ENTERGY CORP DE
For the period ended Mar 31, 2025. Filed May 1, 2025.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Mar 31, 2025 · Filed May 1, 2025
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Definitionsvii
DEFINITIONS
Certain abbreviations or acronyms used in the text and notes are defined below:
| Abbreviation or Acronym | Term |
|---|---|
| AFUDC | Allowance for Funds Used During Construction |
| ALJ | Administrative Law Judge |
| ANO 1 and 2 | Units 1 and 2 of Arkansas Nuclear One (nuclear), owned by Entergy Arkansas |
| APSC | Arkansas Public Service Commission |
| Board | Board of Directors of Entergy Corporation |
| Cajun | Cajun Electric Power Cooperative, Inc. |
| capacity factor | Actual plant output divided by maximum potential plant output for the period |
| City Council | Council of the City of New Orleans, Louisiana |
| D.C. Circuit | U.S. Court of Appeals for the District of Columbia Circuit |
| DOE | United States Department of Energy |
| Entergy | Entergy Corporation and its direct and indirect subsidiaries |
| Entergy Corporation | Entergy Corporation, a Delaware corporation |
| Entergy Gulf States, Inc. | Predecessor company for financial reporting purposes to Entergy Gulf States Louisiana that included the assets and business operations of both Entergy Gulf States Louisiana and Entergy Texas |
| Entergy Gulf States Louisiana | Entergy Gulf States Louisiana, L.L.C., a Louisiana limited liability company formally created as part of the jurisdictional separation of Entergy Gulf States, Inc. and the successor company to Entergy Gulf States, Inc. for financial reporting purposes. The term is also used to refer to the Louisiana jurisdictional business of Entergy Gulf States, Inc., as the context requires. Effective October 1, 2015, the business of Entergy Gulf States Louisiana was combined with Entergy Louisiana. |
| Entergy Louisiana | Entergy Louisiana, LLC, a Texas limited liability company formally created as part of the combination of Entergy Gulf States Louisiana and the company formerly known as Entergy Louisiana, LLC (Old Entergy Louisiana) into a single public utility company and the successor to Old Entergy Louisiana for financial reporting purposes |
| Entergy Texas | Entergy Texas, Inc., a Texas corporation formally created as part of the jurisdictional separation of Entergy Gulf States, Inc. The term is also used to refer to the Texas jurisdictional business of Entergy Gulf States, Inc., as the context requires. |
| Entergy Wholesale Commodities | Prior to January 1, 2023, one of Entergy’s reportable business segments consisting of non-utility business activities primarily comprised of the ownership, operation, and decommissioning of nuclear power plants, the ownership of interests in non-nuclear power plants, and the sale of the electric power produced by its operating power plants to wholesale customers |
| EPA | United States Environmental Protection Agency |
| FERC | Federal Energy Regulatory Commission |
| Form 10-K | Annual Report on Form 10-K for the calendar year ended December 31, 2024, filed with the SEC by Entergy Corporation and its Registrant Subsidiaries |
| GAAP | Generally Accepted Accounting Principles |
| Grand Gulf | Unit No. 1 of Grand Gulf Nuclear Station (nuclear), 90% owned or leased by System Energy |
| GWh | Gigawatt-hour(s), which equals one million kilowatt-hours |
| Independence | Independence Steam Electric Station (coal), owned 16% by Entergy Arkansas, 25% by Entergy Mississippi, and 7% by Entergy Power, LLC |
| IRS | Internal Revenue Service |
| ISO | Independent System Operator |
| kV | Kilovolt |
vii
DEFINITIONS (Concluded)
| Abbreviation or Acronym | Term |
|---|---|
| kW | Kilowatt, which equals one thousand watts |
| kWh | Kilowatt-hour(s) |
| LPSC | Louisiana Public Service Commission |
| LURC | Louisiana Utilities Restoration Corporation |
| MISO | Midcontinent Independent System Operator, Inc., a regional transmission organization |
| MMBtu | One million British Thermal Units |
| MPSC | Mississippi Public Service Commission |
| MW | Megawatt(s), which equals one thousand kilowatts |
| MWh | Megawatt-hour(s) |
| Net debt to net capital ratio | Gross debt less cash and cash equivalents divided by total capitalization less cash and cash equivalents, which is a non-GAAP measure |
| NRC | Nuclear Regulatory Commission |
| Palisades | Palisades Nuclear Plant (nuclear), previously owned as part of Entergy’s non-utility business, which ceased power production in May 2022 and was sold in June 2022 |
| Parent & Other | The portions of Entergy not included in the Utility segment, primarily consisting of the activities of the parent company, Entergy Corporation, and other business activity, including Entergy’s non-utility operations business which owns interests in non-nuclear power plants that sell the electric power produced by those plants to wholesale customers and also provides decommissioning services to nuclear power plants owned by non-affiliated entities in the United States |
| PPA | Purchased power agreement or power purchase agreement |
| PUCT | Public Utility Commission of Texas |
