ENTERGY ARKANSAS, LLC
For the period ended Sep 30, 2025. Filed Oct 31, 2025.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Sep 30, 2025 · Filed Oct 31, 2025
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Definitionsvii
DEFINITIONS
Certain abbreviations or acronyms used in the text and notes are defined below:
| Abbreviation or Acronym | Term |
|---|---|
| AFUDC | Allowance for Funds Used During Construction |
| ALJ | Administrative Law Judge |
| ANO 1 and 2 | Units 1 and 2 of Arkansas Nuclear One (nuclear), owned by Entergy Arkansas |
| APSC | Arkansas Public Service Commission |
| Board | Board of Directors of Entergy Corporation |
| Cajun | Cajun Electric Power Cooperative, Inc. |
| capacity factor | Actual plant output divided by maximum potential plant output for the period |
| City Council | Council of the City of New Orleans, Louisiana |
| COVID-19 | The novel coronavirus disease declared a pandemic by the World Health Organization and the Centers for Disease Control and Prevention in March 2020 |
| D.C. Circuit | U.S. Court of Appeals for the District of Columbia Circuit |
| DOE | United States Department of Energy |
| Entergy | Entergy Corporation and its direct and indirect subsidiaries |
| Entergy Corporation | Entergy Corporation, a Delaware corporation |
| Entergy Gulf States, Inc. | Predecessor company for financial reporting purposes to Entergy Gulf States Louisiana that included the assets and business operations of both Entergy Gulf States Louisiana and Entergy Texas |
| Entergy Gulf States Louisiana | Entergy Gulf States Louisiana, L.L.C., a Louisiana limited liability company formally created as part of the jurisdictional separation of Entergy Gulf States, Inc. and the successor company to Entergy Gulf States, Inc. for financial reporting purposes. The term is also used to refer to the Louisiana jurisdictional business of Entergy Gulf States, Inc., as the context requires. Effective October 1, 2015, the business of Entergy Gulf States Louisiana was combined with Entergy Louisiana. |
| Entergy Louisiana | Entergy Louisiana, LLC, a Texas limited liability company formally created as part of the combination of Entergy Gulf States Louisiana and the company formerly known as Entergy Louisiana, LLC (Old Entergy Louisiana) into a single public utility company and the successor to Old Entergy Louisiana for financial reporting purposes |
| Entergy Texas | Entergy Texas, Inc., a Texas corporation formally created as part of the jurisdictional separation of Entergy Gulf States, Inc. The term is also used to refer to the Texas jurisdictional business of Entergy Gulf States, Inc., as the context requires. |
| Entergy Wholesale Commodities | Prior to January 1, 2023, one of Entergy’s reportable business segments consisting of non-utility business activities primarily comprised of the ownership, operation, and decommissioning of nuclear power plants, the ownership of interests in non-nuclear power plants, and the sale of the electric power produced by its operating power plants to wholesale customers |
| EPA | United States Environmental Protection Agency |
| FERC | Federal Energy Regulatory Commission |
| Form 10-K | Annual Report on Form 10-K for the calendar year ended December 31, 2024, filed with the SEC by Entergy Corporation and its Registrant Subsidiaries |
| GAAP | Generally Accepted Accounting Principles |
| Grand Gulf | Unit No. 1 of Grand Gulf Nuclear Station (nuclear), 90% owned or leased by System Energy |
| GWh | Gigawatt-hour(s), which equals one million kilowatt-hours |
| Independence | Independence Steam Electric Station (coal), owned 16% by Entergy Arkansas, 25% by Entergy Mississippi, and 7% by Entergy Power, LLC |
| IRS | Internal Revenue Service |
vii
DEFINITIONS (Continued)
| Abbreviation or Acronym | Term |
|---|---|
| ISO | Independent System Operator |
| kV | Kilovolt |
| kW | Kilowatt, which equals one thousand watts |
| kWh | Kilowatt-hour(s) |
| LPSC | Louisiana Public Service Commission |
| LURC | Louisiana Utilities Restoration Corporation |
| MISO | Midcontinent Independent System Operator, Inc., a regional transmission organization |
| MMBtu | One million British Thermal Units |
| MPSC | Mississippi Public Service Commission |
| MW | Megawatt(s), which equals one thousand kilowatts |
| MWh | Megawatt-hour(s) |
| Nelson Unit 6 | Unit No. 6 (coal) of the Nelson Steam Electric Generating Station, 70% of which is co-owned by Entergy Louisiana (57.5%) and Entergy Texas (42.5%) and 10.9% of which is owned by EAM Nelson Holding, LLC |
| Net debt to net capital ratio | Gross debt less cash and cash equivalents divided by total capitalization less cash and cash equivalents, which is a non-GAAP measure |
| NRC | Nuclear Regulatory Commission |
| Palisades | Palisades Nuclear Plant (nuclear), previously owned as part of Entergy’s non-utility business, which ceased power production in May 2022 and was sold in June 2022 |
| Parent & Other | The portions of Entergy not included in the Utility segment, primarily consisting of the activities of the parent company, Entergy Corporation, and other business activity, including Entergy’s non-utility operations business which owns interests in non-nuclear power plants that sell the electric power produced by those plants to wholesale customers and also provides decommissioning services to nuclear power plants owned by non-affiliated entities in the United States |
| PPA | Purchased power agreement or power purchase agreement |
| PUCT | Public Utility Commission of Texas |
| Registrant Subsidiaries | Entergy Arkansas, LLC, Entergy Louisiana, LLC, Entergy Mississippi, LLC, Entergy New Orleans, LLC, Entergy Texas, Inc., and System Energy Resources, Inc. |
| River Bend | River Bend Station (nuclear), owned by Entergy Louisiana |
| SEC | Securities and Exchange Commission |
| System Agreement | Agreement, effective January 1, 1983, as modified, among the Utility operating companies relating to the sharing of generating capacity and other power resources. The agreement terminated effective August 2016. |
| System Energy | System Energy Resources, Inc. |
| Unit Power Sales Agreement | Agreement, dated as of June 10, 1982, as amended and approved by the FERC, among Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and System Energy, relating to the sale of capacity and energy from System Energy’s share of Grand Gulf |
| Utility | Entergy’s reportable segment that generates, transmits, distributes, and sells electric power, with a small amount of natural gas distribution in portions of Louisiana |
| Utility operating companies | Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas |
| Waterford 3 | Unit No. 3 (nuclear) of the Waterford Steam Electric Station, owned by Entergy Louisiana |
viii
DEFINITIONS (Concluded)
| Abbreviation or Acronym | Term |
|---|---|
| weather-adjusted usage | Electric usage excluding the effects of deviations from normal weather |
| White Bluff | White Bluff Steam Electric Generating Station, 57% owned by Entergy Arkansas |
ix x
Entergy operates primarily through a single reportable segment, Utility. The Utility segment includes the generation, transmission, distribution, and sale of electric power in portions of Arkansas, Mississippi, Texas, and Louisiana, including the City of New Orleans; and included operation of a small natural gas distribution business in portions of Louisiana through June 30, 2025. See Note 13 to the financial statements herein and the “Held for Sale - Natural Gas Distribution Businesses” section in Note 14 to the financial statements in the Form 10-K for discussion of the sale of the Entergy New Orleans and Entergy Louisiana natural gas distribution businesses on July 1, 2025. See Note 7 to the financial statements herein for discussion of and financial information regarding Entergy’s reportable segment.
Following are income statement variances for Utility, Parent & Other, and Entergy comparing the third quarter 2025 to the third quarter 2024 showing how much the line item increased or (decreased) in comparison to the prior period.
| Utility | Parent &Other (a) | Entergy | |
|---|---|---|---|
| (In Thousands) | |||
| 2024 Net Income (Loss) Attributable to Entergy Corporation | $786,547 | ($141,607) | $644,940 |
| Operating revenues | 427,194 | (4,275) | 422,919 |
| Fuel, fuel-related expenses, and gas purchased for resale | 179,964 | (5,148) | 174,816 |
| Purchased power | 60,485 | (3,817) | 56,668 |
| Other regulatory charges (credits) - net | 79,096 | — | 79,096 |
| Other operation and maintenance | 49,804 | (1,525) | 48,279 |
| Asset write-offs, impairments, and related charges | 12,795 | — | 12,795 |
| Taxes other than income taxes | 40,124 | 120 | 40,244 |
| Depreciation and amortization | 26,864 | 40 | 26,904 |
| Other income (deductions) | 66,000 | 13,058 | 79,058 |
| Interest expense | 39,597 | (9,862) | 29,735 |
| Other expenses | (9,100) | 38 | (9,062) |
| Income taxes | (14,160) | 3,992 | (10,168) |
| Preferred dividend requirements of subsidiaries and noncontrolling interests | 3,810 | — | 3,810 |
| 2025 Net Income (Loss) Attributable to Entergy Corporation | $810,462 | ($116,662) | $693,800 |
(a)Parent & Other includes eliminations, which are primarily intersegment activity.
Utility
| Amount | |
|---|---|
| (In Millions) | |
| 2024 operating revenues | $3,370 |
| Fuel, rider, and other revenues that do not significantly affect net income | 263 |
| Retail one-time bill credit | 92 |
| Volume/weather | 75 |
| Purchased power agreement termination proceeds | 15 |
| Retail electric price | 14 |
| Effect of sale of natural gas distribution businesses | (32) |
| 2025 operating revenues | $3,797 |
The Utility operating companies’ results include revenues from rate mechanisms designed to recover fuel, purchased power, and other costs such that the revenues and expenses associated with these items generally offset and do not affect net income. “Fuel, rider, and other revenues that do not significantly affect net income” includes the revenue variance associated with these items.
The retail one-time bill credit variance represents the disbursement of settlement proceeds in the form of a one-time bill credit provided to Entergy Arkansas’s retail customers during the August 2024 billing cycle through the Grand Gulf credit rider as a result of the System Energy settlement with the APSC. There is no effect on net income because Entergy previously recorded a regulatory liability at the time of the global black box settlement reached between System Energy and the MPSC in June 2022. See Note 2 to the financial statements in the Form 10-K for discussion of the System Energy settlements with the APSC and the MPSC. See Note 2 to the financial statements herein and in the Form 10-K for discussion of Entergy Arkansas’s Grand Gulf credit rider.
