Commercial Airplanes

Segment Results of Operations and Financial Condition

Commercial Airplanes

(Dollars in millions)Nine months ended September 30Three months ended September 30
2024202320242023
Revenues$18,099$23,420$7,443$7,876
Loss from operations($5,879)($1,676)($4,021)($678)
Operating margins(32.5)%(7.2)%(54.0)%(8.6)%

BCA revenues decreased by $5,321 million for the nine months ended September 30, 2024, compared with the same period in 2023 driven by lower deliveries across all programs and 737-9 customer considerations related to the January 2024 grounding. BCA revenues decreased by $433 million for the three months ended September 30, 2024, compared with the same period in 2023 driven by lower 777 and 787 deliveries, partially offset by higher 737 deliveries.

Commercial airplane deliveries, including intercompany deliveries, were as follows:

737*747767*777787Total
Deliveries during the first nine months of 2024229(4)15(7)1136291
Deliveries during the first nine months of 2023286(6)117(6)1750371
Deliveries during the third quarter of 202492(2)6(2)414116
Deliveries during the third quarter of 202370(1)8(5)819105
Cumulative deliveries as of 9/30/20248,7571,5731,3181,7381,146
Cumulative deliveries as of 12/31/20238,5281,5731,3031,7271,110
  • Intercompany deliveries identified by parentheses.

Loss From Operations

BCA loss from operations was $5,879 million for the nine months ended September 30, 2024, compared with $1,676 million in the same period in 2023 reflecting reach-forward losses on 777X and 767, lower deliveries, lower margins driven by production disruption including the IAM 751 work stoppage, 737-9 customer considerations related to the January 2024 grounding and higher research and development expense, partially offset by lower abnormal production costs. BCA loss from operations was $4,021 million for the three months ended September 30, 2024, compared with $678 million in the same period in 2023 reflecting reach-forward losses on 777X and 767, lower margins driven by production disruption including the IAM 751 work stoppage, and higher research and development expense, partially offset by lower abnormal production costs.

Backlog

Our total backlog represents the estimated transaction prices on unsatisfied and partially satisfied performance obligations to our customers where we believe it is probable that we will collect the consideration due and where no contingencies remain before we and the customer are required to perform. Backlog does not include prospective orders where customer-controlled contingencies remain, such as the customer receiving approval from its board of directors, shareholders or government or completing financing arrangements. All such contingencies must be satisfied or have expired prior to recording a new firm order even if satisfying such conditions is highly probable. Backlog excludes options and customer financing orders as well as orders where customers have the unilateral right to terminate. A number of our customers may have contractual remedies, including rights to reject individual airplane deliveries if the actual delivery date is significantly later than the contractual delivery date. We address customer claims and requests for other contractual relief as they arise. The value of orders in backlog is adjusted as changes to price and schedule are agreed to with customers and is reported in accordance with the requirements of Accounting Standards Codification (ASC) 606.

BCA total backlog decreased from $440,507 million as of December 31, 2023, to $427,733 million at September 30, 2024, reflecting an increase in the value of existing orders that, in our assessment, do not meet the accounting requirements of ASC 606 for inclusion in backlog and cancellations, partially offset by new orders in excess of deliveries. Aircraft order cancellations during the nine months ended September 30, 2024, totaled $2,692 million and primarily relate to 737 aircraft. Net ASC 606 adjustments during the nine months ended September 30, 2024, totaled $15,642 million and primarily related to 777X and 737 aircraft. ASC 606 adjustments include consideration of aircraft orders where a customer-controlled contingency may exist, as well as an assessment of whether the customer is committed to perform, impacts of geopolitical events or related sanctions, or whether it is probable that the customer will pay the full amount of consideration when it is due. We may experience reductions to backlog and/or significant order cancellations due to various factors including delivery delays, production disruptions and delays to entry into service of the 777X, 737-7 and/or 737-10.

Accounting Quantity

The following table provides details of the accounting quantities and firm orders by program. Cumulative firm orders represent the cumulative number of commercial jet aircraft deliveries plus undelivered firm orders. Firm orders include certain military derivative aircraft that are not included in program accounting quantities. All revenues and costs associated with military derivative aircraft production are reported in the BDS segment.

Program
As of 9/30/2024737767777†777X787†
Program accounting quantities11,6001,2701,8105001,700
Undelivered units under firm orders4,151*8963(2)396711(8)
Cumulative firm orders12,9081,4071,8013961,857
As of 12/31/2023737767777777X787†
Program accounting quantities11,6001,2791,7905001,700
Undelivered units under firm orders4,33210448416726(8)
Cumulative firm orders12,8601,4071,7754161,836

† Customer financing aircraft orders are identified in parentheses.

*Approximate undelivered orders by minor model: 737-7 (7%), 737-8 (65%), 737-9 (5%) and 737-10 (23%).

Program Highlights

737 Program On January 10, 2024, the FAA notified Boeing that it had initiated an investigation into the 737 quality control system (737-9 Production Audit). This was followed by the FAA announcing actions to increase its oversight of Boeing, including conducting:

  1. An audit involving the 737-9 production line and its suppliers to evaluate Boeing’s compliance with approved quality procedures,

  2. Increased monitoring of Boeing’s 737-9 in-service events, and

  3. An assessment of safety risks around delegated authority and quality oversight, and examination of options to move these functions under independent third parties.