| Registrant Subsidiaries | Entergy Arkansas, LLC, Entergy Louisiana, LLC, Entergy Mississippi, LLC, Entergy New Orleans, LLC, Entergy Texas, Inc., and System Energy Resources, Inc. |
| River Bend | River Bend Station (nuclear), owned by Entergy Louisiana |
| SEC | Securities and Exchange Commission |
| System Agreement | Agreement, effective January 1, 1983, as modified, among the Utility operating companies relating to the sharing of generating capacity and other power resources. The agreement terminated effective August 2016. |
| System Energy | System Energy Resources, Inc. |
| Unit Power Sales Agreement | Agreement, dated as of June 10, 1982, as amended and approved by the FERC, among Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and System Energy, relating to the sale of capacity and energy from System Energy’s share of Grand Gulf |
| Utility | Entergy’s reportable segment that generates, transmits, distributes, and sells electric power, with a small amount of natural gas distribution in portions of Louisiana |
| Utility operating companies | Entergy Arkansas, Entergy Louisiana, Entergy Mississippi, Entergy New Orleans, and Entergy Texas |
| Waterford 3 | Unit No. 3 (nuclear) of the Waterford Steam Electric Station, owned by Entergy Louisiana |
| weather-adjusted usage | Electric usage excluding the effects of deviations from normal weather |
Entergy operates primarily through a single reportable segment, Utility. The Utility segment includes the generation, transmission, distribution, and sale of electric power in portions of Arkansas, Mississippi, Texas, and Louisiana, including the City of New Orleans; and operation of a small natural gas distribution business in portions of Louisiana. See Note 13 to the financial statements herein and the “Held for Sale - Natural Gas Distribution Businesses” section in Note 14 to the financial statements in the Form 10-K for discussion of the planned sale of the Entergy New Orleans and Entergy Louisiana natural gas distribution businesses. See Note 7 to the financial statements herein for discussion of and financial information regarding Entergy’s reportable segment.
First Quarter 2025 Compared to First Quarter 2024
Following are income statement variances for Utility, Parent & Other, and Entergy comparing the first quarter 2025 to the first quarter 2024 showing how much the line item increased or (decreased) in comparison to the prior period.
| Utility | Parent &Other (a) | Entergy | |
|---|---|---|---|
| (In Thousands) | |||
| 2024 Net Income (Loss) Attributable to Entergy Corporation | $195,224 | ($119,943) | $75,281 |
| Operating revenues | 57,424 | (5,178) | 52,246 |
| Fuel, fuel-related expenses, and gas purchased for resale | (265,421) | (6,674) | (272,095) |
| Purchased power | 122,890 | (5,286) | 117,604 |
| Other regulatory charges (credits) - net | (126,189) | — | (126,189) |
| Other operation and maintenance | (18,241) | 3,877 | (14,364) |
| Asset write-offs, impairments, and related charges (credits) | (131,775) | — | (131,775) |
| Taxes other than income taxes | 6,362 | (26) | 6,336 |
| Depreciation and amortization | 13,215 | 67 | 13,282 |
| Other income (deductions) | (29,552) | (5,046) | (34,598) |
| Interest expense | 54,983 | 7,608 | 62,591 |
| Other expenses | (2,739) | 64 | (2,675) |
| Income taxes | 79,725 | (678) | 79,047 |
| Preferred dividend requirements of subsidiaries and noncontrolling interests | 407 | — | 407 |
| 2025 Net Income (Loss) Attributable to Entergy Corporation | $489,879 | ($129,119) | $360,760 |
(a)Parent & Other includes eliminations, which are primarily intersegment activity.
First quarter 2024 results of operations include: (1) a $132 million ($97 million net-of-tax) charge, recorded at Utility, to reflect the write-off of a previously recorded regulatory asset as a result of an adverse decision in the Entergy Arkansas opportunity sales proceeding in March 2024; and (2) a $78 million ($57 million net-of-tax) regulatory charge, recorded at Utility, primarily to reflect a settlement in principle between Entergy New Orleans and the City Council in April 2024 for additional sharing with customers of income tax benefits from the resolution of the 2016-2018 IRS audit. See Note 2 to the financial statements herein and in the Form 10-K for discussion of the Entergy Arkansas opportunity sales proceeding. See Note 3 to the financial statements in the Form 10-K for discussion of the Entergy New Orleans April 2024 settlement in principle and discussion of the resolution of the 2016-2018 IRS audit.
Utility
| Amount | |
|---|---|
| (In Millions) | |
| 2024 operating revenues | $2,772 |
| Fuel, rider, and other revenues that do not significantly affect net income | (132) |
| Volume/weather | 114 |
| Retail electric price | 76 |
| 2025 operating revenues | $2,830 |
The Utility operating companies’ results include revenues from rate mechanisms designed to recover fuel, purchased power, and other costs such that the revenues and expenses associated with these items generally offset and do not affect net income. “Fuel, rider, and other revenues that do not significantly affect net income” includes the revenue variance associated with these items.