The volume/weather variance is primarily due to an increase in industrial and residential usage. The increase in industrial usage is primarily due to an increase in demand from large industrial customers, primarily in the primary metals, chlor-alkali, and industrial gases industries. The increase in residential usage is primarily due to an increase in customers.
The purchased power agreement termination proceeds variance represents $15 million of liquidated damages recognized by Entergy Mississippi in third quarter 2025 resulting from a counterparty’s termination of a purchased power agreement.
The retail electric price variance is primarily due to:
an increase in Entergy Arkansas’s formula rate plan rates effective January 2025;
a decrease in Entergy Louisiana’s formula rate plan revenues for a two month period beginning in September 2025, resulting from earnings above the authorized return on common equity for the 2024 test year;
an increase in Entergy Mississippi’s formula rate plan rates resulting from an increase in interim facilities rate adjustment revenues effective January 2025; and
the implementation of the distribution cost recovery factor rider effective with the first billing cycle in October 2024 and increases in the distribution cost recovery factor rider effective in December 2024 and June 2025, each at Entergy Texas.
See Note 2 to the financial statements herein and in the Form 10-K for discussion of the regulatory proceedings discussed above.
The effect of sale of natural gas distribution businesses variance represents the decrease in operating revenues resulting from the absence of natural gas revenues at Entergy Louisiana and Entergy New Orleans in third quarter 2025 as a result of the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025. See Note 13 to the financial statements herein for discussion of the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025.
Total electric energy sales for Utility for the three months ended September 30, 2025 and 2024 are as follows:
| 2025 | 2024 | % Change | |
|---|---|---|---|
| (GWh) | |||
| Residential | 11,692 | 11,519 | 2 |
| Commercial | 8,499 | 8,394 | 1 |
| Industrial | 16,255 | 15,150 | 7 |
| Governmental | 678 | 684 | (1) |
| Total retail | 37,124 | 35,747 | 4 |
| Sales for resale | 4,079 | 3,727 | 9 |
| Total | 41,203 | 39,474 | 4 |
See Note 12 to the financial statements herein for additional discussion of operating revenues.
Other Income Statement Items
Utility
Other operation and maintenance expenses increased from $714 million for the third quarter 2024 to$764 million for the third quarter 2025 primarily due to:
an increase of $36 million in power delivery expenses primarily due to higher vegetation maintenance costs;
an increase of $13 million in compensation and benefits costs primarily due to higher incentive-based accruals in 2025 as compared to 2024;
the expensing of $11 million at Entergy Louisiana of project costs associated with the Bayou Power Station project following Entergy Louisiana’s election in third quarter 2025 to cancel the project and instead to evaluate an alternative transmission solution. See“MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Liquidity and Capital Resources” below for discussion of Entergy Louisiana’s Bayou Power Station project;
an increase of $8 million in non-nuclear generation expenses primarily due to a higher scope of work performed in 2025 as compared to 2024; and
an increase of $5 million in bad debt expense.
The increase was partially offset by contract costs of $15 million, in third quarter 2024, related to operational performance, customer service, and organizational health initiatives, and a $13 million gain, recorded in third quarter 2025, resulting from the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025, which included the derecognition of $7 million of goodwill attributed to the businesses sold. See Note 13 to the financial statements herein for discussion of the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025.
Asset write-offs, impairments, and related charges includes a $13 million charge, recorded in third quarter 2025 at Entergy New Orleans, to reflect the write-off of retained natural gas plant assets that were not included in the sale of Entergy New Orleans’s natural gas distribution business on July 1, 2025, and which will not be recovered. See Note 13 to the financial statements herein for discussion of the sale of Entergy New Orleans’s natural gas distribution business on July 1, 2025.
Taxes other than income taxes increased primarily due to increases in ad valorem taxes resulting from higher assessments and increases in local franchise taxes as a result of higher retail revenues in 2025 as compared to 2024.
Depreciation and amortization expenses increased primarily due to additions to plant in service and increases in nuclear depreciation rates at Entergy Louisiana effective September 2024 and September 2025 in accordance with the global stipulated settlement agreement approved by the LPSC in August 2024. See Note 2 to the financial statements in the Form 10-K for discussion of the Entergy Louisiana global stipulated settlement agreement.
Other regulatory charges (credits) - net includes the reversal in third quarter 2024 of a $92 million regulatory liability recognized for Entergy Arkansas’s obligation to return to customers the refund from the System Energy settlement with the APSC. The reversal of the regulatory liability offsets a reduction in gross revenues from the retail one-time bill credits provided to customers in the August 2024 billing cycle through the Grand Gulf credit rider. See Note 2 to the financial statements in the Form 10-K for discussion of the System Energy settlement with the APSC. See Note 2 to the financial statements herein and in the Form 10-K for discussion of Entergy Arkansas’s Grand Gulf credit rider. In addition, Entergy records a regulatory charge or credit for the difference between asset retirement obligation-related expenses and nuclear decommissioning trust earnings plus asset retirement obligation-related costs collected in revenue.
changes in decommissioning trust fund activity, including portfolio rebalancing of decommissioning trust funds in third quarter 2024;
an increase in the allowance for equity funds used during construction due to higher construction work in progress in 2025, including the Legend Power Station project and the Orange County Advanced Power Station project, each at Entergy Texas, the Franklin Farms Power Station Units 1 and 2 project at Entergy Louisiana, and the Vicksburg Advanced Power Station project at Entergy Mississippi; and
an increase of $17 million in the amortization of tax gross ups on customer advances for construction.
Interest expense increased primarily due to:
the issuance by Entergy Louisiana of $750 million of 5.80% Series mortgage bonds in January 2025;
the issuance by Entergy Mississippi of $600 million of 5.80% Series mortgage bonds in March 2025;
the issuance by Entergy Texas of $500 million of 5.25% Series mortgage bonds in February 2025;
the issuance by System Energy of $300 million of 5.30% Series mortgage bonds in December 2024 and an additional $240 million in a reopening of the same series in May 2025; and
carrying costs of $12 million in 2025 on customer advances for construction.
The increase was partially offset by an increase in the allowance for borrowed funds used during construction due to higher construction work in progress in 2025, including the Legend Power Station project and the Orange County
Advanced Power Station project, each at Entergy Texas, the Franklin Farms Power Station Units 1 and 2 project at Entergy Louisiana, and the Vicksburg Advanced Power Station project at Entergy Mississippi.
Parent and Other
Other income increased primarily due to legal provisions recorded in third quarter 2024.
Interest expense decreased primarily due to lower commercial paper balances and lower variable interest rates on commercial paper and credit facilities in 2025 as compared to 2024.
The effective income tax rate was 22.7% for the third quarter 2025. The difference in the effective income tax rate for the third quarter 2025 versus the federal statutory rate of 21% was primarily due to the accrual for state income taxes, partially offset by book and tax differences related to the allowance for equity funds used during construction and certain book and tax differences related to utility plant items.
The effective income tax rate was 25% for the third quarter 2024. The difference in the effective income tax rate for the third quarter 2024 versus the federal statutory rate of 21% was primarily due to the accrual for state income taxes, partially offset by the resolution of an Arkansas state income tax audit. See Note 3 to the financial statements in the Form 10-K for discussion of the Arkansas state income tax audit resolution.
Following are income statement variances for Utility, Parent & Other, and Entergy comparing the nine months ended September 30, 2025 to the nine months ended September 30, 2024 showing how much the line item increased or (decreased) in comparison to the prior period.
| Utility | Parent &Other (a) | Entergy | |
|---|---|---|---|
| (In Thousands) | |||
| 2024 Net Income (Loss) Attributable to Entergy Corporation | $1,422,779 | ($653,636) | $769,143 |
| Operating revenues | 858,937 | (8,543) | 850,394 |
| Fuel, fuel-related expenses, and gas purchased for resale | 32,093 | (15,647) | 16,446 |
| Purchased power | 363,207 | (13,535) | 349,672 |
| Other regulatory charges (credits) - net | (228,658) | — | (228,658) |
| Other operation and maintenance | 58,869 | (2,265) | 56,604 |
| Asset write-offs, impairments, and related charges | (118,980) | — | (118,980) |
| Taxes other than income taxes | 60,557 | 276 | 60,833 |
| Depreciation and amortization | 57,192 | 214 | 57,406 |
| Other income (deductions) | 64,278 | 317,872 | 382,150 |
| Interest expense | 130,103 | (5,280) | 124,823 |
| Other expenses | (18,193) | 169 | (18,024) |
| Income taxes | 105,384 | 68,260 | 173,644 |
| Preferred dividend requirements of subsidiaries and noncontrolling interests | 5,431 | — | 5,431 |
| 2025 Net Income (Loss) Attributable to Entergy Corporation | $1,898,989 | ($376,499) | $1,522,490 |
(a)Parent & Other includes eliminations, which are primarily intersegment activity.
Results of operations for the nine months ended September 30, 2024 include: (1) a $317 million ($250 million net-of-tax) settlement charge, reflected in Parent & Other above, recognized as a result of a group annuity contract purchased in May 2024 to settle certain pension liabilities; (2) expenses of $151 million ($112 million net-of-tax), recorded at Utility in second quarter 2024, primarily consisting of regulatory charges to reflect the effects of an agreement in principle between Entergy Louisiana and the LPSC staff and the intervenors in July 2024 to renew Entergy Louisiana’s formula rate plan and resolve a number of other retail dockets and matters, including all formula rate plan test years prior to 2023; (3) a $132 million ($97 million net-of-tax) charge, recorded at Utility, to reflect the write-off of a previously recorded regulatory asset as a result of an adverse decision in the Entergy Arkansas opportunity sales proceeding in March 2024; and (4) a $78 million ($57 million net-of-tax) regulatory charge, recorded at Utility in first quarter 2024, primarily to reflect a settlement in principle between Entergy New Orleans and the City Council in April 2024 for additional sharing with customers of income tax benefits from the resolution of the 2016-2018 IRS audit. See Note 11 to the financial statements in the Form 10-K for discussion of the group annuity contract and settlement charge. See Note 2 to the financial statements in the Form 10-K for discussion of the Entergy Louisiana agreement in principle and the subsequently filed global stipulated settlement agreement. See Note 2 to the financial statements herein and in the Form 10-K for discussion of the Entergy Arkansas opportunity sales proceeding. See Note 3 to the financial statements in the Form 10-K for discussion of the April 2024 settlement in principle and the resolution of the 2016-2018 IRS audit.