On January 24, 2024, the FAA stated it will not approve production rate increases or additional production lines for the 737 MAX until it is satisfied that Boeing is in full compliance with required quality control procedures.

The FAA communicated its findings from the 737-9 Production Audit of Boeing and Spirit AeroSystems Holdings, Inc. (Spirit) on February 28, 2024. The FAA found multiple instances where the companies failed to comply with manufacturing quality control requirements and provided 90 days from March 1, 2024, to submit a corrective action plan. On May 30, 2024, we submitted our safety and quality plan to address the issues identified by the FAA.

Our planned production rates are dependent on our suppliers' ability to support our operations and our ability to meet heightened quality control requirements. Prior to the Alaska Airlines accident, we were operating at a production rate of 38 per month. During the nine months ended September 30, 2024, as part of our plan to address the issues identified, we slowed production rates and delayed planned production rate increases to reduce traveled work in our factory, as well as at our suppliers. During the first quarter of 2024, we began conducting fuselage inspections at Spirit to improve quality prior to shipment to Boeing. In the second quarter of 2024, production rates gradually increased as we implemented new processes as part of our safety and quality plan. In the third quarter of 2024, we continued to gradually increase production aligned with our safety and quality plan. However, production has been paused since September 13, 2024, as a result of the ongoing work stoppage initiated by IAM 751. Prior to the work stoppage, we were working toward a production rate of 38 per month by the end of 2024, which we now expect to be delayed by the work stoppage.

As of September 30, 2024, we had approximately 60 737-8 aircraft in inventory that were produced prior to 2023, including approximately 45 aircraft for customers in China. Deliveries are being impacted by the work stoppage.

We are following the lead of the FAA as we work through the certification process of the 737-7 and 737-10 models. During the first quarter of 2024, the program completed the first phase of FAA certification flight testing for the 737-10. As of September 30, 2024, we had approximately 35 737-7 and 737-10 aircraft in inventory. We are planning to incorporate engineering solutions to the anti-icing systems on the 737-7 and 737-10 prior to certification, which has delayed certification and first deliveries.

See further discussion of the 737 MAX in Note 10 and Note 18 to our Condensed Consolidated Financial Statements.

767 Program The 767 assembly line includes the commercial program and a derivative to support the KC-46A Tanker program. We are currently at a production rate of approximately 3 aircraft per month. We are continuing to experience factory disruption, including supply chain delays and quality issues. We have slowed production in 2024 to reduce traveled work in our factory and enable supply chain recovery, resulting in higher near-term production costs.

We expect to end production of the 767 freighter program in 2027. As a result of this decision, the accounting quantity for the 767 program was decreased by 9 units during the three months ended September 30, 2024. Impacts of this decision, as well as the ongoing IAM 751 work stoppage and contract negotiations, and higher costs driven by ongoing factory disruption resulted in a $0.4 billion reach-forward loss on the 767 freighter program in the third quarter of 2024.

See further discussion of the KC-46A Tanker program in Note 10 to our Condensed Consolidated Financial Statements.

777 and 777X Programs The accounting quantity for the 777 program increased by 20 units during the three months ended September 30, 2024, due to the program's normal progress of obtaining additional orders and delivering airplanes. While production is currently paused, prior to the work stoppage, we were at a combined production rate of 4 per month for the 777/777X programs. Prior to the work stoppage, the programs experienced factory disruption including 777 supply chain delays and quality issues, and challenges associated with 777X production. In July 2024, we obtained approval from the FAA to begin the first phase of FAA certification flight testing. Flight testing was paused in August when a cracked engine thrust link was discovered in a flight test aircraft and remained paused as of September 30, 2024. The flight test aircraft were subsequently approved for flight; however, the resumption of flight activities will be impacted by the work stoppage.

Based on flight test delays and our latest assessment of certification timelines, we now anticipate the first delivery of the 777-9 to occur in 2026 and the 777-8 freighter to occur in 2028. First delivery of the 777-8 passenger aircraft is not expected to occur before 2030. In addition, we are slowing the rate ramp of 777X to address production challenges, which is leading to higher production costs and further customer delivery delays. As a result of these changes, as well as higher estimated labor and supplier costs, we recorded a $2.6 billion reach-forward loss on the 777X program in the third quarter of 2024.

We are following the lead of the FAA as we work through the certification process and the ultimate timing will be determined by the regulators.

The level of profitability on the 777X program will be subject to a number of factors. These factors include aircraft certification requirements and timing, change incorporation on completed aircraft, production disruption due to labor instability (including the ongoing work stoppage) and supply chain disruption, customer delivery timing and negotiations, further production rate adjustments for the 777X or other commercial aircraft programs, and contraction of the accounting quantity. One or more of these factors could result in additional reach-forward losses in future periods.

787 Program During the first quarter of 2024, we disclosed that we were slowing near-term production to below 5 per month due to supply chain constraints. The program continues to experience supply chain constraints and production issues. Delays associated with business class seats are also adversely impacting 2024 deliveries. As of September 30, 2024, we had approximately 30 aircraft in inventory that were produced prior to 2023 and required rework. This required rework is currently paused as a result of the IAM 751 work stoppage. The inspections and rework costs on inventoried aircraft are accounted for as abnormal production costs, and we expensed $209 million in the nine months ended September 30, 2024.

On June 30, 2024, we entered into an agreement to acquire Spirit. See Note 2 to our Condensed Consolidated Financial Statements.