The volume/weather variance is primarily due to the effect of more favorable weather on residential sales and an increase in industrial usage. The increase in industrial usage is primarily due to an increase in demand from large industrial customers, primarily in the petroleum refining, chlor-alkali, and primary metals industries.
The retail electric price variance is primarily due to:
an increase in Entergy Arkansas’s formula rate plan rates effective January 2025;
an increase in Entergy Louisiana’s formula rate plan revenues, including an increase in the distribution recovery mechanism, effective September 2024, partially offset by decreases in formula rate plan revenues due to interim formula rate plan rate adjustments effective January 2025 and March 2025;
increases in Entergy Mississippi’s formula rate plan rates effective April 2024 and July 2024 and an increase in the interim facilities rate adjustment revenues effective January 2025; and
the implementation of the distribution cost recovery factor rider effective with the first billing cycle in October 2024 and an increase in the distribution cost recovery factor rider effective in late December 2024, each at Entergy Texas.
See Note 2 to the financial statements herein and in the Form 10-K for discussion of the regulatory proceedings discussed above.
Total electric energy sales for Utility for the three months ended March 31, 2025 and 2024 are as follows:
| 2025 | 2024 | % Change | |
|---|---|---|---|
| (GWh) | |||
| Residential | 8,784 | 7,758 | 13 |
| Commercial | 6,243 | 6,223 | — |
| Industrial | 13,833 | 12,661 | 9 |
| Governmental | 560 | 572 | (2) |
| Total retail | 29,420 | 27,214 | 8 |
| Sales for resale | 1,634 | 3,958 | (59) |
| Total | 31,054 | 31,172 | — |
See Note 12 to the financial statements herein for additional discussion of operating revenues.
Other Income Statement Items
Utility
Other operation and maintenance expenses decreased from $681 million for the first quarter 2024 to $662 million for the first quarter 2025 primarily due to contract costs of $12 million, in first quarter 2024, related to operational performance, customer service, and organizational health initiatives anda decrease of $8 million in compensation and benefits costs primarily due to a higher revision to estimated incentive-based compensation expense in first quarter 2025 as compared to first quarter 2024.
Asset write-offs, impairments, and related charges (credits) includesa $132 million charge to reflect the write-off, at Entergy Arkansas, of a previously recorded regulatory asset as a result of an adverse decision in the Entergy Arkansas opportunity sales proceeding in March 2024. See Note 2 to the financial statements herein and in the Form 10-K for discussion of the Entergy Arkansas opportunity sales proceeding.
Depreciation and amortization expenses increased primarily due to additions to plant in service and an increase in nuclear depreciation rates at Entergy Louisiana effective September 2024 in accordance with the global stipulated settlement agreement approved by the LPSC in August 2024. The increase was partially offset by the recognition of $14 million in depreciation expense in first quarter 2024 at Entergy Texas for the 2022 base rate case relate back period, effective over six months beginning January 2024. The recognition of depreciation expense for the relate back period was effective over the same period as collections from the relate back surcharge rider and resulted in no effect on net income. See Note 2 to the financial statements in the Form 10-K for discussion of the global stipulated settlement agreement. See Note 2 to the financial statements in the Form 10-K for discussion of the 2022 base rate case at Entergy Texas.
Other regulatory charges (credits) - net includesa regulatory charge of$78 million, recorded by Entergy New Orleans in first quarter 2024, primarily to reflect a settlement in principle between Entergy New Orleans and the City Council in April 2024 for additional sharing with customers of income tax benefits from the resolution of the 2016-2018 IRS audit. See Note 3 to the financial statements in the Form 10-K for discussion of the April 2024 settlement in principle and for discussion of the resolution of the 2016-2018 IRS audit. In addition, Entergy records a regulatory charge or credit for the difference between asset retirement obligation-related expenses and nuclear decommissioning trust earnings plus asset retirement obligation-related costs collected in revenue.
Other income decreased primarily due to changes in decommissioning trust fund activity, including portfolio rebalancing of decommissioning trust funds in first quarter 2024, partially offset by an increase in the allowance for equity funds used during construction due to higher construction work in progress in 2025 and an increase in the amortization of tax gross ups on customer advances for construction.
Interest expense increased primarily due to:
the issuances by Entergy Arkansas of $400 million of 5.75% Series mortgage bonds and $400 million of 5.45% Series mortgage bonds, each in May 2024;
the issuance by Entergy Louisiana of $700 million of 5.15% Series mortgage bonds in August 2024;
the issuance by Entergy Louisiana of $750 million of 5.80% Series mortgage bonds in January 2025;
the issuance by Entergy Mississippi of $300 million of 5.85% Series mortgage bonds in May 2024;
the issuance by Entergy Texas of $350 million of 5.55% Series mortgage bonds in August 2024;
the issuance by System Energy of $300 million of 5.30% Series mortgage bonds in December 2024; and
carrying costs on customer advances for construction.