Utility
| Amount | |
|---|---|
| (In Millions) | |
| 2024 operating revenues | $9,084 |
| Fuel, rider, and other revenues that do not significantly affect net income | 423 |
| Volume/weather | 207 |
| Retail electric price | 154 |
| Retail one-time bill credit | 92 |
| Purchased power agreement termination proceeds | 15 |
| Effect of sale of natural gas distribution businesses | (32) |
| 2025 operating revenues | $9,943 |
The Utility operating companies’ results include revenues from rate mechanisms designed to recover fuel, purchased power, and other costs such that the revenues and expenses associated with these items generally offset and do not affect net income. “Fuel, rider, and other revenues that do not significantly affect net income” includes the revenue variance associated with these items.
The volume/weather variance is primarily due to an increase in industrial usage. The increase in industrial usage is primarily due to an increase in demand from large industrial customers, primarily in the primary metals, chlor-alkali, petroleum refining, and technology industries.
The retail electric price variance is primarily due to:
an increase in Entergy Arkansas’s formula rate plan rates effective January 2025;
increases in Entergy Mississippi’s formula rate plan rates effective April 2024 and July 2024 and an increase in Entergy Mississippi’s formula rate plan rates resulting from an increase in interim facilities rate adjustment revenues effective January 2025; and
the implementation of the distribution cost recovery factor rider effective with the first billing cycle in October 2024 and increases in the distribution cost recovery factor rider effective in December 2024 and June 2025, each at Entergy Texas.
See Note 2 to the financial statements herein and in the Form 10-K for discussion of the regulatory proceedings discussed above.
The retail one-time bill credit variance represents the disbursement of settlement proceeds in the form of a one-time bill credit provided to Entergy Arkansas’s retail customers during the August 2024 billing cycle through the Grand Gulf credit rider as a result of the System Energy settlement with the APSC. There is no effect on net income because Entergy previously recorded a regulatory liability at the time of the global black box settlement reached between System Energy and the MPSC in June 2022. See Note 2 to the financial statements in the Form 10-K for discussion of the System Energy settlements with the APSC and the MPSC. See Note 2 to the financial statements herein and in the Form 10-K for discussion of Entergy Arkansas’s Grand Gulf credit rider.
The purchased power agreement termination proceeds variance represents $15 million of liquidated damages recognized by Entergy Mississippi in third quarter 2025 resulting from a counterparty’s termination of a purchased power agreement.
The effect of sale of natural gas distribution businesses variance represents the decrease in operating revenues resulting from the absence of natural gas revenues at Entergy Louisiana and Entergy New Orleans in third quarter 2025 as a result of the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025. See Note 13 to the financial statements herein for discussion of the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025.
Total electric energy sales for Utility for the nine months ended September 30, 2025 and 2024 are as follows:
| 2025 | 2024 | % Change | |
|---|---|---|---|
| (GWh) | |||
| Residential | 29,376 | 28,499 | 3 |
| Commercial | 22,007 | 21,797 | 1 |
| Industrial | 45,707 | 42,174 | 8 |
| Governmental | 1,853 | 1,883 | (2) |
| Total retail | 98,943 | 94,353 | 5 |
| Sales for resale | 9,847 | 10,737 | (8) |
| Total | 108,790 | 105,090 | 4 |
See Note 12 to the financial statements herein for additional discussion of operating revenues.
Other Income Statement Items
Utility
Purchased power includes an increase in 2025 of $29 million in costs, at Entergy Texas, related to the procurement of capacity through MISO’s annual planning resource auction, including the effect of a significant increase in MISO’s seasonal auction clearing price, due to the implementation of a reliability-based demand curve, for capacity transactions during the summer months. Although Entergy Texas does not have the ability to recover its MISO capacity costs incurred to date beyond the level included in base rates, in June 2025, Texas legislation established a capacity cost recovery rider mechanism that would allow for the recovery of costs related to the procurement of capacity through MISO’s annual planning resource auction outside of base rates, through a rider that is updated annually. Entergy Texas plans to file for such a rider to recover future capacity procurement costs at the earliest opportunity in 2026.
Other expenses decreased primarily due to decreased nuclear refueling outage expenses due to the amortization of lower costs associated with the most recent outages as compared to previous outages.
Other operation and maintenance expenses increased from $2,081 million for the nine months ended September 30, 2024 to $2,140 million for the nine months ended September 30, 2025 primarily due to:
an increase of $44 million in power delivery expenses primarily due to higher vegetation maintenance costs;
an increase of $19 million in non-nuclear generation expenses primarily due to a higher scope of work performed during plant outages in 2025 as compared to 2024;
an increase of $16 million in bad debt expense;
an increase of $11 million in transmission costs allocated by MISO. See Note 2 to the financial statements in the Form 10-K for discussion of the recovery of these costs; and
the expensing of $11 million at Entergy Louisiana of project costs associated with the Bayou Power Station project following Entergy Louisiana’s election in third quarter 2025 to cancel the project and instead to evaluate an alternative transmission solution. See“MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Liquidity and Capital Resources” below for discussion of Entergy Louisiana’s Bayou Power Station project.
contract costs of $39 million in 2024 related to operational performance, customer service, andorganizational health initiatives; and
a $13 million gain, recorded in third quarter 2025, resulting from the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025, which included the derecognition of $7 million of goodwill attributed to the businesses sold. See Note 13 to the financial statements herein for discussion of the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025.
Asset write-offs, impairments, and related charges includes:
a $132 million charge to reflect the write-off, at Entergy Arkansas, of a previously recorded regulatory asset as a result of an adverse decision in the Entergy Arkansas opportunity sales proceeding in March 2024. See Note 2 to the financial statements herein and in the Form 10-K for discussion of the Entergy Arkansas opportunity sales proceeding; and
a $13 million charge, recorded in third quarter 2025 at Entergy New Orleans, to reflect the write-off of retained natural gas plant assets that were not included in the sale of Entergy New Orleans’s natural gas distribution business on July 1, 2025, and which will not be recovered. See Note 13 to the financial statements herein for discussion of the sale of Entergy New Orleans’s natural gas distribution business on July 1, 2025.
Taxes other than income taxes increased primarily due to increases in ad valorem taxes resulting from higher assessments and increases in local franchise taxes as a result of higher retail revenues in 2025 as compared to 2024.
Depreciation and amortization expenses increased primarily due to additions to plant in service and increases in nuclear depreciation rates at Entergy Louisiana effective September 2024 and September 2025 in accordance with the global stipulated settlement agreement approved by the LPSC in August 2024. The increase was partially offset by the recognition of $28 million in depreciation expense in 2024 at Entergy Texas for the 2022 base rate case relate back period, effective over six months beginning January 2024. The recognition of depreciation expense for the relate back period was effective over the same period as collections from the relate back surcharge rider and resulted in no effect on net income. See Note 2 to the financial statements in the Form 10-K for discussion of the Entergy Louisiana global stipulated settlement agreement. See Note 2 to the financial statements in the Form 10-K for discussion of the 2022 base rate case at Entergy Texas.
Other regulatory charges (credits) - net includes:
the reversal in third quarter 2024 of a $92 million regulatory liability recognized for Entergy Arkansas’s obligation to return to customers the refund from the System Energy settlement with the APSC. The reversal of the regulatory liability offsets a reduction in gross revenues from the retail one-time bill credits provided to customers in the August 2024 billing cycle through the Grand Gulf credit rider. See Note 2 to the financial statements in the Form 10-K for discussion of the System Energy settlement with the APSC. See Note 2 to the financial statements herein and in the Form 10-K for discussion of Entergy Arkansas’s Grand Gulf credit rider;
regulatory charges of $150 million, recorded by Entergy Louisiana in second quarter 2024, to reflect the effects of an agreement in principle between Entergy Louisiana and the LPSC staff and the intervenors in July 2024 to renew Entergy Louisiana’s formula rate plan and resolve a number of other retail dockets and matters, including all formula rate plan test years prior to 2023. See Note 2 to the financial statements in the Form 10-K for discussion of the Entergy Louisiana agreement in principle and the subsequently filed global stipulated settlement agreement; and
a regulatory charge of$78 million, recorded by Entergy New Orleans in first quarter 2024, primarily to reflect a settlement in principle between Entergy New Orleans and the City Council in April 2024 for additional sharing with customers of income tax benefits from the resolution of the 2016-2018 IRS audit. See Note 3 to the financial statements in the Form 10-K for discussion of the April 2024 settlement in principle and for discussion of the resolution of the 2016-2018 IRS audit.
In addition, Entergy records a regulatory charge or credit for the difference between asset retirement obligation-related expenses and nuclear decommissioning trust earnings plus asset retirement obligation-related costs collected in revenue.
an increase in the allowance for equity funds used during construction due to higher construction work in progress in 2025, including the Orange County Advanced Power Station project, the Legend Power Station project, and the Lone Star Power Station project, each at Entergy Texas, the Franklin Farms Power Station Units 1 and 2 project at Entergy Louisiana, and the Vicksburg Advanced Power Station project at Entergy Mississippi;
an increase of $41 million in the amortization of tax gross ups on customer advances for construction;
a $17 million true-up of Entergy Louisiana’s MISO cost recovery mechanism over-recovery balance to the 2024 formula rate plan filing, which was filed with the LPSC in May 2025. See Note 2 to the financial statements herein for discussion of the 2024 formula rate plan filing; and
an increase of $17 million in interest earned on money pool investments.
The increase was substantially offset by changes in decommissioning trust fund activity, including portfolio rebalancing of decommissioning trust funds in 2024, and a decrease of $13 million in affiliated dividend income from affiliated preferred membership interests related to storm cost securitization.
Interest expense increased primarily due to:
the issuance by Entergy Arkansas of $400 million of 5.45% Series mortgage bonds in May 2024 and an additional $300 million in a reopening of the same series in May 2025;
the issuance by Entergy Louisiana of $700 million of 5.15% Series mortgage bonds in August 2024;
the issuance by Entergy Louisiana of $750 million of 5.80% Series mortgage bonds in January 2025;
the issuance by Entergy Mississippi of $600 million of 5.80% Series mortgage bonds in March 2025;
the issuance by Entergy Texas of $350 million of 5.55% Series mortgage bonds in August 2024;
the issuance by Entergy Texas of $500 million of 5.25% Series mortgage bonds in February 2025;
the issuance by System Energy of $300 million of 5.30% Series mortgage bonds in December 2024 and an additional $240 million in a reopening of the same series in May 2025; and
carrying costs of $35 million in 2025 on customer advances for construction.
