See Notes 7 and 9 to the financial statements under "Southern Company Gas" and "Southern Company Leveraged Lease," respectively, and Note 15 to the financial statements for additional information on recent asset impairments.
Revenue Recognition (Southern Power)
Southern Power's power sale transactions, which include PPAs, are classified in one of four general categories: leases, normal sale derivatives or contracts with customers, derivatives designated as cash flow hedges, and derivatives not designated as hedges. Southern Power's revenues are dependent upon significant judgments used to determine the appropriate transaction classification, which must be documented upon the inception of each contract. The two categories with the most judgment required for Southern Power are described further below.
Lease Transactions
Southern Power considers the terms of a sales contract to determine whether it should be accounted for as a lease. A contract is or contains a lease if the contract conveys the right to control the use of identified property, plant, or equipment for a period of time in exchange for consideration. If the contract meets the criteria for a lease, Southern Power performs further analysis to determine whether the lease is classified as operating, financing, or sales-type. Generally, Southern Power's power sales contracts that are determined to be leases are accounted for as operating leases and the capacity revenue is recognized on a straight-line basis over the term of the contract and is included in Southern Power's operating revenues. Energy revenues and other contingent revenues are recognized in the period the energy is delivered or the service is rendered. For those contracts that are determined to be sales-type leases, capacity revenues are recognized by accounting for interest income on the net investment in the lease and are included in Southern Power's operating revenues. See Note 9 to the financial statements for additional information.
Normal Sale Derivative Transactions and Contracts with Customers
If the power sales contract is not classified as a lease, Southern Power further considers whether the contract meets the definition of a derivative. If the contract does meet the definition of a derivative, Southern Power will assess whether it can be designated as
II-53 a normal sale contract. The determination of whether a contract can be designated as a normal sale contract requires judgment, including whether the sale of electricity involves physical delivery in quantities within Southern Power's available generating capacity and that the purchaser will take quantities expected to be used or sold in the normal course of business.
Contracts that do not meet the definition of a derivative or are designated as normal sales are accounted for as revenue from contracts with customers. For contracts that have a capacity charge, the revenue is generally recognized in the period that it becomes billable. Revenues related to energy and ancillary services are recognized in the period the energy is delivered or the service is rendered. See Note 4 to the financial statements for additional information.
Acquisition Accounting (Southern Power)
Southern Power may acquire generation assets as part of its overall growth strategy. At the time of an acquisition, Southern Power will assess if these assets and activities meet the definition of a business. Acquisitions that meet the definition of a business are accounted for under the acquisition method, whereby the identifiable assets acquired, liabilities assumed, and any noncontrolling interests (including any intangible assets, primarily related to acquired PPAs) are recognized and measured at fair value. Assets acquired that do not meet the definition of a business are accounted for as an asset acquisition. The purchase price of each asset acquisition is allocated based on the relative fair value of assets acquired.
Determining the fair value of assets acquired and liabilities assumed requires management judgment and Southern Power may engage independent valuation experts to assist in this process. Fair values are determined by using market participant assumptions and typically include the timing and amounts of future cash flows, incurred construction costs, the nature of acquired contracts, discount rates, power market prices, and expected asset lives. For potential or successful acquisitions that meet the definition of a business, any due diligence or transaction costs incurred are expensed as incurred. If the acquisition is an asset acquisition, direct and incremental transaction costs can be capitalized as a component of the cost of the assets acquired.
See Note 13 to the financial statements for additional fair value information and Note 15 to the financial statements for additional information on recent acquisitions.
Variable Interest Entities (Southern Power)
Southern Power enters into partnerships with varying ownership structures. Upon entering into these arrangements, membership interests and other variable interests are evaluated to determine if the legal entity is a VIE. If the legal entity is a VIE, Southern Power will assess if it has both the power to direct the activities of the VIE that most significantly impact the VIE's economic performance and the obligation to absorb losses or the right to receive benefits from the VIE that could potentially be significant to the VIE, making it the primary beneficiary. Making this determination may require significant management judgment.
If Southern Power is the primary beneficiary and is considered to have a controlling ownership, the assets, liabilities, and results of operations of the entity are consolidated. If Southern Power is not the primary beneficiary, the legal entity is generally accounted for under the equity method of accounting. Southern Power reconsiders its conclusions as to whether the legal entity is a VIE and whether it is the primary beneficiary for events that impact the rights of variable interests, such as ownership changes in membership interests.
Southern Power has controlling ownership in certain legal entities for which the contractual provisions represent profit-sharing arrangements because the allocations of cash distributions and tax benefits are not based on fixed ownership percentages. For these arrangements, the noncontrolling interest is accounted for under a balance sheet approach utilizing the HLBV method. The HLBV method calculates each partner's share of income based on the change in net equity the partner can legally claim in a HLBV at the end of the period compared to the beginning of the period.
Contingent Obligations (All Registrants)
The Registrants are subject to a number of federal and state laws and regulations, as well as other factors and conditions that subject them to environmental, litigation, and other risks. See FUTURE EARNINGS POTENTIAL herein and Notes 2 and 3 to the financial statements for more information regarding certain of these contingencies. The Registrants periodically evaluate their exposure to such risks and record reserves for those matters where a non-tax-related loss is considered probable and reasonably estimable. The adequacy of reserves can be significantly affected by external events or conditions that can be unpredictable; thus, the ultimate outcome of such matters could materially affect the results of operations, cash flows, or financial condition of the Registrants.
Recently Issued Accounting Standards
See Note 1 to the financial statements under "Recently Adopted Accounting Standards" for additional information.
II-54