The effective income tax rate was 21.6% for the first quarter 2025. The difference in the effective income tax rate for the first quarter 2025 versus the federal statutory rate of 21% was primarily due to the accrual for state income taxes, partially offset by certain book and tax differences related to utility plant items and book and tax differences related to the allowance for equity funds used during construction.
The effective income tax rate was 21.5% for thefirst quarter 2024. The difference in the effective income tax rate for thefirst quarter 2024 versus the federal statutory rate of 21% was primarily due to the amortization of state accumulated deferred income taxes as a result of tax rate changes, a provision for uncertain tax positions, and the accrual for state income taxes, partially offset by certain book and tax differences related to utility plant items and book and tax differences related to the allowance for equity funds used during construction.
Entergy Wholesale Commodities Exit from the Merchant Power Business
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS -Entergy Wholesale Commodities Exit from the Merchant Power Business” in the Form 10-K for discussion of the exit from the merchant power business.
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Liquidity and Capital Resources” in the Form 10-K for a discussion of Entergy’s capital structure, capital spending plans and other uses of capital, and sources of capital. The following are updates to that discussion.
Recent announcements of changes to international trade policy and tariffs and further similar changes may impact Entergy’s business, operations, results of operations, and liquidity and capital resources. Potential impacts may include increases in costs associated with Entergy’s capital investments or operations and maintenance expenses; operational impacts, such as supply chain, manufacturing or raw materials sourcing disruptions which may affect Entergy’s ability to make planned capital investments as and when expected and needed; legal uncertainties, such as potential legal or other challenges to presidential tariff authority; or broader economic risks, including shifting customer demand, impacts on customer investment decisions, and volatile or uncertain credit and capital markets, which may affect Entergy’s ability to access needed capital. The nature and extent of any such effects will depend on, among other things, the specifics of the changes that are ultimately implemented both domestically and internationally, the responses of vendors, suppliers, and other counterparties to those changes, indirect effects on the price and availability of non-tariffed goods, and the effectiveness of mitigation measures.
Capital Structure and Resources
Entergy’s debt to capital ratio is shown in the following table. The increase in the debt to capital ratio is primarily due to the net issuance of long-term debt in 2025.
| March 31, 2025 | December 31, 2024 | |
|---|---|---|
| Debt to capital | 66.7% | 65.3% |
| Effect of excluding securitization bonds | (0.2%) | (0.2%) |
| Debt to capital, excluding securitization bonds (non-GAAP) (a) | 66.5% | 65.1% |
| Effect of subtracting cash | (1.1%) | (0.7%) |
| Net debt to net capital, excluding securitization bonds (non-GAAP) (a) | 65.4% | 64.4% |
(a)Calculation excludes the Texas securitization bonds, which are non-recourse to Entergy Texas.
As of March 31, 2025, 21.1% of the debt outstanding is at the parent company, Entergy Corporation, and 78.9% is at the Utility. Net debt consists of debt less cash and cash equivalents. Debt consists of notes payable and commercial paper, finance lease obligations, and long-term debt, including the currently maturing portion. Capital consists of debt, equity, and subsidiaries’ preferred stock without sinking fund. Net capital consists of capital less cash and cash equivalents. The debt to capital ratio excluding securitization bonds and net debt to net capital ratio excluding securitization bonds are non-GAAP measures. Entergy uses the debt to capital ratios excluding securitization bonds in analyzing its financial condition and believes they provide useful information to its investors and creditors in evaluating Entergy’s financial condition because the securitization bonds are non-recourse to Entergy, as more fully described in Note 5 to the financial statements in the Form 10-K. Entergy also uses the net debt to net capital ratio excluding securitization bonds in analyzing its financial condition and believes it provides useful information to its investors and creditors in evaluating Entergy’s financial condition because net debt indicates Entergy’s outstanding debt position that could not be readily satisfied by cash and cash equivalents on hand.
Entergy Corporation has in place a credit facility that has a borrowing capacity of $3 billion and expires in June 2029. The facility includes fronting commitments for the issuance of letters of credit against $20 million of the total borrowing capacity of the credit facility. The commitment fee is currently 0.225% of the undrawn commitment amount. Commitment fees and interest rates on loans under the credit facility can fluctuate depending on the senior unsecured debt ratings of Entergy Corporation. As there were no borrowings under the facility for the three months ended March 31, 2025, the estimated interest rate as of March 31, 2025 that would have been applied to outstanding borrowings under the facility was 5.92%. The following is a summary of the amounts outstanding and capacity available under the credit facility as of March 31, 2025:
| Capacity | Borrowings | Lettersof Credit | CapacityAvailable |
|---|---|---|---|
| (In Millions) | |||
| $3,000 | $— | $4 | $2,996 |
Entergy Corporation’s credit facility includes a covenant requiring Entergy to maintain a consolidated debt ratio, as defined, of 65% or less of its total capitalization. The calculation of this debt ratio under Entergy Corporation’s credit facility is different than the calculation of the debt to capital ratio above. Entergy is currently in compliance with the covenant and expects to remain in compliance with this covenant. If Entergy fails to meet this ratio, or if Entergy Corporation or one of the Registrant Subsidiaries (except Entergy New Orleans and System
Energy) defaults on other indebtedness or is in bankruptcy or insolvency proceedings, an acceleration of the Entergy Corporation credit facility’s maturity date may occur. See Note 4 to the financial statements herein for additional discussion of the Entergy Corporation credit facility and discussion of the Registrant Subsidiaries’ credit facilities.