The increase was partially offset by an increase in the allowance for borrowed funds used during construction due to higher construction work in progress in 2025, including the Orange County Advanced Power Station project, the Legend Power Station project, and the Lone Star Power Station project, each at Entergy Texas, the Franklin Farms Power Station Units 1 and 2 project at Entergy Louisiana, and the Vicksburg Advanced Power Station project at Entergy Mississippi.
Parent and Other
Other income (deductions) increased primarily due to a $317 million ($250 million net-of-tax) non-cash settlement charge recognized in second quarter 2024 as a result of a group annuity contract purchased in May 2024 to settle certain pension liabilities. See Note 11 to the financial statements in the Form 10-K for discussion of the group annuity contract and settlement charge.
The effective income tax rate was 22.5% for thenine months ended September 30, 2025. The difference in the effective income tax rate for thenine months ended September 30,2025 versus the federal statutory rate of 21% was primarily due to the accrual for state income taxes, partially offset by book and tax differences related to the allowance for equity funds used during construction and certain book and tax differences related to utility plant items.
The effective income tax rate was 25.9% for thenine months ended September 30, 2024. The difference in the effective income tax rate for thenine months ended September 30, 2024 versus the federal statutory rate of 21% was primarily due to the accrual for state income taxes, amortization of accumulated deferred income taxes as a result of tax rate changes, and a provision for uncertain tax positions, partially offset by the resolution of an Arkansas state income tax audit, certain book and tax differences related to utility plant items, and book and tax differences related to the allowance for equity funds used during construction. See Note 3 to the financial statements in the Form 10-K for discussion of the Arkansas state income tax audit.
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS -Income Tax Legislation and Regulation” in the Form 10-K for discussion of income tax legislation and regulation. The following is an update to that discussion. See Note 10 to the financial statements herein for discussion of the nuclear and solar production tax credits recorded in 2025.
One Big Beautiful Bill Act of 2025
On July 4, 2025, the One Big Beautiful Bill Act (OBBBA) was enacted. The OBBBA is a wide ranging update to U.S. tax and spending policy. In particular, the OBBBA modified and extended various clean energy tax incentives relevant to electric utilities, preserving production tax credits under Internal Revenue Code section 45U for existing nuclear facilities through 2032 and generally maintaining the existing phase-out schedule for new nuclear and battery storage under Internal Revenue Code sections 45Y (clean electricity production credit) or Internal Revenue Code section 48E (clean electricity investment credit). In addition, the OBBBA preserved the tax credits for carbon capture and sequestration facilities that meet the requirements of Internal Revenue Code section 45Q. The OBBBA also retained full transferability of all credits and preserved five-year modified accelerated cost recovery system treatment for eligible Internal Revenue Code section 45Y and 48E assets.
In contrast, the OBBBA significantly shortened the time period for solar and wind facilities to claim clean energy tax incentives. In general, solar and wind facilities must be placed in service by December 31, 2027 to qualify for the tax credits, unless construction begins by July 3, 2026, and certain safe harbor requirements are met.
In addition, the OBBBA adopted new foreign entity of concern (FEOC) rules designed to deny clean energy tax incentives to all clean energy projects beginning construction after December 31, 2025 that use equipment beyond statutory guidelines from prohibited foreign entities (entities with ties to China, Russia, Iran, or North Korea). The FEOC rules also deny these incentives to taxpayers that rely beyond certain thresholds on equity or debt from specified foreign entities or that make payments to specified foreign entity counterparties under contracts or licensing agreements that give such counterparties “effective control” over an eligible project. These taxpayer FEOC rules will apply to taxpayers in their first taxable year following enactment of the OBBBA.
On July 7, 2025, an executive order was issued directing the U.S. Treasury to issue, among other things, new safe harbor guidance, particularly with respect to wind and solar facilities. On August 15, 2025, in response to the executive order, the U.S. Treasury released Notice 2025-42, which provides updated guidance regarding the beginning of construction requirements and termination of the wind and solar energy tax credits under sections 45Y and 48E. Notice 2025-42 provides additional guidance on these safe harbor provisions, clarifying the criteria for beginning construction and offering examples of equipment and contractual terms that will qualify a project for safe harbor treatment under the OBBBA. Notice 2025-42 states that the U.S. Treasury and the IRS are currently drafting additional guidance to address the FEOC rules.
Entergy Wholesale Commodities Exit from the Merchant Power Business
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS -Entergy Wholesale Commodities Exit from the Merchant Power Business” in the Form 10-K for discussion of the exit from the merchant power business. The following is an update to that discussion.
In July 2018, Entergy entered into a purchase and sale agreement with Holtec International to sell to a Holtec subsidiary 100% of the equity interests in the subsidiary that owns Palisades and the Big Rock Point Site, with a subsequent amendment to the purchase and sale agreement in February 2020. In December 2020, Entergy and Holtec submitted a license transfer application to the NRC requesting approval to transfer the Palisades and Big Rock Point licenses from Entergy to Holtec. In February 2021 several parties filed with the NRC petitions to intervene and requests for hearing challenging the license transfer application. In March 2021, Entergy and Holtec filed answers opposing the petitions to intervene and hearing requests, and the petitioners filed replies. In March 2021 an additional party also filed a petition to intervene and request for hearing. Entergy and Holtec filed an answer to the March 2021 petition in April 2021. The NRC issued an order approving the application in December 2021, subject to the NRC’s authority to condition, revise, or rescind the approval order based on the resolution of four pending requests for hearing. These petitions and requests for hearing remained pending with the NRC at the time of the closing of the Palisades transaction in June 2022. In July 2022 the NRC issued an order granting the Michigan Attorney General’s petition hearing request. The hearing was held in February 2023. In August 2025 the NRC transitioned Palisades from decommissioning status back to its oversight process for operating reactors. In October 2025, Entergy and Holtec filed a joint motion to dismiss the proceeding as moot, given Palisades’ return to operational status and impending restart. See Note 14 to the financial statements in the Form 10-K for discussion of the sale of the Palisades plant.
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Liquidity and Capital Resources” in the Form 10-K for a discussion of Entergy’s capital structure, capital spending plans and other uses of capital, and sources of capital. The following are updates to that discussion.
Recent announcements of changes to international trade policy and tariffs and further similar changes may impact Entergy’s business, operations, results of operations, and liquidity and capital resources. Potential impacts may include increases in costs associated with Entergy’s capital investments or operation and maintenance expenses; operational impacts, such as supply chain, manufacturing, or raw materials sourcing disruptions which may affect Entergy’s ability to make planned capital investments as and when expected and needed; legal uncertainties, such as potential legal or other challenges to presidential tariff authority; or broader economic risks, including shifting customer demand, impacts on customer investment decisions, and volatile or uncertain credit and capital markets, which may affect Entergy’s ability to access needed capital. The nature and extent of any such effects will depend on, among other things, the specifics of the changes that are ultimately implemented both domestically and internationally, the responses of vendors, suppliers, and other counterparties to those changes, indirect effects on the price and availability of non-tariffed goods, and the effectiveness of mitigation measures.
Capital Structure and Resources
Entergy’s debt to capital ratio is shown in the following table.
| September 30,2025 | December 31, 2024 | |
|---|---|---|
| Debt to capital | 64.3% | 65.3% |
| Effect of excluding securitization bonds | (0.2%) | (0.2%) |
| Debt to capital, excluding securitization bonds (non-GAAP) (a) | 64.1% | 65.1% |
| Effect of subtracting cash | (1.2%) | (0.7%) |
| Net debt to net capital, excluding securitization bonds (non-GAAP) (a) | 62.9% | 64.4% |
(a)Calculation excludes the Texas securitization bonds, which are non-recourse to Entergy Texas.
As of September 30, 2025, 19% of the debt outstanding is at the parent company, Entergy Corporation, and 81% is at the Utility segment. Net debt consists of debt less cash and cash equivalents. Debt consists of notes payable and commercial paper, finance lease obligations, and long-term debt, including the currently maturing portion. Capital consists of debt, equity, and subsidiaries’ preferred stock without sinking fund. Net capital consists of capital less cash and cash equivalents. The debt to capital ratio excluding securitization bonds and net debt to net capital ratio excluding securitization bonds are non-GAAP measures. Entergy uses the debt to capital ratios excluding securitization bonds in analyzing its financial condition and believes they provide useful information to its investors and creditors in evaluating Entergy’s financial condition because the securitization bonds are non-recourse to
Entergy, as more fully described in Note 5 to the financial statements in the Form 10-K. Entergy also uses the net debt to net capital ratio excluding securitization bonds in analyzing its financial condition and believes it provides useful information to its investors and creditors in evaluating Entergy’s financial condition because net debt indicates Entergy’s outstanding debt position that could not be readily satisfied by cash and cash equivalents on hand.
Entergy Corporation has in place a credit facility that has a borrowing capacity of $3 billion and expires in June 2030. The facility includes fronting commitments for the issuance of letters of credit against $20 million of the total borrowing capacity of the credit facility. The commitment fee is currently 0.225% of the undrawn commitment amount. Commitment fees and interest rates on loans under the credit facility can fluctuate depending on the senior unsecured debt ratings of Entergy Corporation. As there were no borrowings under the facility for the nine months ended September 30, 2025, the estimated interest rate as of September 30, 2025 that would have been applied to outstanding borrowings under the facility was 5.76%. The following is a summary of the amounts outstanding and capacity available under the credit facility as of September 30, 2025:
| Capacity | Borrowings | Lettersof Credit | CapacityAvailable |
|---|---|---|---|
| (In Millions) | |||
| $3,000 | $— | $3 | $2,997 |
Entergy Corporation’s credit facility includes a covenant requiring Entergy to maintain a consolidated debt ratio, as defined, of 65% or less of its total capitalization. The calculation of this debt ratio under Entergy Corporation’s credit facility is different than the calculation of the debt to capital ratio above. Entergy is currently in compliance with the covenant and expects to remain in compliance with this covenant. If Entergy fails to meet this ratio, or if Entergy Corporation or one of the Registrant Subsidiaries (except Entergy New Orleans and System Energy) defaults on other indebtedness or is in bankruptcy or insolvency proceedings, an acceleration of the Entergy Corporation credit facility’s maturity date may occur. See Note 4 to the financial statements herein for additional discussion of the Entergy Corporation credit facility and discussion of the Registrant Subsidiaries’ credit facilities.
