LOEWS CORP
For the period ended Jun 30, 2026. Filed Aug 3, 2026.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Jun 30, 2026 · Filed Aug 3, 2026
Extracted filing text, with the paragraph anchors used by the comparison.
See the whole filing, with its images and exhibitsContents
Boardwalk Pipelines
Current Growth Projects
Boardwalk Pipelines regularly reviews opportunities to expand its existing facilities and footprint to meet growing demand for transportation and storage services. The recent growth of liquefied natural gas export and power generation demand has led to the announcement of additional growth projects for Boardwalk Pipelines. Through the date of this filing, Boardwalk Pipelines has growth projects for which it has executed precedent or long-term firm transportation agreements that are expected to increase capacity on its pipeline systems by an aggregate of 4.5 billion cubic feet per day (“Bcf/d”) and its storage working gas capacity by 10 Bcf at an expected aggregate cost of approximately $3.4 billion and are scheduled to be completed through 2030. Through June 30, 2026, Boardwalk Pipelines has spent $381 million on these growth projects. These projects remain contingent upon, among other things, the receipt of required regulatory approvals and permits and are subject to construction risk.
These projects have lengthy planning and construction periods and, as a result, will not contribute to Boardwalk Pipelines’ earnings and cash flows until they receive the required regulatory approvals and permits and are constructed and placed into service over the next several years. For further discussion of capital expenditures and financing, please see Liquidity and Capital Resources: Subsidiaries of this MD&A. Boardwalk Pipelines’ cost and timing estimates for these projects are based on a variety of inputs such as contractor indicative bids, quotes on materials and internally-developed financial models, metrics and timelines and are subject to a variety of risks and uncertainties, including obtaining timely regulatory and permit approvals and the cost thereof, adverse weather conditions during construction, its ability to acquire and the cost of obtaining rights to construct and operate on land not owned by Boardwalk Pipelines, delays in obtaining and shortages and price increases for key materials (including pipe, compressor facilities and related equipment), tariff implications and shortages and increased costs of qualified labor. Factors in the estimates include, among other things, those related to pipeline costs based on mileage, size and type of pipe, materials including compressors and related equipment, land, engineering and construction costs and timely receipt of all necessary permits and approvals. Actual costs and timing of in-service dates for Boardwalk Pipelines’ growth projects may differ, perhaps materially, from its estimates. In addition, failure to timely meet development milestones may result in, among other things, contractual counterparties having the ability to terminate contracts with Boardwalk Pipelines. Refer to Part I, Item 1. Business and Part I, Item 1A. Risk Factors in our Annual Report on Form 10-K for the year ended December 31, 2025 for project descriptions and additional risks associated with Boardwalk Pipelines’ growth projects and the related financing.
Boardwalk Pipelines’ more significant growth projects are listed below:
| Expected in-service date | Expected incremental capacity added to system(Bcf/d) | |
|---|---|---|
| Eunice - Iowa (a) | September 2026 | 0.1 |
| Carnation Project (b) | Fourth quarter 2027 | 0.2 |
| Northeast Texas Power Plant Project (c) | Fourth quarter 2027 | 0.3 |
| Kosciusko Junction Project (c) | First half 2028 | 1.2 |
| Ohio Power Plant Project (c) | First half 2028 | 0.3 |
| Southeast Compression for Utility Reliability Expansion Project (c) | First half 2028 | 0.3 |
| Parks Line Upgrade and Sorrento Station Project (a) | First half 2028 | 0.2 |
| Texas Gateway Project (c) | Second half 2029 | 1.8 |
| Petal Gas Storage Expansion (d) | Second half 2030 | (d) |
| (a) | These projects have received approval from the Federal Energy Regulatory Commission (“FERC”) and construction has commenced. |
|---|---|
| (b) | This project remains subject to FERC approval and receipt of environmental permits and authorizations. |
| (c) | These projects remain subject to FERC approval, acquisition of land rights and receipt of environmental permits and authorizations. |
| (d) | This project remains subject to FERC approval and is expected to add 10 Bcf of storage working gas capacity. |
Refer to Current Growth Projects in Part I, Item 1. Business in our Annual Report on Form 10-K for the year ended December 31, 2025 for further discussion of Boardwalk Pipelines’ significant growth projects. Boardwalk Pipelines’ growth projects include $9.4 billion of estimated revenues that are anticipated under executed precedent or long-term firm transportation agreements for growth projects that are contingent upon, among other things, receipt of required regulatory approvals and permits and are subject to construction risk.
In addition to growth projects for which Boardwalk Pipelines has executed precedent agreements, it regularly considers other potential growth projects at earlier stages of development, and is currently evaluating additional growth projects involving substantial capital commitments. Boardwalk Pipelines may from time to time make public disclosures regarding these potential projects, for instance, through announcements of open seasons for potential future capacity. In addition to the risks, uncertainties and contingencies described above regarding the growth projects for which Boardwalk Pipelines has executed precedent agreements, these potential growth projects at earlier stages of development are subject to a variety of additional risks and uncertainties as Boardwalk Pipelines has not reached final investment decisions or secured executed precedent agreements for them. Therefore, these potential growth projects at earlier stages of development may not be consummated as contemplated in any such public disclosures or at all.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.