Entergy Corporation has a commercial paper program with a Board-approved program limit of $2 billion. As of March 31, 2025, Entergy Corporation had $1,330 million of commercial paper outstanding. The weighted-average interest rate for the three months ended March 31, 2025 was 4.66%.
Equity Issuances and Equity Distribution Program
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Liquidity and Capital Resources - Sources of Capital - Equity Issuances and Equity Distribution Program” in the Form 10-K and Note 3 to the financial statements herein for discussion of equity issuances and the equity distribution program. The following is an update to that discussion.
In March 2025, Entergy marketed an equity offering of 17.8 million shares of Entergy Corporation common stock. In lieu of issuing equity at the time of the offering, Entergy entered into forward sale agreements with several forward counterparties. The forward sale agreements require Entergy to, at its election on or prior to September 30, 2026, either (1) physically settle the transactions by issuing the total of 17.8 million shares of its common stock to the forward counterparties in exchange for net proceeds at the then-applicable forward sale price specified by the agreements (initially $81.87 per share) or (2) net settle the transactions in whole or in part through the delivery or receipt of cash or shares. The forward sale price is subject to adjustment on a daily basis based on a floating interest rate factor and will decrease by other fixed amounts specified in the agreements. See Note 3 to the financial statements herein for further discussion of the forward sale agreements.
Capital Expenditure Plans and Other Uses of Capital
See the table and discussion in the Form 10-K under “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Liquidity and Capital Resources - Capital Expenditure Plans and Other Uses of Capital,” that sets forth the amounts of Entergy’s planned construction and other capital investments for 2025 through 2027. The following are updates to that discussion.
Other Generation
Lake Catherine Unit 5
As discussed in the Form 10-K, in November 2024, Entergy Arkansas filed an application with the APSC seeking a certificate of environmental compatibility and public need for the construction and operation of Lake Catherine Unit 5, a 446 MW hydrogen-capable simple-cycle natural gas combustion turbine facility to be located at the existing Lake Catherine facility site in Hot Spring County, Arkansas. In December 2024 other parties, including the APSC general staff, filed testimony opposing the resource, although the APSC general staff recognized the capacity need for the resource. Entergy Arkansas filed testimony in January 2025 further supporting its application, and in February 2025 the opposing parties filed responsive rebuttal testimony continuing to dispute the estimated costs and to dispute that Entergy Arkansas performed a market solicitation sufficient to demonstrate that this resource is the most reasonable option for customers. Also in February 2025, Entergy Arkansas filed surrebuttal testimony responding to the opposing parties’ testimony. A hearing was held in March 2025, and in April 2025 the APSC issued an order approving certification of the facility. The order also provided a presumption of prudence finding with respect to a benchmark project cost, which excluded AFUDC and contingency among other items. Entergy Arkansas will have the opportunity to later present all actual costs to the APSC for review for a prudence determination, including any costs incremental to the benchmark. Entergy Arkansas is evaluating potential responses to the APSC order. Subject to receipt of required regulatory approval and other conditions, the facility is expected to be in service by the end of 2028.