Entergy Corporation has a commercial paper program with a Board-approved program limit of $2 billion. As of September 30, 2025, Entergy Corporation had $1,398 million of commercial paper outstanding. The weighted-average interest rate for the nine months ended September 30, 2025 was 4.64%.
Equity Issuances and Equity Distribution Program
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Liquidity and Capital Resources - Sources of Capital - Equity Issuances and Equity Distribution Program” in the Form 10-K and Note 3 to the financial statements herein for discussion of equity issuances, the equity distribution program, and equity forward sale agreements. The following are updates to that discussion.
In March 2025, Entergy marketed an equity offering of 17.8 million shares of Entergy Corporation common stock. In lieu of issuing equity at the time of the offering, Entergy entered into forward sale agreements with several forward counterparties. The forward sale agreements require Entergy to, at its election on or prior to September 30, 2026, either (1) physically settle the transactions by issuing the total of 17.8 million shares of its common stock to the forward counterparties in exchange for net proceeds at the then-applicable forward sale price specified by the agreements (initially $81.87 per share) or (2) net settle the transactions in whole or in part through the delivery or receipt of cash or shares. The forward sale price is subject to adjustment on a daily basis based on a floating interest rate factor and will decrease by other fixed amounts specified in the agreements.
In May 2025, Entergy Corporation physically settled all of its obligations under certain of its then-outstanding forward sale agreements under its at the market equity distribution program for cash proceeds of $806 million.
In October 2025, Entergy Corporation physically settled all of its obligations under certain of its then-outstanding forward sale agreements under its at the market equity distribution program for cash proceeds of $332 million.
Entergy Corporation currently expects to issue approximately $4.4 billion of equity through 2029, which it may issue under its at the market equity distribution program or otherwise, with approximately $1.9 billion already contracted under forward sale agreements, including under its at the market equity distribution program and the March 2025 equity offering described above.
Capital Expenditure Plans and Other Uses of Capital
See the table and discussion in the Form 10-K under “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Liquidity and Capital Resources - Capital Expenditure Plans and Other Uses of Capital,” that sets forth the amounts of Entergy’s planned construction and other capital investments for 2025 through 2027. The following are updates to that discussion.
Entergy is developing its capital investment plan for 2026 through 2029 and currently anticipates that the Utility will make approximately $41 billion in capital investments during that period, including $12 billion in 2026, $11 billion in 2027, $10 billion in 2028, and $8 billion in 2029. In addition to routine capital spending to maintain operations, the preliminary Utility estimate includes investments in generation projects to modernize, decarbonize, expand, and diversify the Utility operating companies’ portfolios, as well as to support customer growth, including Ironwood Power Station (formerly Lake Catherine Unit 5), Jefferson Power Station, Arkansas Cypress Solar, Segno Solar, Votaw Solar, Bogalusa West Solar, Franklin Farms Power Station Units 1 and 2, Waterford 5 Power Station, Delta Blues Advanced Power Station, Delta Solar, Penton Solar, Traceview Advanced Power Station, Vicksburg Advanced Power Station, Orange County Advanced Power Station, Lone Star Power Station, Legend Power Station, and potential construction of additional generation; investments in the Utility nuclear fleet; transmission spending to improve reliability and resilience while also supporting renewables expansion and customer growth; distribution and Utility support spending to improve reliability, resilience, and customer experience through projects focused on asset renewals and enhancements and grid stability; and other investments. Estimated capital expenditures are subject to periodic review and modification and may vary based on the ongoing effects of business restructuring, regulatory constraints and requirements, governmental actions, including trade-related governmental actions, such as tariffs and other measures, environmental regulations, business opportunities, market volatility, economic trends, changes in project plans, and the ability to access capital, including any changes to governmental programs, such as loans, grants, guarantees, and other subsidies. Entergy is not able to predict the effect of potential changes in regulation and law, changes to governmental programs, such as loans, grants, guarantees, and other subsidies, and trade-related governmental actions, such as tariffs and other measures, on its current and planned capital projects.
Renewables
Entergy Arkansas Special Rate Contract and Arkansas Cypress Solar
In September 2025, Entergy Arkansas filed an application with the APSC seeking approval of a long-term special rate contract between Altitude, LLC, a subsidiary of Alphabet, Inc. (Google) and Entergy Arkansas for the sale of electricity to a new large-scale data center in West Memphis, Arkansas. A procedural schedule was established with a hearing to be held in November 2025. In October 2025 the APSC general staff filed testimony finding that based on its evaluation of Entergy Arkansas’s application and the results of the ratepayer impact measure test, the special rate contract meets the requirements of the APSC’s promotional practice rules and is in the public interest. No other parties filed testimony.
Also in September 2025, Entergy Arkansas filed an application with the APSC seeking a certificate of environmental compatibility and public need for the construction and operation of the Arkansas Cypress Solar facility, a planned 600 MW solar photovoltaic array with a 350 MW battery energy storage system and associated transmission facilities interconnecting at Entergy Arkansas’s White Bluff substation. Entergy Arkansas is seeking public interest and prudence findings from the APSC to construct the Arkansas Cypress Solar facility in furtherance of its long-term special rate contract with Google. A procedural schedule has been established with a hearing to be held in December 2025. In October 2025 the APSC general staff filed responsive testimony opposing the project cost and seeking additional information. Subsequently, the APSC general staff submitted supplemental testimony to update its initial conclusion and recommendations, noting the Cypress Solar facility is a reasonable project and recommending the APSC approve the project under certain conditions. The Arkansas Attorney General also filed testimony supporting the project but seeking additional information. Entergy Arkansas proposes to recover the costs of constructing the Arkansas Cypress Solar facility through the Generating Arkansas Jobs Act rider, which was approved by the APSC in October 2025. Subject to receipt of required regulatory approval and other conditions, the facility is expected to be in service by the end of 2028.
2021 Solar Certification and the Geaux Green Option
As discussed in the Form 10-K, in November 2021, Entergy Louisiana filed an application with the LPSC seeking certification of and approval for the addition of four new solar photovoltaic resources with a combined nameplate capacity of 475 megawatts (the 2021 Solar Portfolio) and the implementation of a new green tariff, the Geaux Green Option (Rider GGO). The 2021 Solar Portfolio consists of four resources, which include (i) the Vacherie Facility, a 150 megawatt resource in St. James Parish; (ii) the Sunlight Road Facility, a 50 megawatt resource in Washington Parish; (iii) the St. Jacques Facility, a 150 megawatt resource in St. James Parish; and (iv) the Elizabeth Facility, a 125 megawatt resource in Allen Parish. The St. Jacques Facility would be acquired through a build-own-transfer agreement; the remaining resources involve power purchase agreements. The Sunlight Road Facility and the Elizabeth Facility each achieved commercial operation in 2024, and the Vacherie Facility and the St. Jacques Facility originally had estimated in service dates in 2025.
In August 2022 the parties reached a settlement certifying the 2021 Solar Portfolio and approving implementation of Rider GGO. In September 2022 the LPSC approved the settlement. Following the LPSC approval, the St. James Parish council issued a moratorium on new land use permits for solar facilities until the later of March 2023 or the completion of an environmental and economic impact study. In November 2023, St. James Parish lifted the moratorium and adopted an ordinance modifying the parish’s land use plan to establish solar as an approved land use and defining corresponding solar regulations. In March 2024 the project developer submitted a solar energy facility farm permit application to the St. James Parish planning commission to request approval for the Vacherie and St. Jacques Facilities. In June 2024 the St. James Parish council denied the application and following this denial, the project developer and one of the project’s ground lessors filed separate lawsuits seeking to overturn the council’s decision. The council’s decision was subsequently affirmed by the Louisiana 23rd Judicial District Court. Entergy Louisiana is no longer pursuing the addition of resources through an acquisition of the St. Jacques Facility or through a power purchase agreement with the Vacherie Facility.
Alternative RFP and Certification
As discussed in the Form 10-K, in 2023, Entergy Louisiana made a filing to seek approval from the LPSC for an alternative to the requests for proposals (RFP) process that would enable the acquisition of up to 3 GW of solar resources on a faster timeline than the current RFP and certification processes allow. In June 2024 the LPSC issued an order approving the application. In August 2024, Entergy Louisiana issued the first RFP pursuant to this order in solicitation of solar resources that meet the requirements of the LPSC’s order. In July 2025, Entergy Louisiana filed an application requesting that the LPSC approve and certify the Bogalusa West Solar facility, a 200 MW single axis tracking solar photovoltaic power facility in Washington Parish, Louisiana. In October 2025 the LPSC voted to grant Entergy Louisiana’s application and approve the Bogalusa West Solar facility. The facility is expected to be in service by 2028.
As discussed in the Form 10-K, in July 2024, Entergy Texas filed an application seeking PUCT approval to amend Entergy Texas’s certificate of convenience and necessity to construct, own, and operate the Segno Solar facility, a 170 MW solar facility to be located in Polk County, Texas, and the Votaw Solar facility, a 141 MW solar facility to be located in Hardin County, Texas. In July 2025, Entergy Texas filed, and the ALJs with the State Office of Administrative Hearings granted, an unopposed motion to abate this proceeding to give the parties to the proceeding additional time for settlement discussions. In August 2025, Entergy Texas filed, and the ALJs with the State Office of Administrative Hearings granted, an unopposed motion to withdraw the application. In September 2025, Entergy Texas and Entergy Louisiana entered into assignment and assumption agreements pursuant to which Entergy Texas assigned, and Entergy Louisiana assumed, certain interests in the Segno Solar and Votaw Solar facilities, and the associated assets were transferred in third quarter 2025 from Entergy Texas to Entergy Louisiana for approximately $41.4 million, subject to adjustment per the assignment and assumption agreements. Entergy Louisiana expects to file an application with the LPSC in fourth quarter 2025 seeking certification and approval to construct the Segno Solar facility and Votaw Solar facility.