Entergy Louisiana Additional Generation and Transmission Resources
As discussed in the Form 10-K, in October 2024, Entergy Louisiana filed an application with the LPSC seeking approval of a variety of generation and transmission resources proposed in connection with establishing service to a new data center to be developed by a subsidiary of Meta Platforms, Inc. in north Louisiana, for which an electric service agreement has been executed. The filing requests LPSC certification of three new combined cycle combustion turbine generation resources totaling 2,262 MW, each of which will be enabled for future carbon capture and storage, a new 500 kV transmission line, and 500 kV substation upgrades. The application also requests approval to implement a corporate sustainability rider applicable to the new customer. The corporate sustainability rider contemplates the new customer contributing to the costs of the future addition of 1,500 MW of new solar and energy storage resources, agreements involving carbon capture and storage at Entergy Louisiana’s existing Lake Charles Power Station, and potential future wind and nuclear resources. Entergy Louisiana anticipates funding the incremental cost to serve the customer through direct financial contributions from the customer and the revenues it expects to earn under the electric service agreement. The electric service agreement also contains provisions for termination payments that will help ensure that there is no harm to Entergy Louisiana and its customers in the event of early termination. A directive was issued at the LPSC’s November 2024 meeting for the matter to be decided by October 2025. In February 2025 intervenors filed a motion asking the LPSC to deny Entergy Louisiana’s requested exemption from the LPSC’s order addressing competitive solicitation procedures and further asking the LPSC to dismiss the application. The ALJ issued an order denying the motion to dismiss the application and deferring the LPSC’s consideration of the motion regarding the competitive solicitation procedures until the hearing. In March 2025 the same intervenors filed a motion requesting the LPSC to require the customer and its parent company to be joined as parties to the proceeding or dismiss the application. In April 2025 the ALJ issued an order denying the March 2025 motion, and the moving parties filed a motion asking the LPSC to review and reverse the ALJ’s decision. In April 2025 the LPSC staff and intervenors filed direct testimony. The LPSC staff’s testimony discusses the significant projected benefits associated with the data center project and also recommends that the LPSC impose certain conditions on its approval, including a condition that would require, under specified circumstances, certain sharing of net revenues from service to the project with Entergy Louisiana’s other customers. The LPSC staff also recommends that the LPSC deny approval of the corporate sustainability rider terms providing for the customer to supply funding toward the cost of installing carbon capture and storage infrastructure at Entergy Louisiana’s Lake Charles Power Station. The Louisiana Energy Users Group and other intervenors recommended that the LPSC require various changes to the terms of the electric service agreement with the customer that would shift additional risk and cost to the customer rather than Entergy Louisiana’s broader customer base. Certain intervenors also challenged approval on the basis that Entergy Louisiana did not conduct a request for proposals to procure the proposed generation resources to serve the customer’s project; these intervenors also advocate that Entergy Louisiana be required to procure more renewable generation and evaluate transmission alternatives rather than proceeding with development of all of the proposed new generation resources. Entergy Louisiana’s rebuttal testimony is due in May 2025, and a hearing is set for July 2025.
Entergy Louisiana Transmission Projects
As discussed in the Form 10-K, in March 2024, Entergy Louisiana filed an application with the LPSC seeking an exemption determination, or alternatively, a certificate of public convenience and necessity, for a transmission project that includes a new 500 kV/230 kV Commodore substation and an approximately 60-mile 230 kV line connecting the new Commodore substation to the Waterford substation. In February 2025, Entergy Louisiana and the LPSC staff jointly filed, for consideration by the LPSC, an uncontested stipulated settlement agreement resolving all issues in the proceeding. The LPSC approved the uncontested stipulated settlement agreement in March 2025 and thereby granted certification of the project.
As discussed in the Form 10-K, in December 2024, Entergy Louisiana filed an application with the LPSC seeking a certificate of public convenience and necessity for a 500 kV transmission project that includes the construction of a new 84-mile Commodore to Churchill 500 kV transmission line, the expansion of the Waterford
500 kV substation, the construction of a new Churchill 500 kV substation and improvements to the Churchill 230 kV substation, and the conversion of the existing 230 kV Waterford to Churchill transmission line to 500 kV, forming a 500 kV loop into the Downstream of Gypsy load pocket. In April 2025 the LPSC staff and the Louisiana Energy Users Group, an intervenor, filed direct testimony. The LPSC staff’s testimony recommends LPSC approval of the project. The Louisiana Energy Users Group’s testimony opines that Entergy Louisiana has shown that there is a need for additional transmission investment in the West Bank area of Amite South but recommends that the LPSC withhold approval pending further analysis, including analysis of potential lower cost alternatives to the proposed project, and also pending Entergy Louisiana demonstrating that it has contributions in aid of construction from the customers whose block load additions would be enabled by the proposed transmission project in amounts sufficient to substantially, if not fully, cover the revenue requirement of the proposed project. Discovery is ongoing in the proceeding, and a hearing is set for August 2025.
Legend Power Station and Lone Star Power Station
As discussed in the Form 10-K, in June 2024, Entergy Texas filed an application seeking PUCT approval to amend Entergy Texas’s certificate of convenience and necessity to construct, own, and operate the Legend Power Station, a 754 MW combined-cycle combustion turbine facility, which will be enabled for future carbon capture and storage and for hydrogen co-firing optionality, to be located in Jefferson County, Texas, and the Lone Star Power Station, a 453 MW simple-cycle combustion turbine facility, which will be enabled with hydrogen co-firing optionality, to be located in Liberty County, Texas. A hearing on the merits was held in April 2025. Also in April 2025, Entergy Texas, intervenors, and the PUCT staff filed initial briefs. In its initial brief, the PUCT staff recommends denial of Entergy Texas’s application or, in the alternative, approval subject to conditions that include a prudence review by an external consultant if actual project costs exceed estimated costs by more than 10%, transmission cost reporting, and weatherization of both the Legend Power Station and the Lone Star Power Station. Certain intervenors requested that the PUCT impose various conditions upon the approval of the resources, including, among others, cost recovery limitations, a direction that Entergy Texas initiate a competitive tariff proceeding to facilitate industrial sleeving, a requirement for additional regulatory approvals related to hydrogen or carbon capture and storage implementation, limits on the recovery of supplemental filing costs, and calculation of AFUDC based on an adjusted weighted average cost of capital. Reply briefs are due in May 2025. A PUCT decision is expected in third quarter 2025. Subject to receipt of required regulatory approval and other conditions, both facilities are expected to be in service by mid-2028.
SETEX Area Reliability Project
In February 2025, Entergy Texas filed an application seeking PUCT approval to amend Entergy Texas’s certificate of convenience and necessity to construct, own, and operate a new single-circuit 500 kV transmission line and associated stations and 138/230 kV facilities. The transmission line is expected to be approximately 131 to 160 miles in length and the estimated cost of the project ranges from $1.3 billion to $1.5 billion, depending upon the route ultimately approved by the PUCT. Also in February 2025 the PUCT referred the proceeding to the State Office of Administrative Hearings. In March 2025 the ALJs with the State Office of Administrative Hearings adopted a procedural schedule with a hearing on the merits to be held in May 2025. A PUCT decision is expected in third quarter 2025. Subject to receipt of required regulatory approval and other conditions and approvals, construction of the project is expected to be completed by the end of 2029.
Dividends
Declarations of dividends on Entergy Corporation common stock are made at the discretion of the Board. Among other things, the Board evaluates the level of Entergy Corporation common stock dividends based upon earnings per share from the Utility segment and the Parent and Other portion of the business, financial strength, and future investment opportunities. In April 2025, the Board declared a dividend of $0.60 per share.
Cash Flow Activity
As shown in Entergy’s Consolidated Statements of Cash Flows, cash flows for the three months ended March 31, 2025 and 2024 were as follows:
| 2025 | 2024 | |
|---|---|---|
| (In Millions) | ||
| Cash and cash equivalents at beginning of period | $860 | $133 |
| Net cash provided by (used in): | ||
| Operating activities | 536 | 521 |
| Investing activities | (1,711) | (1,288) |
| Financing activities | 1,828 | 1,929 |
| Net increase in cash and cash equivalents | 653 | 1,162 |
| Cash and cash equivalents at end of period | $1,513 | $1,295 |
Net cash flow provided by operating activities increased $15 million for the three months ended March 31, 2025 compared to the three months ended March 31, 2024 primarily due to the timing of payments to vendors and the receipt of $108 million in advance payments related to customer agreements. The increase was offset by higher fuel and purchased power payments, an increase of $89 million in interest paid, and the timing of recovery of fuel and purchased power costs. See Note 2 to the financial statements herein and in the Form 10-K for a discussion of fuel and purchased power cost recovery.
Net cash flow used in investing activities increased $423 million for the three months ended March 31, 2025 compared to the three months ended March 31, 2024 primarily due to:
an increase of $502 million in non-nuclear generation construction expenditures primarily due to higher spending by Entergy Louisiana on new generation resources in north Louisiana, by Entergy Mississippi on the Delta Blues Advanced Power Station project and the Penton Solar project, and by Entergy Texas on the Orange County Advanced Power Station project and the Legend Power Station project;
an increase of $144 million in distribution construction expenditures primarily due to increased investment in the resilience of the Utility distribution system and higher capital expenditures for storm restoration in 2025. The increase in storm restoration expenditures is primarily due to Hurricane Francine restoration efforts in 2025;
an increase of $83 million in nuclear construction expenditures primarily due to increased spending on various nuclear projects in 2025; and
an increase of $64 million in transmission construction expenditures primarily due to increased spending on various transmission projects in 2025.
The increase was partially offset by:
the initial payment of approximately $170 million in February 2024 for the purchase of the Walnut Bend Solar facility by Entergy Arkansas;
a decrease of $113 million in information technology capital expenditures primarily due to decreased spending on various technology projects in 2025;
a decrease of $45 million in nuclear fuel purchases due to variations from year to year in the timing and pricing of fuel reload requirements, materials and services deliveries, and the timing of cash payments during the nuclear fuel cycle; and
net receipts from storm reserve escrow accounts of $39 million in 2025 compared to payments to storm reserve escrow accounts of $5 million in 2024.
See Note 14 to the financial statements in the Form 10-K for discussion of the Walnut Bend Solar facility purchase.
Net cash flow provided by financing activities decreased $101 million for the three months ended March 31, 2025 compared to the three months ended March 31, 2024 primarily due to a decrease of $373 million in net issuances of commercial paper in 2025 as compared to 2024, partially offset by long-term debt activity providing approximately $1,595 million of cash in 2025 compared to providing approximately $1,371 million of cash in 2024 and an increase of $48 million in advance payments from customers for construction related to transmission, distribution, and generator interconnection agreements. See Note 4 to the financial statements herein and Notes 4 and 5 to the financial statements in the Form 10-K for details of Entergy’s commercial paper program and long-term debt.