Other Generation and Transmission
Ironwood Power Station
As discussed in the Form 10-K, in November 2024, Entergy Arkansas filed an application with the APSC seeking a certificate of environmental compatibility and public need for the construction and operation of Ironwood Power Station (formerly Lake Catherine Unit 5), a 446 MW hydrogen-capable simple-cycle natural gas combustion turbine facility to be located at the existing Lake Catherine facility site in Hot Spring County, Arkansas. In December 2024 other parties, including the APSC general staff, filed testimony opposing the resource, although the APSC general staff recognized the capacity need for the resource. Entergy Arkansas filed testimony in January 2025 further supporting its application, and in February 2025 the opposing parties filed responsive rebuttal testimony continuing to dispute the estimated costs and to dispute that Entergy Arkansas performed a market solicitation sufficient to demonstrate that this resource is the most reasonable option for customers. Also in February 2025, Entergy Arkansas filed surrebuttal testimony responding to the opposing parties’ testimony. A hearing was held in March 2025, and in April 2025 the APSC issued an order approving certification of the facility. The order also provided a presumption of prudence finding with respect to a benchmark project cost. In May 2025, Entergy Arkansas filed a motion for clarification concerning the appropriate calculation of the benchmark that was below the estimated cost of Ironwood Power Station and was based upon older technology and dated pricing. Entergy Arkansas will have the opportunity to later present all actual costs to the APSC for review and a prudence determination of final costs, including costs incremental to the benchmark. Entergy Arkansas proposes to recover the costs of constructing Ironwood Power Station through the Generating Arkansas Jobs Act rider, which was approved by the APSC in October 2025. The facility is expected to be in service by the end of 2028.
Jefferson Power Station
In August 2025, Entergy Arkansas filed an application with the APSC seeking a certificate of environmental compatibility and public need for the construction and operation of Jefferson Power Station, an approximately 754 MW natural gas-fired combined cycle combustion turbine facility to be located in Jefferson County, Arkansas. In September 2025 other parties, including the APSC general staff, filed testimony opposing the resource pending further information, although the APSC general staff recognized the capacity need for the resource and that Entergy Arkansas had satisfied the statutory requirements for a certificate of environmental compatibility and public need. Entergy Arkansas filed testimony further supporting its application in September and October 2025. A hearing was held in October 2025, and an APSC decision is expected by January 2026. Entergy Arkansas proposes to recover the costs of constructing Jefferson Power Station through the Generating Arkansas Jobs Act rider, which was approved by the APSC in October 2025. Subject to receipt of required regulatory approval and other conditions, the facility is expected to be in service by the end of 2029.
Bayou Power Station
In March 2024, Entergy Louisiana filed an application with the LPSC seeking certification that the public convenience and necessity would be served by the construction of the Bayou Power Station, a 112 MW aggregated capacity floating natural gas power station with black-start capability in Leeville, Louisiana and an associated microgrid that would serve nearby areas, including Port Fourchon, Golden Meadow, Leeville, and Grand Isle. In its application, Entergy Louisiana noted that the estimated cost of the Bayou Power Station was $411 million, including estimated costs of transmission interconnection and other related costs. In October 2024, Entergy Louisiana filed a motion to suspend the procedural schedule in this proceeding in order to evaluate certain recent developments related to the project including potential changes to the estimated cost of the project. In October 2025, Entergy Louisiana filed with the LPSC a motion to dismiss its application without prejudice, noting that this project has been canceled and that Entergy Louisiana is evaluating an alternative transmission solution. In third quarter 2025, Entergy Louisiana expensed $10.8 million of project costs related to the Bayou Power Station project.
Entergy Louisiana Additional Generation and Transmission Resources
As discussed in the Form 10-K, in October 2024, Entergy Louisiana filed an application with the LPSC seeking approval of a variety of generation and transmission resources proposed in connection with establishing service to a new data center to be developed by a subsidiary of Meta Platforms, Inc. in north Louisiana, for which an electric service agreement has been executed. The filing requests LPSC certification of three new combined cycle combustion turbine generation resources totaling 2,262 MW, each of which will be enabled for future carbon capture and storage, a new 500 kV transmission line, and 500 kV substation upgrades. Two of the new combined cycle combustion turbine generation resources are to be located at Franklin Farms in north Louisiana (Franklin Farms Power Station Units 1 and 2). The application also requests approval to implement a corporate sustainability rider applicable to the new customer. The corporate sustainability rider contemplates the new customer contributing to the costs of the future addition of 1,500 MW of new solar and energy storage resources, agreements involving carbon capture and storage at Entergy Louisiana’s existing Lake Charles Power Station, and potential future wind and nuclear resources. Entergy Louisiana anticipates funding the incremental cost to serve the customer through direct financial contributions from the customer and the revenues it expects to earn under the electric service agreement. The electric service agreement also contains provisions for termination payments that will help ensure that there is no harm to Entergy Louisiana and its customers in the event of early termination. A directive was issued at the LPSC’s November 2024 meeting for the matter to be decided by October 2025. In February 2025 intervenors filed a motion asking the LPSC to deny Entergy Louisiana’s requested exemption from the LPSC’s order addressing competitive solicitation procedures and further asking the LPSC to dismiss the application. The ALJ issued an order denying the motion to dismiss the application and deferring the LPSC’s consideration of the motion regarding the competitive solicitation procedures until the hearing. In March 2025 the same intervenors filed a motion requesting the LPSC to require the customer and its parent company to be joined as parties to the proceeding or dismiss the application. In April 2025 the ALJ issued an order denying the March 2025 motion, and the moving parties filed a motion asking the LPSC to review and reverse the ALJ’s decision.
In February 2025, Entergy Louisiana filed supplemental testimony with the LPSC stating that the third combined cycle combustion turbine resource presented in the October 2024 application (Waterford 5 Power Station) would be sited at Entergy Louisiana’s Waterford site in Killona, Louisiana, alongside existing Entergy Louisiana generation resources. The testimony also notes that Entergy Louisiana is negotiating with the customer in response to the customer’s request to increase the load associated with its project in north Louisiana. The testimony indicates further that the additional load can be served without additional generation capacity beyond what was presented in the October 2024 application, but that additional transmission facilities, which will be funded directly by the customer, are needed to serve this additional load.
In April 2025 and May 2025 the LPSC staff and certain intervenors each filed their direct testimony and cross-answering testimony, respectively. The LPSC staff’s testimony discussed the significant projected benefits associated with the data center project; however, both the LPSC staff and such intervenors also identified purported risks associated with constructing the requested resources based on the terms and conditions under which the customer would be taking service. Both the LPSC staff and such intervenors also recommended that the LPSC impose certain conditions on its approval which, if adopted, would support approval of Entergy Louisiana’s application. The LPSC staff’s recommendations included a condition that would require, under specified circumstances, certain sharing of net revenues from service to the project with Entergy Louisiana’s other customers. The LPSC staff also recommended that the LPSC deny approval of the corporate sustainability rider terms providing for the customer to supply funding toward the cost of installing carbon capture and storage infrastructure at Entergy Louisiana’s Lake Charles Power Station. The Louisiana Energy Users Group and other intervenors recommended that the LPSC require various changes to the terms of the electric service agreement with the customer that would shift additional risk and cost to the customer rather than Entergy Louisiana’s broader customer base. Certain intervenors also challenged approval on the basis that Entergy Louisiana did not conduct a request for proposals to procure the proposed generation resources to serve the customer’s project; these intervenors also advocated that Entergy Louisiana be required to procure more renewable generation and evaluate transmission alternatives rather than proceeding with development of all of the proposed new generation resources. In May 2025, Entergy Louisiana filed its rebuttal testimony responding to the direct and cross-answering testimony of the LPSC staff and intervenors. The rebuttal testimony expressed support for or no opposition to the LPSC’s adoption of certain of the proposed recommendations and identified why other proposed recommendations should not be adopted. In addition, the rebuttal testimony stated that the negotiations related to the increase in the load amount for the customer’s project had concluded and that a rider to the electric service agreement reflecting this increase had been executed. In advance of the July 2025 hearing, Entergy Louisiana reached a settlement agreement with the LPSC staff and three separate intervenors. In August 2025, Entergy Louisiana, the LPSC staff, and the three separate intervenors jointly moved for consideration of the settlement agreement, and the LPSC issued an order accepting the settlement agreement. Franklin Farms Power Station Units 1 and 2 are expected to be in service in 2028, and Waterford 5 Power Station is expected to be in service in 2029.
Amite South Transmission Projects
As discussed in the Form 10-K, in March 2024, Entergy Louisiana filed an application with the LPSC seeking an exemption determination, or alternatively, a certificate of public convenience and necessity, for a transmission project that includes a new 500 kV/230 kV Commodore substation and an approximately 60-mile 230 kV line connecting the new Commodore substation to the Waterford substation. In February 2025, Entergy Louisiana and the LPSC staff jointly filed, for consideration by the LPSC, an uncontested stipulated settlement agreement resolving all issues in the proceeding. The LPSC approved the uncontested stipulated settlement agreement in March 2025 and thereby granted certification of the project.
As discussed in the Form 10-K, in December 2024, Entergy Louisiana filed an application with the LPSC seeking a certificate of public convenience and necessity for a 500 kV transmission project that includes the construction of a new 84-mile Commodore to Churchill 500 kV transmission line, the expansion of the Waterford 500 kV substation, the construction of a new Churchill 500 kV substation and improvements to the Churchill 230 kV substation, and the conversion of the existing 230 kV Waterford to Churchill transmission line to 500 kV, forming a 500 kV loop into the Downstream of Gypsy load pocket. In April 2025 the LPSC staff and the Louisiana Energy Users Group, an intervenor, filed direct testimony. The LPSC staff’s testimony recommends LPSC approval of the project. The Louisiana Energy Users Group’s testimony opines that Entergy Louisiana has shown that there is a need for additional transmission investment in the West Bank area of Amite South but recommends that the LPSC withhold approval pending further analysis, including analysis of potential lower cost alternatives to the proposed project, and also pending Entergy Louisiana demonstrating that it has contributions in aid of construction or minimum bill revenues from the customers whose block load additions would be enabled by the proposed transmission project in amounts sufficient to substantially, if not fully, cover the revenue requirement of the proposed project. In June 2025, Entergy Louisiana filed rebuttal testimony. The hearing was held in August 2025, and an LPSC decision is expected in first quarter 2026.
Traceview Advanced Power Station
Entergy Mississippi plans to construct, own, and operate the Traceview Advanced Power Station, a 754 MW combined cycle combustion turbine facility to be located in the City of Ridgeland, Madison County, Mississippi. The facility will be powered primarily by natural gas, and it will also be enabled for future carbon capture and storage and for hydrogen co-firing optionality. The Traceview Advanced Power Station is expected to cost in excess of $1 billion. The facility is expected to be in service in 2029.