Rate, Cost-recovery, and Other Regulation
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Rate, Cost-recovery, and Other Regulation” in the Form 10-K for discussions of rate regulation, federal regulation, and related regulatory proceedings.
See Note 2 to the financial statements herein for updates to the discussion in the Form 10-K regarding these proceedings.
See Note 2 to the financial statements herein for updates to the discussion in the Form 10-K regarding federal regulatory proceedings.
Market and Credit Risk Sensitive Instruments
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS – Market and Credit Risk Sensitive Instruments” in the Form 10-K for a discussion of market and credit risk sensitive instruments. The following is an update to that discussion.
Some of the agreements to sell the power produced by Entergy’s non-utility operations business contain provisions that require an Entergy subsidiary to provide credit support to secure its obligations under such agreements. The primary form of credit support used to satisfy these requirements is an Entergy Corporation guarantee. Cash and letters of credit are also acceptable forms of credit support. At March 31, 2025, based on power prices at that time, Entergy had no liquidity exposure under the guarantees in place supporting its non-utility operations business transactions and $3 million of posted cash collateral.
See “MANAGEMENT’S FINANCIAL DISCUSSION AND ANALYSIS - Critical Accounting Estimates” in the Form 10-K for a discussion of the estimates and judgments necessary in Entergy’s accounting for nuclear decommissioning costs, utility regulatory accounting, taxation and uncertain tax positions, qualified pension and other postretirement benefits, and other contingencies.
See Note 1 to the financial statements in the Form 10-K for discussion of new accounting pronouncements. The following is an update to that discussion.
As discussed in the Form 10-K, in March 2024 the SEC issued final rules that require registrants to provide certain climate-related disclosures in annual reports and registration statements in order to enhance and standardize climate-related disclosures for investors. In April 2024 the SEC stayed the final rules, pending judicial review of consolidated challenges to the rules by the United States Court of Appeals for the Eighth Circuit. In March 2025, the SEC voted to end its defense of the final rules against parties that have legally challenged the rules. Entergy will continue to monitor developments related to the SEC’s stay of, and subsequent vote to end its defense in litigation of, the rules.
| ENTERGY CORPORATION AND SUBSIDIARIES | ||
|---|---|---|
| CONSOLIDATED INCOME STATEMENTS | ||
| For the Three Months Ended March 31, 2025 and 2024 | ||
| (Unaudited) | ||
| 2025 | 2024 | |
| (In Thousands, Except Share Data) | ||
| OPERATING REVENUES | ||
| Electric | $2,757,866 | $2,706,506 |
| Natural gas | 71,731 | 65,667 |
| Other | 17,277 | 22,455 |
| TOTAL | 2,846,874 | 2,794,628 |
| OPERATING EXPENSES | ||
| Operation and Maintenance: | ||
| Fuel, fuel-related expenses, and gas purchased for resale | 344,522 | 616,617 |
| Purchased power | 345,746 | 228,142 |
| Nuclear refueling outage expenses | 33,041 | 38,263 |
| Other operation and maintenance | 672,667 | 687,031 |
| Asset write-offs, impairments, and related charges (credits) | — | 131,775 |
| Decommissioning | 55,929 | 53,382 |
| Taxes other than income taxes | 198,765 | 192,429 |
| Depreciation and amortization | 512,943 | 499,661 |
| Other regulatory charges (credits) - net | (16,843) | 109,346 |
| TOTAL | 2,146,770 | 2,556,646 |
| OPERATING INCOME | 700,104 | 237,982 |
| OTHER INCOME | ||
| Allowance for equity funds used during construction | 44,018 | 26,794 |
| Interest and investment income | 33,406 | 150,697 |
| Miscellaneous - net | 14,726 | (50,743) |
| TOTAL | 92,150 | 126,748 |
| INTEREST EXPENSE | ||
| Interest expense | 348,384 | 277,743 |
| Allowance for borrowed funds used during construction | (18,593) | (10,543) |
| TOTAL | 329,791 | 267,200 |
| INCOME BEFORE INCOME TAXES | 462,463 | 97,530 |
| Income taxes | 100,041 | 20,994 |
| CONSOLIDATED NET INCOME | 362,422 | 76,536 |
| Preferred dividend requirements of subsidiaries and noncontrolling interests | 1,662 | 1,255 |
| NET INCOME ATTRIBUTABLE TO ENTERGY CORPORATION | $360,760 | $75,281 |
| Earnings per average common share: | ||
| Basic | $0.84 | $0.18 |
| Diluted | $0.82 | $0.18 |
| Basic average number of common shares outstanding | 430,347,768 | 426,287,439 |
| Diluted average number of common shares outstanding | 440,648,342 | 427,746,256 |
| See Notes to Financial Statements. | ||
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.