Vicksburg Advanced Power Station
In October 2025, Entergy Mississippi announced plans to construct, own, and operate the Vicksburg Advanced Power Station, a 754 MW combined-cycle combustion turbine facility, to be located in the City of Vicksburg, Warren County, Mississippi. The facility will be powered primarily by natural gas, and it will also be enabled for future carbon capture and storage and for hydrogen co-firing optionality. The Vicksburg Advanced Power Station is expected to cost in excess of $1 billion. The facility is expected to be in service in 2028.
Legend Power Station and Lone Star Power Station
As discussed in the Form 10-K, in June 2024, Entergy Texas filed an application seeking PUCT approval to amend Entergy Texas’s certificate of convenience and necessity to construct, own, and operate the Legend Power Station, a 754 MW combined cycle combustion turbine facility, which will be enabled for future carbon capture and storage and for hydrogen co-firing optionality, to be located in Jefferson County, Texas, and the Lone Star Power Station, a 453 MW simple-cycle combustion turbine facility, which will be enabled with hydrogen co-firing optionality, originally expected to be located in Liberty County, Texas. In March 2025, Entergy Texas filed testimony explaining that Entergy Texas planned to move forward with building the Lone Star Power Station on a more cost-effective alternative site in San Jacinto County, Texas. A hearing on the merits was held in April 2025. Also in April 2025, Entergy Texas, intervenors, and the PUCT staff filed initial briefs. In its initial brief, the PUCT staff recommends denial of Entergy Texas’s application or, in the alternative, approval subject to conditions that include a prudence review by an external consultant if actual project costs exceed estimated costs by more than 10%, transmission cost reporting, and weatherization of both the Legend Power Station and the Lone Star Power Station. Certain intervenors requested that the PUCT impose various conditions upon the approval of the resources, including, among others, cost recovery limitations, a direction that Entergy Texas initiate a competitive tariff proceeding to facilitate industrial sleeving, a requirement for additional regulatory approvals related to hydrogen or carbon capture and storage implementation, limits on the recovery of supplemental filing costs, and calculation of AFUDC based on an adjusted weighted average cost of capital. Reply briefs were filed in May 2025. In June 2025 the ALJs with the State Office of Administrative Hearings issued a proposal for decision, in which they recommended rejection of Entergy Texas’s application to construct the Legend Power Station and the Lone Star Power Station based upon their finding that Entergy Texas did not demonstrate the resources to be cost-effective alternatives to address the uncontested need for additional generation. In the alternative, the ALJs recommended that if the PUCT approves the resources, that conditions be imposed, including a deferral of the finding that the resources were prudently selected until Entergy Texas’s next rate case, a prudence review by an external consultant if actual project costs exceed estimated costs by more than 10%, weatherization requirements, and a requirement that Entergy Texas obtain additional regulatory approvals prior to implementing hydrogen co-firing or carbon capture and storage. The ALJs’ proposal for decision is an interim step in the certification process, and it is not binding upon the PUCT. Entergy Texas filed exceptions in July 2025. In September 2025 the PUCT issued a decision granting the application, subject to conditions that include a cost cap at Entergy Texas’s previously-filed modified estimated costs of $1.6 billion for the Legend Power Station and $799 million for the Lone Star Power Station, weatherization requirements, environmental compliance requirements, and a requirement to request additional authorization prior to implementing hydrogen co-firing or carbon capture and storage. In October 2025 an intervenor filed a motion for rehearing requesting that the PUCT modify the Lone Star Power Station cost cap to reflect the estimated project costs associated with a new project site, clarify that the cost cap is inclusive of transmission upgrades, and reconsider the intervenor’s prior proposal for a “soft cost cap” below the estimated project costs, and that Entergy Texas be directed to initiate a competitive tariff proceeding to facilitate industrial sleeving of purchased power. Entergy Texas filed a response to the motion for rehearing in October 2025. Subject to receipt of required regulatory approval and other conditions, both facilities are expected to be in service by mid-2028.
Southeast Texas Area Reliability Project (SETEX)
In February 2025, Entergy Texas filed an application seeking PUCT approval to amend Entergy Texas’s certificate of convenience and necessity to construct, own, and operate a new single-circuit 500 kV transmission line and associated stations and 138/230 kV facilities. The transmission line is expected to be approximately 131 to 160 miles in length and the estimated cost of the project ranges from $1.3 billion to $1.5 billion, depending upon the route ultimately approved by the PUCT. Also in February 2025 the PUCT referred the proceeding to the State Office of Administrative Hearings. A hearing on the merits was held in May 2025. In July 2025 the ALJs with the State Office of Administrative Hearings issued a proposal for decision recommending the PUCT approve Entergy Texas’s application to construct SETEX and recommending the PUCT’s approval include selection of a specific route with an estimated cost of $1.4 billion. In October 2025 the PUCT issued a final order approving the requested amendment to Entergy Texas’s certificate of convenience and necessity to construct, own, and operate the new single-circuit 500 kV transmission line and associated stations and 138/230 kV facilities, and selecting the final route for the project, which has an estimated cost of $1.36 billion. Construction of the project is expected to be completed by the end of 2029.
Cypress to Legend 500 kV Transmission Line
In May 2025, Entergy Texas filed an application seeking PUCT approval to amend Entergy Texas’s certificate of convenience and necessity to construct, own, and operate a new single-circuit 500 kV transmission line. The transmission line is expected to be approximately 40 to 49 miles in length and the estimated cost of the project ranges from $392.7 million to $436.2 million, depending on the route ultimately approved by the PUCT. In June 2025 the PUCT referred the proceeding to the State Office of Administrative Hearings and a hearing on the merits was held in August 2025. A PUCT decision is expected in fourth quarter 2025. Subject to receipt of required regulatory approval and other conditions, construction of the project is expected to be completed by the end of 2028.
Resilience and Grid Hardening
In June 2024, Entergy Texas filed an application with the PUCT requesting approval of Phase I of its Texas Future Ready Resiliency Plan, a set of measures to begin accelerating the resiliency of Entergy Texas’s transmission and distribution system. Phase I is comprised of projects totaling approximately $335.1 million, including approximately $137 million of projects to be funded by Entergy Texas and approximately $198 million of projects contingent upon Entergy Texas’s receipt of grant funds in that amount from the Texas Energy Fund. The projects in Phase I include distribution and transmission hardening and modernization projects and targeted vegetation management projects to mitigate the risk of wildfire. These projects are expected to be implemented within approximately three years of PUCT approval. In January 2025 the PUCT unanimously approved Phase I of Entergy Texas’s Texas Future Ready Resiliency Plan, including the approximately $137 million of projects to be funded by Entergy Texas and application of performance metrics consistent with the unopposed settlement. The PUCT clarified that, while not part of Entergy Texas’s Phase I plan, Entergy Texas is permitted to pursue the remaining $198 million of identified projects and Texas Energy Fund grant funding for those projects. In February 2025 the PUCT issued an order adopting a new rule establishing the procedures for application to the grant fund. In July
2025, Entergy Texas submitted an application for approximately $200 million in grant funding from the Texas Energy Fund to implement the resilience projects originally included in its Texas Future Ready Resiliency Plan. In October 2025 the PUCT voted to approve the $200 million grant request in full.
Dividends
Declarations of dividends on Entergy Corporation common stock are made at the discretion of the Board. Among other things, the Board evaluates the level of Entergy Corporation common stock dividends based upon earnings per share from the Utility segment and the Parent and Other portion of the business, financial strength, and future investment opportunities. In October 2025 the Board declared a dividend of $0.64 per share.
Cash Flow Activity
As shown in Entergy’s Consolidated Statements of Cash Flows, cash flows for the nine months ended September 30, 2025 and 2024 were as follows:
| 2025 | 2024 | |
|---|---|---|
| (In Millions) | ||
| Cash and cash equivalents at beginning of period | $860 | $133 |
| Net cash provided by (used in): | ||
| Operating activities | 3,932 | 3,109 |
| Investing activities | (5,211) | (4,002) |
| Financing activities | 1,936 | 2,172 |
| Net increase in cash and cash equivalents | 657 | 1,279 |
| Cash and cash equivalents at end of period | $1,517 | $1,412 |
Net cash flow provided by operating activities increased $823 million for the nine months ended September 30, 2025 compared to the nine months ended September 30, 2024 primarily due to:
higher collections from Utility customers;
the receipt of $405 million in payments related to the sale of nuclear and solar production tax credits in third quarter 2025. See Note 3 to the financial statements in the Form 10-K and Note 10 to the financial statements herein for discussion of the nuclear and solar production tax credits;
the receipt of $313 million in advance payments related to customer agreements in 2025, which are recorded as current liabilities and included within changes in other working capital accounts;
the timing of payments to vendors; and
one-time bill credits of $92 million in third quarter 2024 to Entergy Arkansas’s retail customers through the Grand Gulf credit rider as a result of the System Energy settlement with the APSC. See Note 2 to the financial statements in the Form 10-K for discussion of the System Energy settlement agreement with the APSC and Entergy Arkansas’s Grand Gulf credit rider.
The increase was partially offset by higher fuel and purchased power payments and an increase of $168 million in interest paid. See Note 2 to the financial statements herein and in the Form 10-K for a discussion of fuel and purchased power cost recovery.
Net cash flow used in investing activities increased $1,209 million for the nine months ended September 30, 2025 compared to the nine months ended September 30, 2024 primarily due to:
an increase of $1,712 million in non-nuclear generation construction expenditures primarily due to higher spending by Entergy Arkansas on the Ironwood Power Station (formerly Lake Catherine Unit 5) project, by Entergy Louisiana on the Franklin Farms Power Station Units 1 and 2 project and the Sterlington Facility solar project, by Entergy Mississippi on the Delta Blues Advanced Power Station project, the Vicksburg Advanced Power Station project, and the Penton Solar project, and by Entergy Texas on the Lone Star Power Station project, the Legend Power Station project, and the Orange County Advanced Power Station project;
an increase of $340 million in distribution construction expenditures primarily due to increased investment in the resilience of the Utility distribution system and higher capital expenditures for storm restoration in 2025;
an increase of $168 million in transmission construction expenditures primarily due to higher spending by Entergy Louisiana on the Amite South transmission projects and increased spending on various other transmission projects in 2025;
an increase of $106 million in nuclear construction expenditures primarily due to increased spending on various nuclear projects in 2025;
cash collateral of $37 million posted in 2025 to support Entergy Louisiana’s obligations to MISO; and
an increase of $36 million in decommissioning trust fund investment activity.
the receipt of $491 million in proceeds from the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025. See Note 13 to the financial statements herein for discussion of the sale of the Entergy Louisiana and Entergy New Orleans natural gas distribution businesses on July 1, 2025;
the initial payment of approximately $308 million in August 2024 for the purchase of the Driver Solar facility by Entergy Arkansas;
the initial and substantial completion payments totaling approximately $186 million in 2024 for the purchase of the Walnut Bend Solar facility by Entergy Arkansas;
a decrease of $79 million in information technology capital expenditures primarily due to decreased spending on technology upgrade projects in 2025;
the initial payment of approximately $48 million in August 2024 for the purchase of the West Memphis Solar facility by Entergy Arkansas;
net receipts from storm reserve escrow accounts of $34 million in 2025 compared to net payments to storm reserve escrow accounts of $13 million in 2024; and
a decrease of $41 million in nuclear fuel purchases due to variations from year to year in the timing and pricing of fuel reload requirements, materials and services deliveries, and the timing of cash payments during the nuclear fuel cycle.
See Note 14 to the financial statements in the Form 10-K for discussion of the Driver Solar facility, the Walnut Bend Solar facility, and the West Memphis Solar facility purchases.
Net cash flow provided by financing activities decreased $236 million for the nine months ended September 30, 2025 compared to the nine months ended September 30, 2024 primarily due to:
long-term debt activity providing approximately $1,013 million of cash in 2025 compared to providing approximately $2,742 million of cash in 2024;
a decrease of $61 million in proceeds received from treasury stock issuances in 2025 due to a smaller amount of previously repurchased Entergy Corporation common stock issued in 2025 to satisfy stock option exercises as compared to 2024; and
an increase of $61 million in common stock dividends paid in 2025 as a result of an increase in the dividend paid per share in 2025 as compared to 2024.
$805 million in net proceeds from the issuance of common stock under the at the market equity distribution program in 2025. There were no issuances of common stock under the at the market equity distribution program in 2024;
net issuances of $488 million of commercial paper in 2025 as compared to net repayments of $16 million of commercial paper in 2024; and
an increase of $295 million in net customer advances for construction related to transmission, distribution, and generator interconnection agreements.
See Note 3 to the financial statements herein and Note 7 to the financial statements in the Form 10-K for discussion of Entergy Corporation’s at the market equity distribution program. See Note 4 to the financial statements herein and Notes 4 and 5 to the financial statements in the Form 10-K for details of Entergy’s commercial paper program and long-term debt.
Rate, Cost-recovery, and Other Regulation
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Rate, Cost-recovery, and Other Regulation” in the Form 10-K for discussions of rate regulation, federal regulation, and related regulatory proceedings.
See Note 2 to the financial statements herein for updates to the discussion in the Form 10-K regarding these proceedings.
See Note 2 to the financial statements herein for updates to the discussion in the Form 10-K regarding federal regulatory proceedings.
Market and Credit Risk Sensitive Instruments
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS – Market and Credit Risk Sensitive Instruments” in the Form 10-K for a discussion of market and credit risk sensitive instruments. The following is an update to that discussion.
Some of the agreements to sell the power produced by Entergy’s non-utility operations business contain provisions that require an Entergy subsidiary to provide credit support to secure its obligations under such agreements. The primary form of credit support used to satisfy these requirements is an Entergy Corporation guarantee. Cash and letters of credit are also acceptable forms of credit support. At September 30, 2025, based on power prices at that time, Entergy had no liquidity exposure under the guarantees in place supporting its non-utility operations business transactions and $10 million of posted cash collateral.
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS – Nuclear Matters” in the Form 10-K for a discussion of nuclear matters. The following is an update to that discussion.
The NRC’s Reactor Oversight Process is a program to collect information about plant performance, assess the information for its safety significance, and provide for appropriate licensee and NRC response. The NRC evaluates plant performance by analyzing two distinct inputs: inspection findings resulting from the NRC’s inspection program and performance indicators reported by the licensee. The evaluations result in the placement of each plant in one of the NRC’s Reactor Oversight Process Action Matrix columns: “licensee response column,” or Column 1, “regulatory response column,” or Column 2, “degraded cornerstone column,” or Column 3, “multiple/repetitive degraded cornerstone column,” or Column 4, and “unacceptable performance,” or Column 5. Plants in Column 1 are subject to normal NRC inspection activities. Plants in Column 2, Column 3, or Column 4 are subject to progressively increasing levels of inspection by the NRC with, in general, progressively increasing levels of associated costs. Continued plant operation is not permitted for plants in Column 5. All of the nuclear generating plants owned and operated by Entergy’s Utility business are currently in Column 1, except Waterford 3, which is in Column 2.
In June 2025 the NRC placed Waterford 3 in Column 2, effective second quarter 2025, based on the failure to properly develop and implement adequate maintenance instructions for the fuel linkage connection to the mechanical governor for an emergency diesel generator. In September 2025, Waterford 3 successfully completed the supplemental inspection related to the issue. Waterford 3 will return to Column 1, effective third quarter 2025, pending receipt of the NRC’s formal inspection report.
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Critical Accounting Estimates” in the Form 10-K for a discussion of the estimates and judgments necessary in Entergy’s accounting for nuclear decommissioning costs, utility regulatory accounting, taxation and uncertain tax positions, qualified pension and other postretirement benefits, and other contingencies.
See Note 1 to the financial statements in the Form 10-K for discussion of new accounting pronouncements. The following is an update to that discussion.
As discussed in the Form 10-K, in March 2024 the SEC issued final rules that require registrants to provide certain climate-related disclosures in annual reports and registration statements in order to enhance and standardize climate-related disclosures for investors. In April 2024 the SEC stayed the final rules, pending judicial review of consolidated challenges to the rules by the United States Court of Appeals for the Eighth Circuit. In March 2025 the SEC voted to end its defense of the final rules against parties that have legally challenged the rules. In April 2025 the United States Court of Appeals for the Eighth Circuit ordered the litigation to be held in abeyance and directed the SEC to indicate within 90 days whether the SEC would reconsider or review the climate disclosure rules. In July 2025 the SEC submitted a status report to the United States Court of Appeals for the Eighth Circuit stating that it does not intend to review or reconsider its final rules at this time and requesting that the Court of
Appeals terminate the abeyance and proceed with its judicial review of the case. In September 2025 the United States Court of Appeals for the Eighth Circuit paused its consideration of legal challenges against the rules, pending further action by the SEC. Entergy will continue to monitor developments related to the SEC’s final rules on climate-related disclosures.
| ENTERGY CORPORATION AND SUBSIDIARIES | ||||
|---|---|---|---|---|
| CONSOLIDATED INCOME STATEMENTS | ||||
| For the Three and Nine Months Ended September 30, 2025 and 2024 | ||||
| (Unaudited) | ||||
| Three Months Ended | Nine Months Ended | |||
| 2025 | 2024 | 2025 | 2024 | |
| (In Thousands, Except Share Data) | ||||
| OPERATING REVENUES | ||||
| Electric | $3,797,177 | $3,337,820 | $9,829,988 | $8,950,373 |
| Natural gas | 155 | 32,318 | 112,664 | 133,342 |
| Other | 14,687 | 18,962 | 45,090 | 53,633 |
| TOTAL | 3,812,019 | 3,389,100 | 9,987,742 | 9,137,348 |
| OPERATING EXPENSES | ||||
| Operation and Maintenance: | ||||
| Fuel, fuel-related expenses, and gas purchased for resale | 822,798 | 647,982 | 1,803,594 | 1,787,148 |
| Purchased power | 269,740 | 213,072 | 991,591 | 641,919 |
| Nuclear refueling outage expenses | 25,225 | 36,280 | 87,879 | 112,820 |
| Other operation and maintenance | 771,166 | 722,887 | 2,168,296 | 2,111,692 |
| Asset write-offs, impairments, and related charges (credits) | 12,795 | — | 12,795 | 131,775 |
| Decommissioning | 57,313 | 55,320 | 169,811 | 162,894 |
| Taxes other than income taxes | 232,371 | 192,127 | 632,910 | 572,077 |
| Depreciation and amortization | 525,385 | 498,481 | 1,560,911 | 1,503,505 |
| Other regulatory charges (credits) - net | (23,815) | (102,911) | (96,615) | 132,043 |
| TOTAL | 2,692,978 | 2,263,238 | 7,331,172 | 7,155,873 |
| OPERATING INCOME | 1,119,041 | 1,125,862 | 2,656,570 | 1,981,475 |
| OTHER INCOME (DEDUCTIONS) | ||||
| Allowance for equity funds used during construction | 53,887 | 33,126 | 149,210 | 89,196 |
| Interest and investment income | 106,090 | 64,316 | 226,915 | 285,600 |
| Miscellaneous - net | (50,409) | (66,932) | (79,405) | (460,226) |
| TOTAL | 109,568 | 30,510 | 296,720 | (85,430) |
| INTEREST EXPENSE | ||||
| Interest expense | 346,992 | 308,502 | 1,038,443 | 887,508 |
| Allowance for borrowed funds used during construction | (22,114) | (13,359) | (61,700) | (35,588) |
| TOTAL | 324,878 | 295,143 | 976,743 | 851,920 |
| INCOME BEFORE INCOME TAXES | 903,731 | 861,229 | 1,976,547 | 1,044,125 |
| Income taxes | 205,307 | 215,475 | 443,747 | 270,103 |
| CONSOLIDATED NET INCOME | 698,424 | 645,754 | 1,532,800 | 774,022 |
| Preferred dividend requirements of subsidiaries and noncontrolling interests | 4,624 | 814 | 10,310 | 4,879 |
| NET INCOME ATTRIBUTABLE TO ENTERGY CORPORATION | $693,800 | $644,940 | $1,522,490 | $769,143 |
| Earnings per average common share: | ||||
| Basic | $1.55 | $1.51 | $3.47 | $1.80 |
| Diluted | $1.53 | $1.50 | $3.40 | $1.79 |
| Basic average number of common shares outstanding | 446,532,648 | 428,024,935 | 438,746,880 | 427,185,273 |
| Diluted average number of common shares outstanding | 453,550,895 | 431,388,418 | 447,250,827 | 429,473,900 |
| See Notes to Financial Statements. | ||||
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.